Strip mowing unit price, Texas
Low bidders on TxDOT contracts carried a median of $33.16 per ACRE for item 730-7020, strip mowing, over the 24 months to 19 NOV 2026, across 132 low bids. Half of all 597 bids fell between $30.29 and $49.00.
- Owner
- Texas DOT
- Item
- 730-7020
- Unit
- ACRE
- Latest letting
- 12 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2025 | 90 | 82 | $33.25 | 389 | $40.00 |
| 2026 | 56 | 50 | $32.49 | 208 | $40.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Paris District | 16 | $24.00 | 87 | $36.00 |
| Dallas District | 12 | $39.00 | 74 | $45.00 |
| Abilene District | 19 | $27.00 | 57 | $35.00 |
| Wichita Falls District | 12 | $20.00 | 54 | $31.31 |
| Yoakum District | 11 | $24.00 | 47 | $30.00 |
| Amarillo District | 7 | $37.84 | 36 | $50.25 |
| Beaumont District | 8 | $22.00 | 34 | $44.00 |
| Tyler District | 5 | $25.00 | 28 | $41.50 |
| Lufkin District | 3 | $36.00 | 27 | $36.00 |
| Brownwood District | 6 | $38.36 | 27 | $41.89 |
| Corpus Christi District | 8 | $42.17 | 25 | $46.00 |
| Fort Worth District | 3 | $40.00 | 22 | $40.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (ACRE) | Low bids | Low-bid median |
|---|---|---|
| 3 to 756 | 33 | $35.80 |
| 857 to 1,276 | 33 | $32.00 |
| 1,280 to 1,946 | 33 | $28.00 |
| 1,984 to 11,208 | 33 | $33.98 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 12 NOV 2026 | A00221878 | Dallas District | 200 | n/a | $46.00 | $43.00 | 4 | ORTEGA'S LAWN AND LANDSCAPING, LLC | TxDOT |
| 15 SEP 2026 | A00223755 | Brownwood District | 11,208 | $39.22 | $43.67 | $39.00 | 7 | T&L CLEANING SERVICES LLC | TxDOT |
| 18 AUG 2026 | A00223043 | Corpus Christi District | 857 | $48.76 | $59.38 | $54.00 | 2 | R&M INCORPORATED | TxDOT |
| 18 AUG 2026 | A00223044 | Corpus Christi District | 961 | $46.00 | $46.00 | $54.00 | 3 | CROSS PLUS CONSTRUCTION, LLC | TxDOT |
| 09 JUL 2026 | A00220198 | San Angelo District | 1,650 | $39.45 | $45.00 | $26.64 | 3 | R&M INCORPORATED | TxDOT |
| 01 JUL 2026 | A00193362 | San Antonio District | 3 | $3,500.00 | $2,860.00 | $40.00 | 7 | J3 COMPANY, LLC | TxDOT |
| 18 JUN 2026 | A00220829 | Laredo District | 1,436 | $41.98 | $48.00 | $40.00 | 3 | R&M INCORPORATED | TxDOT |
| 26 MAY 2026 | A00220136 | Laredo District | 1,073 | $49.71 | $49.71 | $42.00 | 1 | R&M INCORPORATED | TxDOT |
| 19 MAY 2026 | A00220960 | Corpus Christi District | 382 | $53.97 | $53.97 | $41.00 | 1 | R&M INCORPORATED | TxDOT |
| 07 MAY 2026 | A00220700 | Amarillo District | 400 | $58.00 | $60.00 | $49.00 | 6 | ALL HANDS & DUKE, INC. | TxDOT |
| 07 MAY 2026 | A00220705 | Amarillo District | 224 | $36.93 | $45.00 | $37.37 | 5 | BERT WHITAKER | TxDOT |
| 07 MAY 2026 | A00220711 | Amarillo District | 312 | $37.49 | $48.00 | $36.08 | 5 | SQUARE G, INC. | TxDOT |
| 07 MAY 2026 | A00220712 | Amarillo District | 636 | $37.84 | $55.00 | $43.00 | 5 | SQUARE G, INC. | TxDOT |
| 06 MAY 2026 | A00220703 | Amarillo District | 28 | $40.00 | $55.00 | $41.50 | 5 | GORMAN OUTDOOR, INC. | TxDOT |
| 06 MAY 2026 | A00220707 | Amarillo District | 1,984 | $35.46 | $47.50 | $38.00 | 6 | BERT WHITAKER | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.