Replace rail element (thrie-beam) unit price, Texas
Low bidders on TxDOT contracts carried a median of $31.52 per LF for item 770-7002, replace rail element (thrie-beam), over the 24 months to 19 NOV 2026, across 74 low bids. Half of all 277 bids fell between $25.00 and $69.00.
- Owner
- Texas DOT
- Item
- 770-7002
- Unit
- LF
- Latest letting
- 19 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 2 | 2 | $55.00 | 13 | $50.00 |
| 2025 | 53 | 49 | $35.00 | 196 | $40.00 |
| 2026 | 25 | 23 | $25.00 | 68 | $30.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Houston District | 14 | $55.00 | 65 | $38.00 |
| Dallas District | 6 | $40.00 | 24 | $50.00 |
| Austin District | 5 | $40.00 | 24 | $47.50 |
| Fort Worth District | 4 | $25.00 | 20 | $37.50 |
| Beaumont District | 4 | $20.00 | 19 | $30.00 |
| Atlanta District | 6 | $37.50 | 19 | $35.00 |
| Bryan District | 5 | $20.00 | 16 | $20.00 |
| El Paso District | 4 | $39.00 | 13 | $54.05 |
| Paris District | 3 | $15.00 | 10 | $27.50 |
| Odessa District | 4 | $22.50 | 9 | $24.00 |
| Abilene District | 3 | $50.00 | 9 | $50.00 |
| San Antonio District | 3 | $19.00 | 8 | $37.50 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 1 to 25 | 18 | $42.50 |
| 25 to 50 | 19 | $40.00 |
| 50 to 50 | 18 | $20.00 |
| 60 to 1,000 | 19 | $26.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 19 NOV 2026 | A00224139 | Paris District | 325 | n/a | $25.00 | $10.00 | 1 | AUSTIN BARRICADE COMPANY, L.L.C. | TxDOT |
| 12 AUG 2026 | A00223094 | Bryan District | 50 | $20.00 | $20.00 | $30.00 | 2 | RHINO EQUITY, LLC | TxDOT |
| 11 AUG 2026 | A00223019 | Bryan District | 50 | $20.00 | $22.50 | $30.00 | 2 | T&L CLEANING SERVICES LLC | TxDOT |
| 14 JUL 2026 | A00220506 | Houston District | 35 | $60.00 | $41.50 | $87.00 | 4 | T&L CLEANING SERVICES LLC | TxDOT |
| 01 JUL 2026 | A00218278 | Dallas District | 38 | $5.00 | $10.00 | $27.50 | 2 | ROY JORGENSEN ASSOCIATES, INC. | TxDOT |
| 09 JUN 2026 | A00220019 | Houston District | 100 | $15.00 | $20.00 | $75.00 | 3 | ROY JORGENSEN ASSOCIATES, INC. | TxDOT |
| 27 MAY 2026 | A00221790 | Amarillo District | 50 | $587.50 | $35.00 | $30.00 | 3 | TI-ZACK CONCRETE, LLC | TxDOT |
| 13 MAY 2026 | A00220031 | Lufkin District | 25 | n/a | $30.00 | $100.00 | 1 | BK FIELD OPERATIONS LLC | TxDOT |
| 13 MAY 2026 | A00220151 | Austin District | 100 | $25.00 | $30.00 | $75.00 | 5 | ROSS SA ENTERPRISE LLC | TxDOT |
| 12 MAY 2026 | A00221612 | Odessa District | 30 | $20.00 | $24.00 | $35.00 | 3 | AUSTIN BARRICADE COMPANY, L.L.C. | TxDOT |
| 12 MAY 2026 | A00220799 | Tyler District | 20 | $100.00 | $100.00 | $35.00 | 1 | CATOCON, INC. | TxDOT |
| 12 MAY 2026 | A00218435 | Tyler District | 25 | $40.00 | $40.00 | $35.00 | 1 | CATOCON, INC. | TxDOT |
| 21 APR 2026 | A00219951 | Odessa District | 50 | $25.00 | $24.50 | $35.00 | 2 | HJC FARMS, INC. | TxDOT |
| 21 APR 2026 | A00220088 | Odessa District | 50 | $25.00 | $25.00 | $35.00 | 1 | HJC FARMS, INC. | TxDOT |
| 16 APR 2026 | A00212377 | San Angelo District | 50 | $20.00 | $25.00 | $35.00 | 4 | T&L CLEANING SERVICES LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.