Removing conc (misc) unit price, Texas
Low bidders on TxDOT contracts carried a median of $31.50 per SY for item 1046028, removing conc (misc), from 06 FEB 2020 to 10 JUL 2024, across 133 low bids. Half of all 577 bids fell between $20.00 and $84.50.
- Owner
- Texas DOT
- Item
- 1046028
- Unit
- SY
- Latest letting
- 10 JUL 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 26 | 26 | $28.09 | 146 | $38.00 |
| 2021 | 35 | 35 | $32.00 | 169 | $35.00 |
| 2022 | 20 | 20 | $27.50 | 68 | $28.74 |
| 2023 | 29 | 28 | $32.25 | 107 | $38.90 |
| 2024 | 24 | 24 | $45.60 | 87 | $40.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| San Antonio District | 12 | $35.14 | 76 | $40.00 |
| Houston District | 11 | $9.00 | 64 | $15.50 |
| Austin District | 11 | $41.00 | 51 | $28.00 |
| Dallas District | 12 | $22.50 | 51 | $25.60 |
| Tyler District | 10 | $75.00 | 47 | $50.00 |
| El Paso District | 10 | $21.00 | 40 | $32.25 |
| Paris District | 6 | $29.00 | 30 | $75.00 |
| Fort Worth District | 9 | $56.34 | 24 | $53.17 |
| Yoakum District | 5 | $20.00 | 20 | $32.20 |
| Laredo District | 6 | $48.74 | 19 | $70.00 |
| Lubbock District | 7 | $30.00 | 17 | $30.00 |
| Wichita Falls District | 5 | $46.20 | 17 | $29.14 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 1 to 15.50 | 33 | $100.00 |
| 18 to 50 | 33 | $39.00 |
| 50 to 204 | 33 | $30.00 |
| 241 to 30,843 | 34 | $18.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 10 JUL 2024 | 07243227 | Fort Worth District | 6 | $83.90 | $136.95 | $65.00 | 2 | YUNEX LLC | TxDOT |
| 06 JUN 2024 | 06243202 | Houston District | 2,279 | $5.00 | $5.00 | $30.00 | 3 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
| 06 JUN 2024 | 06243226 | Amarillo District | 1,148 | $25.02 | $25.01 | $35.00 | 4 | TI-ZACK CONCRETE, LLC | TxDOT |
| 05 JUN 2024 | 06243014 | Amarillo District | 32 | $28.50 | $28.50 | $50.00 | 3 | L A FULLER & SONS CONSTRUCTION, LTD. | TxDOT |
| 05 JUN 2024 | 06243027 | Fort Worth District | 1 | $100.00 | $1,800.00 | $52.00 | 2 | FNH CONSTRUCTION, LLC | TxDOT |
| 05 JUN 2024 | 06243058 | Amarillo District | 477 | $16.73 | $21.24 | $50.00 | 2 | TI-ZACK CONCRETE, LLC | TxDOT |
| 03 MAY 2024 | 05243204 | Pharr District | 156 | $45.00 | $56.50 | $70.00 | 2 | FOREMOST PAVING, INC. | TxDOT |
| 03 MAY 2024 | 05243214 | Wichita Falls District | 1,344 | $46.20 | $33.10 | $75.00 | 2 | GIBSON & ASSOCIATES, INC. | TxDOT |
| 02 MAY 2024 | 05243039 | San Antonio District | 12 | $500.00 | $79.80 | $13.00 | 9 | DIAMOND R CONTRACTING, LLC | TxDOT |
| 05 APR 2024 | 04243208 | San Antonio District | 125 | $30.00 | $44.02 | $45.04 | 6 | ENCINO LANDSCAPE, INC. | TxDOT |
| 05 APR 2024 | 04243219 | Austin District | 4 | $75.00 | $170.00 | $35.00 | 2 | DAN WILLIAMS COMPANY | TxDOT |
| 05 APR 2024 | 04243234 | Paris District | 185 | $100.00 | $95.00 | $50.00 | 4 | DCC CONSTRUCTION AND SERVICES, L.L.C. | TxDOT |
| 04 APR 2024 | 04243002 | Corpus Christi District | 12,862 | $26.00 | $26.00 | $37.50 | 3 | BAY LTD. | TxDOT |
| 04 APR 2024 | 04243017 | El Paso District | 364 | $85.00 | $92.50 | $30.00 | 4 | DAN WILLIAMS COMPANY | TxDOT |
| 04 APR 2024 | 04243018 | Laredo District | 14 | $150.00 | $162.50 | $34.00 | 4 | LUCANIA CONTRACTORS LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.