Remov rdsd flsh bcn am (solar pwrd) unit price, Texas
Low bidders on TxDOT contracts carried a median of $583.63 per EACH for item 6856006, remov rdsd flsh bcn am (solar pwrd), from 06 FEB 2020 to 10 JUL 2024, across 63 low bids. Half of all 260 bids fell between $393.73 and $933.72.
- Owner
- Texas DOT
- Item
- 6856006
- Unit
- EACH
- Latest letting
- 10 JUL 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 11 | 11 | $505.00 | 51 | $505.05 |
| 2021 | 18 | 18 | $559.14 | 85 | $530.00 |
| 2022 | 9 | 9 | $721.00 | 33 | $721.00 |
| 2023 | 16 | 16 | $610.49 | 59 | $600.00 |
| 2024 | 9 | 9 | $831.60 | 32 | $917.90 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Corpus Christi District | 12 | $621.62 | 71 | $550.00 |
| Austin District | 10 | $562.50 | 43 | $650.00 |
| Houston District | 7 | $265.00 | 37 | $262.02 |
| Odessa District | 7 | $550.00 | 26 | $596.87 |
| Yoakum District | 6 | $668.76 | 13 | $666.24 |
| Abilene District | 3 | $3,800.00 | 11 | $550.00 |
| Fort Worth District | 5 | $905.80 | 9 | $1,124.90 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 15 | $505.00 |
| 1 to 2 | 16 | $734.47 |
| 2 to 4 | 16 | $584.12 |
| 4 to 31 | 16 | $535.32 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 10 JUL 2024 | 07243227 | Fort Worth District | 1 | $905.80 | $1,202.90 | $868.90 | 2 | YUNEX LLC | TxDOT |
| 06 JUN 2024 | 06243246 | Corpus Christi District | 1 | $831.60 | $900.00 | $1,500.00 | 7 | CLARK CONSTRUCTION OF TEXAS, INC. | TxDOT |
| 03 MAY 2024 | 05243230 | Odessa District | 6 | $2,000.00 | $2,000.00 | $525.00 | 3 | WILLIS ELECTRIC CO., LP | TxDOT |
| 05 APR 2024 | 04243215 | Corpus Christi District | 31 | $750.00 | $505.11 | $750.00 | 5 | HIGHWAY BARRICADES AND SERVICES, LLC | TxDOT |
| 05 APR 2024 | 04243222 | Brownwood District | 1 | $80.00 | $1,058.75 | $1,700.00 | 3 | HJC FARMS, INC. | TxDOT |
| 05 MAR 2024 | 03243021 | Abilene District | 2 | $4,600.00 | $2,000.00 | $900.00 | 3 | GILVIN-TERRILL, LTD. | TxDOT |
| 01 FEB 2024 | 02243002 | Lubbock District | 4 | $1,000.00 | $917.50 | $550.00 | 2 | DUININCK, INC. | TxDOT |
| 01 FEB 2024 | 02243025 | Austin District | 1 | $500.00 | $700.00 | $1,100.00 | 3 | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. | TxDOT |
| 05 JAN 2024 | 01243229 | Yoakum District | 6 | $487.00 | $743.50 | $1,200.00 | 4 | TRAF-TEX, INC. | TxDOT |
| 05 DEC 2023 | 12233003 | Yoakum District | 3 | $400.00 | $595.00 | $1,200.00 | 4 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 05 DEC 2023 | 12233012 | Amarillo District | 4 | $1,050.00 | $1,157.50 | $1,200.00 | 4 | TI-ZACK CONCRETE, INC. | TxDOT |
| 02 NOV 2023 | 11233201 | Odessa District | 3 | $500.00 | $500.00 | $1,000.00 | 5 | SUNDT CONSTRUCTION, INC. | TxDOT |
| 03 AUG 2023 | 08233202 | Houston District | 8 | $583.63 | $580.00 | $300.00 | 5 | ZACHRY CONSTRUCTION CORPORATION | TxDOT |
| 03 AUG 2023 | 08233204 | Yoakum District | 10 | $865.00 | $865.00 | $600.00 | 1 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 03 AUG 2023 | 08233212 | Bryan District | 1 | $1,500.00 | $844.00 | $832.00 | 3 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.