Riprap (conc)(cl b)(RR8&RR9) unit price, Texas
Low bidders on TxDOT contracts carried a median of $523.42 per CY for item 4326008, riprap (conc)(cl b)(rr8&rr9), from 11 FEB 2020 to 01 AUG 2024, across 130 low bids. Half of all 590 bids fell between $465.00 and $735.26.
- Owner
- Texas DOT
- Item
- 4326008
- Unit
- CY
- Latest letting
- 01 AUG 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 22 | 22 | $427.20 | 117 | $500.00 |
| 2021 | 28 | 28 | $450.00 | 164 | $500.00 |
| 2022 | 23 | 23 | $521.86 | 90 | $565.66 |
| 2023 | 27 | 27 | $644.76 | 96 | $650.00 |
| 2024 | 30 | 30 | $650.00 | 123 | $700.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Houston District | 26 | $450.00 | 115 | $500.00 |
| Corpus Christi District | 17 | $580.00 | 87 | $550.00 |
| San Antonio District | 10 | $417.06 | 78 | $520.00 |
| Dallas District | 14 | $635.50 | 64 | $650.00 |
| Fort Worth District | 7 | $626.00 | 33 | $500.00 |
| Austin District | 6 | $465.50 | 32 | $510.00 |
| Bryan District | 4 | $750.00 | 18 | $828.16 |
| Odessa District | 4 | $765.81 | 17 | $681.11 |
| Waco District | 5 | $385.00 | 17 | $425.00 |
| Yoakum District | 7 | $600.00 | 17 | $640.00 |
| Atlanta District | 3 | $450.00 | 15 | $500.00 |
| El Paso District | 4 | $532.50 | 12 | $382.50 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 2 to 45 | 32 | $640.00 |
| 46 to 130 | 33 | $585.00 |
| 132.10 to 370 | 32 | $500.92 |
| 373 to 3,243.90 | 33 | $457.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 01 AUG 2024 | 08243001 | Houston District | 690.36 | $341.09 | $520.54 | $467.00 | 2 | WEBBER, LLC | TxDOT |
| 10 JUL 2024 | 07243201 | Dallas District | 211 | $805.93 | $628.96 | $624.85 | 2 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 10 JUL 2024 | 07243218 | Lufkin District | 5 | $1,100.00 | $1,000.00 | $700.00 | 3 | TI-ZACK CONCRETE, LLC | TxDOT |
| 09 JUL 2024 | 07243001 | Fort Worth District | 97 | $650.00 | $651.00 | $652.00 | 2 | ZACHRY CONSTRUCTION CORPORATION | TxDOT |
| 09 JUL 2024 | 07243009 | Houston District | 369.90 | $648.07 | $612.50 | $793.00 | 8 | BRICE CONSTRUCTION AND DESIGN LLC | TxDOT |
| 09 JUL 2024 | 07243032 | Dallas District | 5 | $1,850.00 | $1,850.00 | $2,100.00 | 3 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 06 JUN 2024 | 06243203 | Houston District | 198 | $467.90 | $500.95 | $410.00 | 2 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 06 JUN 2024 | 06243205 | Wichita Falls District | 158 | $600.00 | $630.00 | $750.00 | 3 | A. L. HELMCAMP, INC. | TxDOT |
| 06 JUN 2024 | 06243206 | Childress District | 837 | $725.00 | $737.50 | $650.00 | 4 | MORTMARA CONSTRUCTION, INC. | TxDOT |
| 05 JUN 2024 | 06243006 | Brownwood District | 174 | $750.87 | $725.43 | $525.00 | 4 | ALLEN KELLER COMPANY | TxDOT |
| 03 MAY 2024 | 05243201 | Yoakum District | 2,747 | $519.98 | $519.98 | $450.00 | 3 | PULICE CONSTRUCTION, INC. | TxDOT |
| 03 MAY 2024 | 05243203 | El Paso District | 1,411.90 | $700.00 | $550.00 | $450.00 | 3 | SUNDT CONSTRUCTION, INC. | TxDOT |
| 03 MAY 2024 | 05243215 | San Antonio District | 215 | $465.00 | $610.00 | $385.36 | 7 | RELMCO, INC. | TxDOT |
| 02 MAY 2024 | 05243001 | Beaumont District | 20 | $800.00 | $800.00 | $611.00 | 1 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. | TxDOT |
| 02 MAY 2024 | 05243003 | Waco District | 604 | $550.00 | $650.00 | $625.00 | 4 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way