Re pm w/ret req ty i (y)6"(sld)(090MIL) unit price, Texas
Low bidders on TxDOT contracts carried a median of $0.79 per LF for item 6666320007, re pm w/ret req ty i (y)6"(sld)(090mil), from 06 AUG 2020 to 02 AUG 2024, across 150 low bids. Half of all 470 bids fell between $0.65 and $1.16.
- Owner
- Texas DOT
- Item
- 6666320007
- Unit
- LF
- Latest letting
- 02 AUG 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 2 | 2 | $0.45 | 10 | $0.46 |
| 2021 | 5 | 5 | $0.41 | 19 | $0.51 |
| 2022 | 4 | 4 | $0.52 | 12 | $0.56 |
| 2023 | 64 | 64 | $0.75 | 181 | $0.76 |
| 2024 | 75 | 75 | $0.83 | 248 | $0.88 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Beaumont District | 40 | $0.80 | 106 | $0.80 |
| Paris District | 18 | $0.73 | 70 | $0.95 |
| Corpus Christi District | 15 | $0.75 | 53 | $0.72 |
| El Paso District | 19 | $1.10 | 40 | $1.10 |
| Lufkin District | 15 | $0.75 | 36 | $0.75 |
| Bryan District | 7 | $1.00 | 35 | $1.16 |
| Amarillo District | 7 | $1.10 | 24 | $1.03 |
| Austin District | 7 | $0.89 | 23 | $1.05 |
| Yoakum District | 5 | $0.79 | 18 | $1.05 |
| Dallas District | 3 | $0.66 | 12 | $0.78 |
| San Angelo District | 3 | $0.72 | 11 | $0.72 |
| Wichita Falls District | 3 | $0.72 | 8 | $0.32 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 80 to 6,332 | 37 | $1.37 |
| 6,454 to 23,588 | 38 | $0.85 |
| 23,940 to 63,590 | 37 | $0.75 |
| 64,078 to 2,302,670 | 38 | $0.66 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 02 AUG 2024 | 08243203 | San Angelo District | 395,860 | $0.72 | $0.72 | $0.65 | 5 | RK HALL, LLC | TxDOT |
| 10 JUL 2024 | 07243207 | Dallas District | 12,164 | $1.23 | $1.26 | $1.00 | 6 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
| 10 JUL 2024 | 07243212 | Bryan District | 21,662 | $1.00 | $1.00 | $0.80 | 5 | LARRY YOUNG PAVING, INC. | TxDOT |
| 10 JUL 2024 | 07243213 | Lufkin District | 44,365 | $0.77 | $1.39 | $0.75 | 2 | PINTO CONSTRUCTION CO., INC. | TxDOT |
| 10 JUL 2024 | 07243214 | Beaumont District | 51,192 | $0.85 | $0.87 | $0.61 | 3 | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. | TxDOT |
| 10 JUL 2024 | 07243228 | Paris District | 2,632 | $1.50 | $1.91 | $2.00 | 6 | L & N BRIDGE, LLC | TxDOT |
| 09 JUL 2024 | 07243002 | El Paso District | 17,930 | $0.79 | $0.88 | $1.20 | 2 | SUNDT CONSTRUCTION, INC. | TxDOT |
| 09 JUL 2024 | 07243010 | Beaumont District | 80 | $1.38 | $1.25 | $1.00 | 3 | TEXAS MATERIALS GROUP, INC. | TxDOT |
| 09 JUL 2024 | 07243020 | Beaumont District | 2,677 | $0.97 | $1.00 | $0.54 | 3 | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. | TxDOT |
| 09 JUL 2024 | 07243031 | Amarillo District | 31,885 | $0.77 | $0.77 | $0.65 | 5 | L A FULLER & SONS CONSTRUCTION, LTD. | TxDOT |
| 06 JUN 2024 | 06243217 | Lufkin District | 119,939 | $0.78 | $0.77 | $0.75 | 2 | TEXAS MATERIALS GROUP, INC. | TxDOT |
| 06 JUN 2024 | 06243219 | Paris District | 144,201 | $0.55 | $0.62 | $0.72 | 4 | OVERLAND CORPORATION | TxDOT |
| 06 JUN 2024 | 06243233 | Lufkin District | 16,419 | $1.09 | $0.92 | $0.75 | 2 | PINTO CONSTRUCTION CO., INC. | TxDOT |
| 06 JUN 2024 | 06243239 | El Paso District | 3,698 | $1.20 | $1.17 | $1.14 | 2 | TRI STATE ELECTRIC, LTD. | TxDOT |
| 06 JUN 2024 | 06243243 | Bryan District | 6,454 | $1.50 | $1.41 | $1.00 | 4 | BRAZOS PAVING, INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.