Tree removal (42" - 48" dia) unit price, Texas
Low bidders on TxDOT contracts carried a median of $400.00 per EACH for item 752-7011, tree removal (42" - 48" dia), over the 24 months to 19 NOV 2026, across 85 low bids. Half of all 563 bids fell between $345.50 and $1,000.00.
- Owner
- Texas DOT
- Item
- 752-7011
- Unit
- EACH
- Latest letting
- 19 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 7 | 7 | $900.00 | 27 | $1,500.00 |
| 2025 | 46 | 38 | $275.00 | 287 | $500.00 |
| 2026 | 48 | 45 | $500.00 | 269 | $700.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Lufkin District | 18 | $200.00 | 113 | $400.00 |
| Dallas District | 7 | $250.00 | 63 | $700.00 |
| Atlanta District | 9 | $250.00 | 51 | $700.00 |
| Bryan District | 9 | $250.00 | 50 | $472.50 |
| Fort Worth District | 6 | $565.00 | 47 | $950.00 |
| Paris District | 7 | $400.00 | 46 | $600.00 |
| Tyler District | 4 | $700.00 | 29 | $450.00 |
| Beaumont District | 5 | $500.00 | 28 | $1,000.00 |
| San Angelo District | 3 | $500.00 | 23 | $700.00 |
| Waco District | 4 | $1,300.00 | 20 | $1,000.00 |
| Austin District | 3 | $300.00 | 19 | $1,000.00 |
| Brownwood District | 3 | $500.00 | 18 | $675.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 21 | $500.00 |
| 2 to 5 | 21 | $499.00 |
| 5 to 10 | 21 | $250.00 |
| 10 to 50 | 22 | $390.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 19 NOV 2026 | A00224894 | San Angelo District | 2 | $1,200.00 | $700.00 | $500.00 | 7 | ALLIES LAND CLEARING | TxDOT |
| 17 NOV 2026 | A00223761 | Beaumont District | 2 | $500.00 | $1,000.00 | $650.00 | 7 | ACE CONTRACTORS, INC. | TxDOT |
| 17 NOV 2026 | A00223887 | Beaumont District | 10 | $400.00 | $1,000.00 | $650.00 | 7 | L & M MOWING CONTRACTORS, LLC | TxDOT |
| 17 NOV 2026 | A00223897 | Beaumont District | 2 | $500.00 | $1,400.00 | $650.00 | 8 | ACE CONTRACTORS, INC. | TxDOT |
| 12 NOV 2026 | A00224261 | Amarillo District | 22 | $1,200.00 | $1,250.00 | $1,300.00 | 8 | ALLIES LAND CLEARING | TxDOT |
| 28 OCT 2026 | A00224238 | Lufkin District | 2 | $500.00 | $375.00 | $420.00 | 4 | ACE CONTRACTORS, INC. | TxDOT |
| 14 OCT 2026 | A00221497 | Dallas District | 2 | $800.00 | $900.00 | $895.33 | 8 | GV LANDSCAPE AND CONSTRUCTION LLC | TxDOT |
| 08 OCT 2026 | A00223995 | Yoakum District | 5 | $200.00 | $555.00 | $450.00 | 5 | ROW Contractors LLC | TxDOT |
| 23 SEP 2026 | A00222474 | Lufkin District | 15 | $650.00 | $500.00 | $400.00 | 2 | WESTERN CERTIFIED ARBORISTS | TxDOT |
| 17 SEP 2026 | A00222992 | Paris District | 10 | $500.00 | $500.00 | $584.49 | 7 | CATOCON, INC. | TxDOT |
| 16 SEP 2026 | A00223390 | Fort Worth District | 2 | $750.00 | $750.00 | $342.39 | 5 | WESTERN CERTIFIED ARBORISTS | TxDOT |
| 20 AUG 2026 | A00222783 | Fort Worth District | 10 | $380.00 | $359.44 | $295.00 | 8 | GV LANDSCAPE AND CONSTRUCTION LLC | TxDOT |
| 12 AUG 2026 | A00222416 | Lufkin District | 2 | $50.00 | $450.00 | $420.00 | 5 | K & R CONTRACTORS | TxDOT |
| 12 AUG 2026 | A00222372 | Lufkin District | 2 | n/a | $450.00 | $425.00 | 3 | ACE CONTRACTORS, INC. | TxDOT |
| 11 AUG 2026 | A00221492 | Childress District | 16 | $1,000.00 | $812.00 | $540.00 | 6 | BLACK CROWN CONSTRUCTION LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.