Remove str (rail) unit price, Texas
Low bidders on TxDOT contracts carried a median of $30.00 per LF for item 4966099, remove str (rail), from 09 JAN 2020 to 06 JUN 2024, across 81 low bids. Half of all 387 bids fell between $15.00 and $53.25.
- Owner
- Texas DOT
- Item
- 4966099
- Unit
- LF
- Latest letting
- 06 JUN 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 18 | 17 | $26.56 | 97 | $30.00 |
| 2021 | 23 | 21 | $25.00 | 122 | $29.00 |
| 2022 | 14 | 14 | $27.50 | 59 | $30.00 |
| 2023 | 20 | 20 | $35.30 | 77 | $40.03 |
| 2024 | 9 | 9 | $40.00 | 32 | $47.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Abilene District | 10 | $27.50 | 48 | $29.00 |
| San Antonio District | 10 | $34.58 | 44 | $30.70 |
| Corpus Christi District | 6 | $45.50 | 31 | $40.03 |
| Fort Worth District | 4 | $18.00 | 30 | $22.50 |
| Tyler District | 4 | $31.50 | 26 | $39.00 |
| Childress District | 3 | $10.00 | 24 | $57.00 |
| Houston District | 7 | $19.25 | 23 | $26.00 |
| Wichita Falls District | 4 | $31.50 | 21 | $30.00 |
| Austin District | 4 | $19.94 | 20 | $26.11 |
| Dallas District | 4 | $30.00 | 15 | $50.00 |
| Waco District | 3 | $50.00 | 13 | $25.00 |
| Bryan District | 3 | $37.81 | 13 | $25.29 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 6 to 82 | 20 | $37.71 |
| 100 to 209 | 20 | $27.75 |
| 216 to 562.30 | 20 | $28.28 |
| 576 to 2,074 | 21 | $28.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 06 JUN 2024 | 06243201 | San Antonio District | 830.40 | $31.54 | $136.00 | $36.00 | 5 | WEBBER, LLC | TxDOT |
| 06 JUN 2024 | 06243202 | Houston District | 122 | $10.00 | $10.00 | $8.00 | 3 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
| 06 JUN 2024 | 06243237 | Abilene District | 342 | $43.80 | $43.80 | $60.00 | 5 | TALBERT COMPANIES LLC | TxDOT |
| 03 MAY 2024 | 05243233 | Wichita Falls District | 135 | $30.00 | $37.00 | $22.00 | 4 | 3LW CIVIL LLC | TxDOT |
| 03 MAY 2024 | 05243246 | Houston District | 30 | $20.00 | $23.00 | $100.00 | 4 | GARRET SHIELDS INFRASTRUCTURE | TxDOT |
| 04 APR 2024 | 04243002 | Corpus Christi District | 278 | $190.00 | $113.00 | $110.00 | 3 | BAY LTD. | TxDOT |
| 06 MAR 2024 | 03243220 | Waco District | 150.80 | $65.00 | $42.50 | $25.00 | 4 | AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC | TxDOT |
| 05 JAN 2024 | 01243208 | El Paso District | 1,156 | $40.00 | $40.00 | $38.00 | 1 | DAN WILLIAMS COMPANY | TxDOT |
| 04 JAN 2024 | 01243024 | Odessa District | 780 | $50.00 | $50.00 | $50.00 | 3 | DELGADO'S CONTRACTORS, LLC | TxDOT |
| 06 DEC 2023 | 12233201 | Yoakum District | 618 | $25.00 | $69.82 | $30.00 | 3 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. | TxDOT |
| 01 NOV 2023 | 11233007 | Dallas District | 606 | $50.00 | $100.00 | $40.00 | 5 | RAGLE CONSTRUCTION, INC. | TxDOT |
| 01 NOV 2023 | 11233028 | San Antonio District | 6 | $114.37 | $119.00 | $110.00 | 3 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 03 AUG 2023 | 08233210 | Pharr District | 209 | $20.00 | $23.75 | $24.56 | 4 | FOREMOST PAVING, INC. | TxDOT |
| 03 AUG 2023 | 08233273 | Dallas District | 75 | $60.00 | $60.00 | $35.00 | 1 | DURABLE SPECIALTIES, INC. | TxDOT |
| 02 AUG 2023 | 08233002 | San Antonio District | 1,075 | $7.95 | $11.14 | $25.00 | 2 | JORDAN FOSTER CONSTRUCTION, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.