Set (ty ii) (36 in) (rcp) (4: 1) (c) unit price, Texas
Low bidders on TxDOT contracts carried a median of $4,375.00 per EACH for item 467-7366, set (ty ii) (36 in) (rcp) (4: 1) (c), over the 24 months to 19 NOV 2026, across 47 low bids. Half of all 281 bids fell between $3,650.00 and $5,360.00.
- Owner
- Texas DOT
- Item
- 467-7366
- Unit
- EACH
- Latest letting
- 13 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 2 | 2 | $3,350.00 | 10 | $5,000.00 |
| 2025 | 21 | 21 | $4,300.00 | 111 | $4,500.00 |
| 2026 | 26 | 26 | $4,687.50 | 170 | $4,345.97 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Tyler District | 5 | $3,500.00 | 34 | $3,585.00 |
| Dallas District | 4 | $5,410.00 | 30 | $4,323.47 |
| Paris District | 5 | $4,000.00 | 24 | $4,344.00 |
| San Antonio District | 3 | $4,800.00 | 24 | $5,372.94 |
| Bryan District | 4 | $5,000.00 | 23 | $5,000.00 |
| Laredo District | 4 | $5,082.19 | 22 | $4,436.14 |
| Wichita Falls District | 4 | $4,425.00 | 22 | $4,000.00 |
| Beaumont District | 3 | $4,000.00 | 12 | $3,669.38 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 11 | $5,350.00 |
| 2 to 3 | 12 | $4,815.00 |
| 3 to 6 | 12 | $4,400.00 |
| 6 to 18 | 12 | $3,800.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 13 OCT 2026 | A00223040 | Tyler District | 1 | $5,500.00 | $4,000.00 | $3,500.00 | 7 | ICOS MANAGEMENT, LLC | TxDOT |
| 07 OCT 2026 | A00064192 | San Antonio District | 4 | $3,475.87 | $4,971.83 | $5,385.00 | 8 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 03 SEP 2026 | A00196194 | Atlanta District | 2 | $3,950.00 | $4,225.00 | $4,500.00 | 4 | LONGVIEW BRIDGE AND ROAD, LTD. | TxDOT |
| 03 SEP 2026 | A00061184 | Austin District | 2 | $5,250.45 | $4,956.70 | $4,000.00 | 8 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 02 SEP 2026 | A00121174 | Pharr District | 4 | $8,000.00 | $5,630.83 | $3,900.00 | 7 | IOC COMPANY LLC | TxDOT |
| 12 AUG 2026 | A00222813 | Bryan District | 4 | $3,500.00 | $4,650.00 | $4,300.00 | 4 | GARRET SHIELDS INFRASTRUCTURE | TxDOT |
| 06 AUG 2026 | A00199843 | Odessa District | 8 | $3,800.00 | $5,200.00 | $4,800.00 | 5 | DAN WILLIAMS COMPANY | TxDOT |
| 06 AUG 2026 | A00119935 | Laredo District | 4 | $6,997.73 | $7,492.45 | $3,752.00 | 4 | PULICE CONSTRUCTION, INC. | TxDOT |
| 06 AUG 2026 | A00219498 | Wichita Falls District | 2 | $5,000.00 | $4,600.00 | $3,800.00 | 3 | GARRET SHIELDS INFRASTRUCTURE | TxDOT |
| 05 AUG 2026 | A00196471 | Corpus Christi District | 3 | $4,375.00 | $4,375.00 | $5,500.00 | 9 | CLARK CONSTRUCTION OF TEXAS, INC. | TxDOT |
| 05 AUG 2026 | A00007222 | Fort Worth District | 2 | $6,400.00 | $5,500.00 | $3,000.00 | 11 | INDUS ROAD & BRIDGE, INC. | TxDOT |
| 01 JUL 2026 | A00187963 | Beaumont District | 6 | $3,200.00 | $3,505.75 | $4,000.00 | 3 | DURWOOD GREENE CONSTRUCTION CO. | TxDOT |
| 01 JUL 2026 | A00058522 | Tyler District | 11 | $3,200.00 | $3,600.00 | $4,500.00 | 7 | DRAKE COMPANIES LLC | TxDOT |
| 03 JUN 2026 | A00183477 | Beaumont District | 2 | $5,125.00 | $3,916.50 | $4,250.00 | 4 | R CONSTRUCTION CIVIL, LLC | TxDOT |
| 02 JUN 2026 | A00133020 | Laredo District | 6 | $4,040.01 | $3,708.10 | $3,373.00 | 7 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.