Remov str (headwall) unit price, Texas

Low bidders on TxDOT contracts carried a median of $1,500.00 per EACH for item 496-7006, remov str (headwall), over the 24 months to 19 NOV 2026, across 139 low bids. Half of all 857 bids fell between $1,035.00 and $2,500.00.

Owner
Texas DOT
Item
496-7006
Unit
EACH
Latest letting
04 NOV 2026
$1,500.00Low bidder's median, per EACH
$1,731.78Median of all bids, per EACH
139Contracts in the window
$1,850.00Engineer's estimate, median per EACH

By year of letting

Remov str (headwall), TxDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202433$2,130.0016$2,350.00
20257575$1,340.00443$1,650.00
20266363$1,500.00410$1,800.00
Remov str (headwall), TxDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Remov str (headwall), TxDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Dallas District31$1,100.00203$1,627.00
San Antonio District13$1,603.9085$2,000.00
Austin District10$1,692.9982$1,986.38
Atlanta District9$500.0063$1,000.00
Houston District7$1,700.0056$2,000.00
Fort Worth District9$1,800.0055$2,000.00
Bryan District8$2,400.0053$2,000.00
Paris District7$1,000.0044$1,115.00
Wichita Falls District8$1,000.0042$1,050.00
Pharr District6$1,750.0029$2,200.00
Amarillo District5$1,632.6025$1,900.00
Corpus Christi District4$3,225.4622$2,395.00
Remov str (headwall), TxDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Remov str (headwall), TxDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 234$1,500.00
2 to 335$2,000.00
3 to 835$1,100.00
9 to 5935$1,100.00
Remov str (headwall), TxDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest TxDOT contracts carrying Remov str (headwall)
LetContractDistrictQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
04 NOV 2026A00193521Corpus Christi District2$3,586.00$2,500.00$5,000.005J E CONSTRUCTION SERVICES, LLCTxDOT
04 NOV 2026A00124162Bryan District2$3,840.00$3,082.50n/a12FLUOR ENTERPRISES, INC.TxDOT
04 NOV 2026A00206631Bryan District3$1,500.00$1,500.00n/a7BIG CREEK CONSTRUCTION, LTD.TxDOT
04 NOV 2026A00196925Paris District1$500.00$1,000.00$1,300.009HIGHWAY 19 CONSTRUCTION LLCTxDOT
04 NOV 2026A00129572Dallas District19$1,500.00$1,575.00$1,650.004MARIO SINACOLA & SONS EXCAVATING, INC.TxDOT
03 NOV 2026A00184974Austin District2$3,000.00$4,000.00n/a6AUSTIN BRIDGE & ROAD SERVICES, LPTxDOT
13 OCT 2026A00223040Tyler District2$3,000.00$1,500.00$2,500.007ICOS MANAGEMENT, LLCTxDOT
07 OCT 2026A00064192San Antonio District20$2,578.87$2,789.43$1,685.008HUNTER INDUSTRIES, LTD.TxDOT
06 OCT 2026A00186301Waco District1$1,500.00$1,562.50$1,126.256BIG CREEK CONSTRUCTION, LTD.TxDOT
06 OCT 2026A00066946Dallas District17$800.00$1,200.00$1,250.008A. K. GILLIS & SONS, LLCTxDOT
02 SEP 2026A00206056Wichita Falls District2$1,500.00$2,003.00$1,500.007TIGHT LINE CONSTRUCTION, LLCTxDOT
11 AUG 2026A00221935Odessa District3$1,950.00$4,875.00$1,300.002SCOTT TUCKER CONSTRUCTION COMPANY, LLCTxDOT
06 AUG 2026A00193144Austin District1$2,207.58$2,500.00$2,500.007HUNTER INDUSTRIES, LTD.TxDOT
06 AUG 2026A00189724Laredo District2$1,400.00$1,000.00$2,000.003ANDERSON COLUMBIA CO., INC.TxDOT
06 AUG 2026A00196275Atlanta District10$1,000.00$750.00$1,000.005MADDEN CONTRACTING COMPANY, LLC.TxDOT
Latest TxDOT contracts carrying Remov str (headwall)

Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.

How these prices were read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy