Remove cable barrier terminal section unit price, Texas
Low bidders on TxDOT contracts carried a median of $500.00 per EACH for item 5436022, remove cable barrier terminal section, from 10 JAN 2020 to 02 AUG 2024, across 45 low bids. Half of all 167 bids fell between $400.00 and $861.85.
- Owner
- Texas DOT
- Item
- 5436022
- Unit
- EACH
- Latest letting
- 02 AUG 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 5 | 5 | $465.00 | 26 | $489.50 |
| 2021 | 10 | 10 | $499.11 | 42 | $499.11 |
| 2022 | 6 | 6 | $460.00 | 17 | $500.00 |
| 2023 | 12 | 12 | $706.12 | 40 | $706.12 |
| 2024 | 12 | 12 | $525.00 | 42 | $546.50 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| San Antonio District | 4 | $393.50 | 22 | $470.00 |
| Amarillo District | 4 | $705.00 | 16 | $1,277.78 |
| Fort Worth District | 3 | $465.00 | 15 | $650.00 |
| Atlanta District | 4 | $625.00 | 14 | $525.00 |
| Pharr District | 3 | $225.00 | 13 | $426.34 |
| El Paso District | 4 | $422.50 | 11 | $490.00 |
| Yoakum District | 3 | $386.56 | 9 | $438.00 |
| Odessa District | 3 | $700.00 | 9 | $525.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 11 | $577.50 |
| 2 to 4 | 11 | $450.00 |
| 4 to 14 | 11 | $550.00 |
| 14 to 80 | 12 | $370.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 02 AUG 2024 | 08243201 | Pharr District | 10 | $200.00 | $386.96 | $400.00 | 3 | FOREMOST PAVING, INC. | TxDOT |
| 01 AUG 2024 | 08243002 | Pharr District | 8 | $740.00 | $543.00 | $400.00 | 5 | FOREMOST PAVING, INC. | TxDOT |
| 10 JUL 2024 | 07243212 | Bryan District | 5 | $550.00 | $550.00 | $800.00 | 5 | LARRY YOUNG PAVING, INC. | TxDOT |
| 09 JUL 2024 | 07243001 | Fort Worth District | 5 | $500.00 | $681.00 | $700.00 | 2 | ZACHRY CONSTRUCTION CORPORATION | TxDOT |
| 09 JUL 2024 | 07243002 | El Paso District | 4 | $575.00 | $541.31 | $815.00 | 2 | SUNDT CONSTRUCTION, INC. | TxDOT |
| 03 MAY 2024 | 05243201 | Yoakum District | 22 | $386.56 | $438.00 | $800.00 | 3 | PULICE CONSTRUCTION, INC. | TxDOT |
| 03 MAY 2024 | 05243203 | El Paso District | 16 | $570.00 | $812.18 | $600.00 | 3 | SUNDT CONSTRUCTION, INC. | TxDOT |
| 05 APR 2024 | 04243202 | Wichita Falls District | 15 | $375.00 | $411.14 | $1,200.00 | 2 | AUSTIN BRIDGE & ROAD SERVICES, LP ZACHRY CONSTRUCTION CORPORATION | TxDOT |
| 04 APR 2024 | 04243005 | Lubbock District | 4 | $500.00 | $1,250.00 | $1,000.00 | 4 | GRATIOT CONSTRUCTION, LTD. | TxDOT |
| 05 MAR 2024 | 03243010 | Amarillo District | 1 | $3,518.66 | $2,500.00 | $500.00 | 4 | ALTUS CONSTRUCTION LLC | TxDOT |
| 02 FEB 2024 | 02243202 | Houston District | 21 | $365.00 | $441.06 | $250.00 | 8 | BRICE CONSTRUCTION AND DESIGN LLC | TxDOT |
| 01 FEB 2024 | 02243044 | Amarillo District | 18 | $560.00 | $560.00 | $613.00 | 1 | WEBBER, LLC | TxDOT |
| 05 DEC 2023 | 12233002 | Yoakum District | 1 | $636.00 | $636.00 | $500.00 | 1 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 05 DEC 2023 | 12233007 | Amarillo District | 6 | $850.00 | $1,650.00 | $500.00 | 5 | BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC | TxDOT |
| 05 DEC 2023 | 12233028 | Pharr District | 3 | $225.00 | $426.34 | $550.00 | 5 | POSILLICO CIVIL, INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way