Refl pav mrk ty i (w)18"(sld)(100MIL) unit price, Texas
Low bidders on TxDOT contracts carried a median of $5.00 per LF for item 6666045007, refl pav mrk ty i (w)18"(sld)(100mil), from 10 JAN 2020 to 09 JUL 2024, across 44 low bids. Half of all 190 bids fell between $4.75 and $6.50.
- Owner
- Texas DOT
- Item
- 6666045007
- Unit
- LF
- Latest letting
- 09 JUL 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 6 | 6 | $5.00 | 29 | $5.20 |
| 2021 | 16 | 16 | $5.00 | 75 | $5.00 |
| 2022 | 10 | 10 | $5.62 | 44 | $6.00 |
| 2023 | 7 | 7 | $5.50 | 26 | $5.50 |
| 2024 | 5 | 5 | $5.50 | 16 | $5.50 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Tyler District | 19 | $5.00 | 79 | $5.00 |
| San Antonio District | 12 | $6.47 | 57 | $7.25 |
| Dallas District | 3 | $5.25 | 17 | $5.30 |
| Fort Worth District | 4 | $6.40 | 15 | $6.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 40 to 80 | 11 | $10.00 |
| 88 to 164 | 11 | $5.00 |
| 172 to 500 | 11 | $5.00 |
| 609 to 3,086 | 11 | $5.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 09 JUL 2024 | 07243001 | Fort Worth District | 320 | $3.57 | $3.54 | $6.50 | 2 | ZACHRY CONSTRUCTION CORPORATION | TxDOT |
| 06 JUN 2024 | 06243238 | Fort Worth District | 152 | $5.50 | $6.50 | $6.00 | 4 | RAGLE CONSTRUCTION, INC. | TxDOT |
| 02 MAY 2024 | 05243035 | Odessa District | 193 | $4.88 | $8.44 | $6.00 | 2 | TI-ZACK CONCRETE, LLC | TxDOT |
| 04 APR 2024 | 04243039 | Tyler District | 303 | $8.75 | $5.88 | $4.00 | 4 | STRIPE-A-ZONE, LLC | TxDOT |
| 05 JAN 2024 | 01243219 | Tyler District | 172 | $6.60 | $5.25 | $5.50 | 4 | LONGVIEW BRIDGE AND ROAD, LTD. | TxDOT |
| 06 DEC 2023 | 12233202 | Tyler District | 718 | $5.00 | $5.00 | $5.93 | 5 | RONALD R. WAGNER & CO., LP | TxDOT |
| 03 AUG 2023 | 08233252 | Fort Worth District | 45 | $10.00 | $2.73 | $8.00 | 3 | FNH CONSTRUCTION, LLC | TxDOT |
| 03 AUG 2023 | 08233274 | Tyler District | 152 | $5.50 | $5.50 | $5.25 | 3 | EAST TEXAS BRIDGE, INC. | TxDOT |
| 02 AUG 2023 | 08233002 | San Antonio District | 140 | $5.70 | $4.85 | $5.35 | 2 | JORDAN FOSTER CONSTRUCTION, LLC | TxDOT |
| 02 AUG 2023 | 08233010 | Fort Worth District | 173 | $7.30 | $6.75 | $5.25 | 6 | JAGOE-PUBLIC COMPANY | TxDOT |
| 05 MAY 2023 | 05233229 | Tyler District | 398 | $5.00 | $7.50 | $4.00 | 4 | INTERSTATE BARRICADES & MARKINGS, INC. | TxDOT |
| 04 MAY 2023 | 05234015 | El Paso District | 500 | $3.00 | $4.00 | $1.80 | 3 | MIJELUM, L.L.C. | TxDOT |
| 02 DEC 2022 | 12223201 | Dallas District | 139 | $5.00 | $5.28 | $5.25 | 9 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
| 02 DEC 2022 | 12223203 | Tyler District | 654 | $4.00 | $4.50 | $4.00 | 2 | CLARK CONSTRUCTION OF TEXAS, INC. | TxDOT |
| 08 SEP 2022 | 09223218 | Tyler District | 126 | $5.00 | $5.38 | $4.00 | 4 | MADDEN CONTRACTING COMPANY, LLC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.