Removing concrete(mow strip) unit price, Texas
Low bidders on TxDOT contracts carried a median of $10.00 per LF for item 1046054, removing concrete(mow strip), from 06 FEB 2020 to 02 AUG 2024, across 256 low bids. Half of all 1,125 bids fell between $6.65 and $15.75.
- Owner
- Texas DOT
- Item
- 1046054
- Unit
- LF
- Latest letting
- 02 AUG 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 50 | 50 | $8.97 | 255 | $10.00 |
| 2021 | 59 | 59 | $7.77 | 311 | $8.00 |
| 2022 | 43 | 43 | $10.00 | 164 | $11.43 |
| 2023 | 52 | 52 | $10.00 | 189 | $11.00 |
| 2024 | 52 | 52 | $15.00 | 206 | $13.59 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Houston District | 30 | $8.50 | 145 | $10.00 |
| San Antonio District | 22 | $6.66 | 134 | $8.62 |
| Dallas District | 19 | $10.00 | 93 | $9.21 |
| Atlanta District | 23 | $10.00 | 88 | $10.90 |
| Austin District | 19 | $8.94 | 81 | $10.00 |
| Waco District | 17 | $10.00 | 67 | $10.00 |
| Abilene District | 12 | $10.25 | 60 | $12.00 |
| Beaumont District | 15 | $9.00 | 55 | $10.00 |
| Fort Worth District | 9 | $8.60 | 51 | $10.00 |
| Tyler District | 9 | $10.00 | 42 | $12.50 |
| Bryan District | 8 | $7.75 | 41 | $10.00 |
| Paris District | 10 | $15.00 | 40 | $12.59 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 10 to 500 | 64 | $13.46 |
| 501 to 1,181 | 64 | $10.00 |
| 1,181 to 2,887.50 | 64 | $9.00 |
| 3,150 to 45,858 | 64 | $7.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 02 AUG 2024 | 08243202 | Houston District | 1,034 | $6.18 | $6.09 | $11.00 | 4 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 10 JUL 2024 | 07243201 | Dallas District | 1,256 | $5.26 | $6.88 | $12.50 | 2 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 10 JUL 2024 | 07243207 | Dallas District | 703 | $25.00 | $10.00 | $50.00 | 6 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
| 10 JUL 2024 | 07243209 | Wichita Falls District | 250 | $25.00 | $24.50 | $15.00 | 5 | OVERLAND CORPORATION | TxDOT |
| 10 JUL 2024 | 07243212 | Bryan District | 931 | $8.50 | $8.50 | $9.00 | 5 | LARRY YOUNG PAVING, INC. | TxDOT |
| 09 JUL 2024 | 07243009 | Houston District | 700 | $9.26 | $7.13 | $16.47 | 8 | BRICE CONSTRUCTION AND DESIGN LLC | TxDOT |
| 06 JUN 2024 | 06243201 | San Antonio District | 8,599 | $6.09 | $11.00 | $15.00 | 5 | WEBBER, LLC | TxDOT |
| 06 JUN 2024 | 06243206 | Childress District | 4,025 | $15.00 | $13.00 | $11.00 | 4 | MORTMARA CONSTRUCTION, INC. | TxDOT |
| 05 JUN 2024 | 06243003 | Pharr District | 2,242 | $10.00 | $11.50 | $15.00 | 2 | IOC COMPANY LLC | TxDOT |
| 05 JUN 2024 | 06243031 | Wichita Falls District | 2,850 | $22.00 | $21.50 | $15.00 | 2 | ZACK BURKETT CO. | TxDOT |
| 03 MAY 2024 | 05243202 | Fort Worth District | 7,000 | $6.00 | $8.00 | $13.00 | 5 | ZACHRY CONSTRUCTION CORPORATION | TxDOT |
| 03 MAY 2024 | 05243203 | El Paso District | 17,036 | $6.00 | $5.50 | $7.00 | 3 | SUNDT CONSTRUCTION, INC. | TxDOT |
| 03 MAY 2024 | 05243204 | Pharr District | 872 | $25.00 | $28.50 | $15.00 | 2 | FOREMOST PAVING, INC. | TxDOT |
| 03 MAY 2024 | 05243212 | Abilene District | 2,385 | $16.50 | $16.50 | $9.00 | 1 | RK HALL, LLC | TxDOT |
| 03 MAY 2024 | 05243215 | San Antonio District | 1,139 | $8.00 | $8.00 | $15.93 | 7 | RELMCO, INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.