Rumble strips (shoulder) asphalt unit price, Texas
Low bidders on TxDOT contracts carried a median of $0.20 per LF for item 5336003, rumble strips (shoulder) asphalt, from 09 JAN 2020 to 10 JUL 2024, across 261 low bids. Half of all 1,092 bids fell between $0.15 and $0.42.
- Owner
- Texas DOT
- Item
- 5336003
- Unit
- LF
- Latest letting
- 10 JUL 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 44 | 44 | $0.21 | 229 | $0.20 |
| 2021 | 71 | 71 | $0.20 | 343 | $0.22 |
| 2022 | 47 | 47 | $0.20 | 184 | $0.21 |
| 2023 | 41 | 41 | $0.20 | 122 | $0.24 |
| 2024 | 58 | 58 | $0.21 | 214 | $0.25 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Dallas District | 48 | $0.24 | 233 | $0.25 |
| Fort Worth District | 15 | $0.18 | 73 | $0.18 |
| Beaumont District | 19 | $0.20 | 68 | $0.21 |
| Wichita Falls District | 16 | $0.22 | 60 | $0.20 |
| Atlanta District | 16 | $0.32 | 59 | $0.45 |
| El Paso District | 18 | $0.19 | 54 | $0.25 |
| Laredo District | 14 | $0.19 | 54 | $0.20 |
| Paris District | 14 | $0.20 | 54 | $0.20 |
| Waco District | 13 | $0.21 | 49 | $0.24 |
| Childress District | 9 | $0.18 | 43 | $0.19 |
| Bryan District | 9 | $0.65 | 43 | $0.75 |
| Lubbock District | 10 | $0.60 | 39 | $0.40 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 998 to 16,345 | 65 | $0.90 |
| 16,430 to 52,168 | 65 | $0.22 |
| 52,500 to 105,105 | 65 | $0.18 |
| 105,201 to 2,696,677 | 66 | $0.15 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 10 JUL 2024 | 07243201 | Dallas District | 21,723 | $0.13 | $0.47 | $1.10 | 2 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 10 JUL 2024 | 07243205 | Laredo District | 110,437 | $0.10 | $0.13 | $0.25 | 4 | ANDERSON COLUMBIA CO., INC. | TxDOT |
| 10 JUL 2024 | 07243207 | Dallas District | 7,402 | $0.50 | $1.05 | $1.00 | 6 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
| 10 JUL 2024 | 07243212 | Bryan District | 32,260 | $0.25 | $0.25 | $0.50 | 5 | LARRY YOUNG PAVING, INC. | TxDOT |
| 10 JUL 2024 | 07243215 | Wichita Falls District | 76,060 | $0.29 | $0.24 | $0.24 | 4 | ZACK BURKETT CO. | TxDOT |
| 09 JUL 2024 | 07243020 | Beaumont District | 17,574 | $0.10 | $0.10 | $0.15 | 3 | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. | TxDOT |
| 09 JUL 2024 | 07243032 | Dallas District | 87,320 | $0.12 | $0.13 | $0.50 | 3 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 09 JUL 2024 | 07244018 | Dallas District | 1,882 | $1.00 | $2.38 | $0.50 | 4 | FOUTSCO PAVING COMPANY, LLC | TxDOT |
| 06 JUN 2024 | 06243213 | Dallas District | 144,350 | $0.20 | $0.20 | $0.35 | 3 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 06 JUN 2024 | 06243219 | Paris District | 266,859 | $0.20 | $0.17 | $0.12 | 4 | OVERLAND CORPORATION | TxDOT |
| 06 JUN 2024 | 06243220 | Wichita Falls District | 197,906 | $0.26 | $0.23 | $0.12 | 3 | ZACK BURKETT CO. | TxDOT |
| 06 JUN 2024 | 06243224 | Austin District | 13,607 | $0.26 | $0.27 | $0.17 | 4 | LONE STAR PAVING COMPANY | TxDOT |
| 06 JUN 2024 | 06243243 | Bryan District | 3,402 | $2.60 | $2.80 | $0.50 | 4 | BRAZOS PAVING, INC. | TxDOT |
| 05 JUN 2024 | 06243007 | Dallas District | 51,752 | $0.28 | $0.28 | $0.13 | 3 | KNIFE RIVER CORPORATION - SOUTH | TxDOT |
| 05 JUN 2024 | 06243009 | Bryan District | 47,600 | $0.12 | $0.21 | $0.20 | 6 | KNIFE RIVER CORPORATION - SOUTH | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way