Sp mixes sp-c sac-a PG70-22 unit price, Texas
Low bidders on TxDOT contracts carried a median of $161.00 per TON for item 344-7020, sp mixes sp-c sac-a pg70-22, over the 24 months to 19 NOV 2026, across 66 low bids. Half of all 355 bids fell between $145.00 and $192.55.
- Owner
- Texas DOT
- Item
- 344-7020
- Unit
- TON
- Latest letting
- 04 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2025 | 39 | 39 | $162.50 | 187 | $175.00 |
| 2026 | 27 | 27 | $160.00 | 168 | $164.63 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Bryan District | 19 | $140.00 | 109 | $152.00 |
| Tyler District | 19 | $172.00 | 100 | $180.00 |
| Lufkin District | 9 | $171.00 | 59 | $177.42 |
| Dallas District | 5 | $151.00 | 36 | $169.88 |
| San Angelo District | 3 | $139.19 | 12 | $141.00 |
| El Paso District | 5 | $137.00 | 11 | $137.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 179 to 1,849 | 16 | $183.50 |
| 1,863 to 4,940 | 17 | $146.00 |
| 5,239 to 10,967 | 16 | $164.31 |
| 11,174 to 85,119 | 17 | $139.19 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 04 NOV 2026 | A00124162 | Bryan District | 14,424 | $116.00 | $130.83 | $110.00 | 12 | FLUOR ENTERPRISES, INC. | TxDOT |
| 14 OCT 2026 | A00218279 | Dallas District | 2,364.39 | $178.00 | $200.00 | $150.00 | 7 | TEXAS MATERIALS GROUP, INC. | TxDOT |
| 06 OCT 2026 | A00186301 | Waco District | 8,642 | $110.00 | $121.50 | $140.00 | 6 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 06 AUG 2026 | A00049653 | Tyler District | 8,633 | $157.00 | $157.00 | $130.00 | 5 | LONGVIEW BRIDGE AND ROAD, LTD. | TxDOT |
| 06 AUG 2026 | A00222319 | Bryan District | 5,239 | $160.00 | $163.65 | $180.00 | 4 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 05 AUG 2026 | A00196824 | Bryan District | 8,890 | $110.00 | $127.50 | $130.00 | 6 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 02 JUL 2026 | A00222320 | Bryan District | 7,563 | $162.50 | $173.80 | $180.00 | 4 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 02 JUL 2026 | A00027293 | Tyler District | 25,740 | $150.50 | $149.00 | $142.00 | 9 | BAKER & COMPANY CONSTRUCTION, LLC | TxDOT |
| 01 JUL 2026 | A00206568 | Lufkin District | 4,602 | $165.00 | $165.00 | $150.00 | 5 | L. S. EQUIPMENT CO., INC. | TxDOT |
| 01 JUL 2026 | A00222317 | Bryan District | 5,775 | $162.75 | $165.00 | $180.00 | 5 | BRAZOS PAVING, INC. | TxDOT |
| 01 JUL 2026 | A00058522 | Tyler District | 45,266 | $145.50 | $152.00 | $142.00 | 7 | DRAKE COMPANIES LLC | TxDOT |
| 03 JUN 2026 | A00206565 | Lufkin District | 5,989 | $165.88 | $165.88 | $150.00 | 9 | PINTO CONSTRUCTION CO., INC. | TxDOT |
| 03 JUN 2026 | A00132662 | Abilene District | 1,342 | $165.00 | $165.00 | $280.00 | 1 | FNF CONSTRUCTION, INC. | TxDOT |
| 03 JUN 2026 | A00220774 | Tyler District | 14,726 | $189.00 | $194.00 | $170.00 | 4 | EAST TEXAS BRIDGE, INC. | TxDOT |
| 02 JUN 2026 | A00206629 | Bryan District | 1,863 | $140.00 | $143.00 | $151.16 | 7 | LARRY YOUNG PAVING, INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.