Riprap (mow strip)(4 in) unit price, Texas
Low bidders on TxDOT contracts carried a median of $575.00 per CY for item 4326045, riprap (mow strip)(4 in), from 09 JAN 2020 to 02 AUG 2024, across 1,168 low bids. Half of all 5,514 bids fell between $500.00 and $727.75.
- Owner
- Texas DOT
- Item
- 4326045
- Unit
- CY
- Latest letting
- 02 AUG 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 240 | 240 | $494.63 | 1,350 | $535.00 |
| 2021 | 265 | 265 | $517.32 | 1,521 | $533.61 |
| 2022 | 194 | 194 | $587.61 | 832 | $604.25 |
| 2023 | 254 | 254 | $650.00 | 954 | $693.72 |
| 2024 | 215 | 215 | $695.79 | 857 | $707.75 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Dallas District | 106 | $575.00 | 569 | $575.00 |
| Houston District | 108 | $545.00 | 539 | $600.00 |
| Austin District | 88 | $525.00 | 458 | $550.00 |
| San Antonio District | 72 | $522.50 | 442 | $580.00 |
| Fort Worth District | 65 | $600.00 | 341 | $590.00 |
| Tyler District | 61 | $564.00 | 334 | $564.50 |
| Bryan District | 46 | $500.00 | 237 | $600.00 |
| Paris District | 52 | $513.55 | 228 | $520.50 |
| Wichita Falls District | 55 | $702.00 | 226 | $656.62 |
| Corpus Christi District | 45 | $540.00 | 223 | $550.00 |
| Waco District | 50 | $538.24 | 220 | $550.00 |
| Abilene District | 47 | $700.00 | 212 | $700.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 2 to 34 | 292 | $626.67 |
| 34 to 82 | 292 | $600.00 |
| 82 to 246 | 292 | $561.89 |
| 246 to 11,778.30 | 292 | $525.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 02 AUG 2024 | 08243201 | Pharr District | 555 | $625.00 | $625.00 | $490.00 | 3 | FOREMOST PAVING, INC. | TxDOT |
| 02 AUG 2024 | 08243202 | Houston District | 49 | $695.79 | $695.48 | $650.00 | 4 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 02 AUG 2024 | 08243203 | San Angelo District | 895 | $643.50 | $860.00 | $550.00 | 5 | RK HALL, LLC | TxDOT |
| 01 AUG 2024 | 08243001 | Houston District | 183 | $418.11 | $959.06 | $590.00 | 2 | WEBBER, LLC | TxDOT |
| 01 AUG 2024 | 08243002 | Pharr District | 99 | $500.00 | $500.00 | $490.00 | 5 | FOREMOST PAVING, INC. | TxDOT |
| 10 JUL 2024 | 07243201 | Dallas District | 1,097 | $733.82 | $604.41 | $683.50 | 2 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 10 JUL 2024 | 07243203 | Pharr District | 125 | $1,400.00 | $676.53 | $400.00 | 4 | FOREMOST PAVING, INC. | TxDOT |
| 10 JUL 2024 | 07243205 | Laredo District | 49 | $650.00 | $585.23 | $725.00 | 4 | ANDERSON COLUMBIA CO., INC. | TxDOT |
| 10 JUL 2024 | 07243207 | Dallas District | 130 | $738.00 | $787.50 | $700.00 | 6 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
| 10 JUL 2024 | 07243208 | San Antonio District | 113 | $837.00 | $813.50 | $435.83 | 8 | ACME BRIDGE COMPANY, INC. | TxDOT |
| 10 JUL 2024 | 07243209 | Wichita Falls District | 90.35 | $725.00 | $800.00 | $700.00 | 5 | OVERLAND CORPORATION | TxDOT |
| 10 JUL 2024 | 07243211 | Childress District | 60 | $610.14 | $750.00 | $750.00 | 5 | C. E. BARKER, LTD. | TxDOT |
| 10 JUL 2024 | 07243212 | Bryan District | 14 | $3,500.00 | $1,500.00 | $750.00 | 5 | LARRY YOUNG PAVING, INC. | TxDOT |
| 10 JUL 2024 | 07243215 | Wichita Falls District | 15 | $877.50 | $908.75 | $525.00 | 4 | ZACK BURKETT CO. | TxDOT |
| 10 JUL 2024 | 07243223 | Waco District | 15 | $700.00 | $700.00 | $418.02 | 8 | GARRET SHIELDS INFRASTRUCTURE | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.