Low bidders on TxDOT contracts carried a median of $1,217.00 per EACH for item 4676348, set (ty ii) (18 in) (cmp) (6: 1) (p), from 06 FEB 2020 to 10 JUL 2024, across 74 low bids. Half of all 355 bids fell between $1,000.00 and $1,658.00.
- Owner
- Texas DOT
- Item
- 4676348
- Unit
- EACH
- Latest letting
- 10 JUL 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 27 | 27 | $1,025.00 | 141 | $1,100.00 |
| 2021 | 20 | 20 | $1,250.00 | 99 | $1,250.00 |
| 2022 | 11 | 10 | $1,555.92 | 38 | $1,490.00 |
| 2023 | 10 | 10 | $1,423.07 | 31 | $1,500.00 |
| 2024 | 7 | 7 | $1,500.00 | 46 | $1,605.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Yoakum District | 17 | $1,403.94 | 93 | $1,446.13 |
| Wichita Falls District | 16 | $1,250.00 | 59 | $1,250.00 |
| Paris District | 11 | $709.30 | 53 | $700.00 |
| Corpus Christi District | 5 | $1,155.01 | 26 | $1,337.19 |
| Bryan District | 5 | $946.00 | 24 | $985.00 |
| San Antonio District | 4 | $1,555.92 | 22 | $1,522.50 |
| Austin District | 4 | $1,623.62 | 21 | $1,500.00 |
| Waco District | 3 | $1,000.00 | 17 | $1,500.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 2 to 4 | 18 | $1,582.20 |
| 6 to 14 | 19 | $1,250.00 |
| 16 to 40 | 18 | $1,242.00 |
| 42 to 192 | 19 | $950.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 10 JUL 2024 | 07243223 | Waco District | 4 | $1,000.00 | $1,350.00 | $1,209.82 | 9 | GARRET SHIELDS INFRASTRUCTURE | TxDOT |
| 05 JUN 2024 | 06243016 | Beaumont District | 16 | $1,050.00 | $1,050.00 | $1,343.80 | 3 | TEXAS MATERIALS GROUP, INC. | TxDOT |
| 02 MAY 2024 | 05243018 | Corpus Christi District | 88 | $1,750.00 | $1,575.00 | $1,280.00 | 8 | CK NEWBERRY, LLC | TxDOT |
| 05 APR 2024 | 04243209 | Yoakum District | 4 | $1,500.00 | $1,970.00 | $1,200.00 | 11 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 04 APR 2024 | 04243013 | Abilene District | 4 | $5,000.00 | $3,000.00 | $959.80 | 6 | COPPELL CONSTRUCTION CO., INC. | TxDOT |
| 01 FEB 2024 | 02243008 | Yoakum District | 26 | $1,709.80 | $1,655.00 | $1,750.00 | 6 | CLARK CONSTRUCTION OF TEXAS, INC. | TxDOT |
| 04 JAN 2024 | 01243012 | Wichita Falls District | 32 | $1,250.00 | $1,600.00 | $1,700.00 | 3 | A. L. HELMCAMP, INC. | TxDOT |
| 05 DEC 2023 | 12233003 | Yoakum District | 46 | $1,446.13 | $1,388.07 | $1,400.00 | 4 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 01 NOV 2023 | 11233012 | Paris District | 10 | $900.00 | $900.00 | $825.00 | 1 | HIGHWAY 19 CONSTRUCTION LLC | TxDOT |
| 01 NOV 2023 | 11233013 | Corpus Christi District | 22 | $1,000.00 | $1,450.00 | $1,800.00 | 3 | CK NEWBERRY, LLC | TxDOT |
| 06 SEP 2023 | 09233012 | Corpus Christi District | 16 | $1,234.00 | $1,579.50 | $1,645.00 | 4 | BRANNAN PAVING CO., LTD. | TxDOT |
| 03 AUG 2023 | 08233214 | Paris District | 24 | $777.00 | $786.00 | $800.00 | 2 | HIGHWAY 19 CONSTRUCTION LLC | TxDOT |
| 28 JUN 2023 | 06233618 | Wichita Falls District | 14 | $1,700.00 | $1,475.00 | $1,500.00 | 2 | JAGOE-PUBLIC COMPANY | TxDOT |
| 02 JUN 2023 | 06233214 | Wichita Falls District | 2 | $1,700.00 | $1,732.50 | $1,400.00 | 3 | DUININCK, INC. | TxDOT |
| 04 MAY 2023 | 05233015 | Yoakum District | 18 | $1,680.00 | $1,640.65 | $1,750.00 | 5 | BRANNAN PAVING CO., LTD. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.