Refl pav mrk ty ii (w) 12" (sld) unit price, Texas
Low bidders on TxDOT contracts carried a median of $1.75 per LF for item 6666180007, refl pav mrk ty ii (w) 12" (sld), from 09 JAN 2020 to 10 JUL 2024, across 168 low bids. Half of all 624 bids fell between $1.20 and $2.50.
- Owner
- Texas DOT
- Item
- 6666180007
- Unit
- LF
- Latest letting
- 10 JUL 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 38 | 38 | $1.50 | 162 | $1.52 |
| 2021 | 34 | 34 | $1.70 | 140 | $1.50 |
| 2022 | 34 | 34 | $1.75 | 122 | $2.00 |
| 2023 | 37 | 37 | $2.00 | 127 | $2.00 |
| 2024 | 25 | 25 | $2.05 | 73 | $2.25 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Austin District | 49 | $1.65 | 176 | $1.65 |
| Houston District | 29 | $1.50 | 107 | $1.60 |
| Dallas District | 16 | $1.93 | 74 | $2.00 |
| Fort Worth District | 17 | $2.00 | 70 | $2.00 |
| El Paso District | 19 | $1.85 | 61 | $1.85 |
| Pharr District | 6 | $0.94 | 24 | $0.90 |
| San Angelo District | 5 | $1.59 | 18 | $2.00 |
| San Antonio District | 3 | $2.00 | 14 | $1.52 |
| Tyler District | 3 | $2.00 | 11 | $2.00 |
| Corpus Christi District | 4 | $0.65 | 7 | $0.60 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 18 to 200 | 42 | $2.21 |
| 200 to 623 | 42 | $2.00 |
| 640 to 1,950 | 42 | $1.30 |
| 2,000 to 31,285 | 42 | $1.70 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 10 JUL 2024 | 07243227 | Fort Worth District | 120 | $2.00 | $2.50 | $2.15 | 2 | YUNEX LLC | TxDOT |
| 09 JUL 2024 | 07243001 | Fort Worth District | 6,863 | $0.61 | $0.60 | $3.00 | 2 | ZACHRY CONSTRUCTION CORPORATION | TxDOT |
| 09 JUL 2024 | 07243002 | El Paso District | 8,098 | $1.76 | $1.94 | $1.85 | 2 | SUNDT CONSTRUCTION, INC. | TxDOT |
| 09 JUL 2024 | 07243021 | Houston District | 547 | $1.15 | $1.98 | $1.59 | 4 | TRP INFRASTRUCTURE SERVICES, LLC | TxDOT |
| 09 JUL 2024 | 07243024 | Austin District | 101 | $2.05 | $2.16 | $2.66 | 6 | TEXAS MATERIALS GROUP, INC. | TxDOT |
| 06 JUN 2024 | 06243203 | Houston District | 216 | $1.05 | $1.30 | $2.30 | 2 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 06 JUN 2024 | 06243214 | San Antonio District | 48 | $2.69 | $1.65 | $1.50 | 5 | RELMCO, INC. | TxDOT |
| 06 JUN 2024 | 06243228 | Fort Worth District | 922 | $4.00 | $4.00 | $2.00 | 2 | RAGLE CONSTRUCTION, INC. | TxDOT |
| 05 JUN 2024 | 06243009 | Bryan District | 27 | $4.20 | $4.79 | $1.50 | 6 | KNIFE RIVER CORPORATION - SOUTH | TxDOT |
| 05 JUN 2024 | 06243025 | Dallas District | 74 | $3.00 | $3.00 | $5.50 | 3 | SELECT MAINTENANCE, L.L.C. | TxDOT |
| 03 MAY 2024 | 05243203 | El Paso District | 6,855 | $1.48 | $1.48 | $2.00 | 3 | SUNDT CONSTRUCTION, INC. | TxDOT |
| 02 MAY 2024 | 05243005 | Austin District | 183 | $2.40 | $4.20 | $4.00 | 2 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
| 04 APR 2024 | 04243001 | Dallas District | 4,094 | $1.73 | $2.39 | $3.50 | 2 | SEMA CONSTRUCTION, INC. | TxDOT |
| 06 MAR 2024 | 03243214 | Fort Worth District | 159 | $1.75 | $1.91 | $3.00 | 6 | GIBSON & ASSOCIATES, INC. | TxDOT |
| 05 MAR 2024 | 03243014 | Corpus Christi District | 505 | $1.00 | $1.00 | $7.00 | 1 | ANDERSON COLUMBIA CO., INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.