Refl pav mrk ty i(y)(med nose)(100MIL) unit price, Texas
Low bidders on TxDOT contracts carried a median of $350.00 per EACH for item 6666156007, refl pav mrk ty i(y)(med nose)(100mil), from 09 JAN 2020 to 06 JUN 2024, across 105 low bids. Half of all 453 bids fell between $300.00 and $450.00.
- Owner
- Texas DOT
- Item
- 6666156007
- Unit
- EACH
- Latest letting
- 06 JUN 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 15 | 15 | $322.00 | 94 | $335.57 |
| 2021 | 29 | 29 | $381.84 | 139 | $350.00 |
| 2022 | 24 | 24 | $500.00 | 96 | $450.00 |
| 2023 | 24 | 24 | $282.78 | 73 | $320.00 |
| 2024 | 13 | 13 | $360.00 | 51 | $385.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| San Antonio District | 55 | $377.00 | 265 | $370.00 |
| Austin District | 17 | $350.00 | 72 | $351.41 |
| Houston District | 13 | $200.00 | 51 | $250.00 |
| Lubbock District | 7 | $560.00 | 19 | $550.00 |
| Odessa District | 4 | $415.00 | 10 | $435.60 |
| El Paso District | 3 | $325.00 | 9 | $350.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 26 | $421.50 |
| 1 to 2 | 26 | $350.00 |
| 2 to 6 | 26 | $368.51 |
| 6 to 33.25 | 27 | $308.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 06 JUN 2024 | 06243202 | Houston District | 1 | $315.00 | $320.00 | $150.00 | 3 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
| 06 JUN 2024 | 06243207 | Odessa District | 1 | $330.00 | $350.60 | $565.26 | 4 | JONES BROS. DIRT & PAVING CONTRACTORS, INC. | TxDOT |
| 02 MAY 2024 | 05243032 | San Antonio District | 1 | $450.00 | $510.00 | $400.00 | 4 | E-Z BEL CONSTRUCTION, LLC | TxDOT |
| 05 APR 2024 | 04243208 | San Antonio District | 2 | $350.00 | $365.00 | $321.58 | 6 | ENCINO LANDSCAPE, INC. | TxDOT |
| 04 APR 2024 | 04243041 | Lubbock District | 2 | $560.00 | $555.00 | $650.00 | 4 | A. L. HELMCAMP, INC. | TxDOT |
| 06 MAR 2024 | 03243203 | Lubbock District | 10 | $360.00 | $400.00 | $500.00 | 2 | DUININCK, INC. | TxDOT |
| 05 MAR 2024 | 03243032 | Lubbock District | 12 | $500.00 | $500.00 | $900.00 | 3 | L&L COMPANY | TxDOT |
| 02 FEB 2024 | 02243205 | San Antonio District | 6 | $310.00 | $320.00 | $380.00 | 9 | DAN WILLIAMS COMPANY | TxDOT |
| 01 FEB 2024 | 02243014 | Austin District | 2 | $650.00 | $457.50 | $296.65 | 4 | CLARK CONSTRUCTION OF TEXAS, INC. | TxDOT |
| 01 FEB 2024 | 02243025 | Austin District | 1 | $525.00 | $450.00 | $230.00 | 3 | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. | TxDOT |
| 01 FEB 2024 | 02243031 | San Antonio District | 1 | $350.00 | $350.00 | $400.00 | 3 | E-Z BEL CONSTRUCTION, LLC | TxDOT |
| 05 JAN 2024 | 01243203 | San Antonio District | 4 | $175.00 | $175.00 | $395.70 | 3 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 05 JAN 2024 | 01243231 | Odessa District | 2 | $565.26 | $565.26 | $300.00 | 3 | REECE ALBERT, INC. | TxDOT |
| 05 DEC 2023 | 12233030 | Houston District | 10 | $140.00 | $219.46 | $292.47 | 2 | GARRET SHIELDS INFRASTRUCTURE | TxDOT |
| 02 NOV 2023 | 11233206 | Austin District | 1 | $340.00 | $330.00 | $300.00 | 6 | ALLEN KELLER COMPANY | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.