Trench excavation protection unit price, Texas
Low bidders on TxDOT contracts carried a median of $10.00 per LF for item 402-7001, trench excavation protection, over the 24 months to 19 NOV 2026, across 249 low bids. Half of all 1,513 bids fell between $5.00 and $21.00.
- Owner
- Texas DOT
- Item
- 402-7001
- Unit
- LF
- Latest letting
- 04 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 11 | 11 | $16.00 | 69 | $10.00 |
| 2025 | 131 | 129 | $10.00 | 749 | $10.00 |
| 2026 | 121 | 117 | $10.00 | 743 | $10.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Dallas District | 40 | $9.50 | 254 | $10.00 |
| Austin District | 23 | $10.35 | 169 | $12.00 |
| Pharr District | 19 | $4.50 | 112 | $4.66 |
| San Antonio District | 18 | $20.50 | 104 | $10.00 |
| Fort Worth District | 18 | $10.00 | 101 | $8.51 |
| Houston District | 10 | $5.95 | 89 | $6.00 |
| Tyler District | 12 | $10.00 | 79 | $10.00 |
| Yoakum District | 11 | $12.00 | 74 | $15.00 |
| Bryan District | 12 | $7.50 | 68 | $12.50 |
| Paris District | 12 | $12.50 | 65 | $15.00 |
| Waco District | 10 | $10.00 | 64 | $10.00 |
| Corpus Christi District | 7 | $4.89 | 45 | $8.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 6 to 82 | 62 | $18.00 |
| 86 to 313 | 62 | $10.00 |
| 323 to 1,588 | 62 | $10.00 |
| 1,800 to 69,959.41 | 63 | $6.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 04 NOV 2026 | A00193012 | Beaumont District | 80 | $6.60 | $128.30 | $25.00 | 2 | TEXAS MATERIALS GROUP, INC. | TxDOT |
| 04 NOV 2026 | A00206631 | Bryan District | 175 | $15.00 | $9.50 | $10.00 | 7 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 04 NOV 2026 | A00212892 | Dallas District | 41,827 | $7.00 | $2.44 | $10.00 | 6 | INDUS ROAD & BRIDGE, INC. | TxDOT |
| 04 NOV 2026 | A00196925 | Paris District | 174 | $5.00 | $15.00 | $15.00 | 9 | HIGHWAY 19 CONSTRUCTION LLC | TxDOT |
| 04 NOV 2026 | A00129572 | Dallas District | 19,740 | $1.00 | $1.05 | $7.50 | 4 | MARIO SINACOLA & SONS EXCAVATING, INC. | TxDOT |
| 03 NOV 2026 | A00184974 | Austin District | 69,959.41 | $10.00 | $15.78 | $10.00 | 6 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 13 OCT 2026 | A00223040 | Tyler District | 162 | $10.00 | $10.00 | $25.00 | 7 | ICOS MANAGEMENT, LLC | TxDOT |
| 07 OCT 2026 | A00132124 | Lufkin District | 1,821 | $10.00 | $8.50 | $12.00 | 7 | LONGVIEW BRIDGE AND ROAD, LTD. | TxDOT |
| 07 OCT 2026 | A00187431 | Paris District | 824 | $15.00 | $13.87 | $10.00 | 6 | A. K. GILLIS & SONS, LLC | TxDOT |
| 07 OCT 2026 | A00064192 | San Antonio District | 1,575 | $28.03 | $10.00 | $6.50 | 8 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 06 OCT 2026 | A00195149 | Corpus Christi District | 232 | $20.00 | $14.00 | $15.00 | 7 | CK NEWBERRY, LLC | TxDOT |
| 06 OCT 2026 | A00186301 | Waco District | 14,187 | $10.00 | $4.20 | $6.00 | 6 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 06 OCT 2026 | A00066946 | Dallas District | 460 | $15.00 | $6.78 | $13.00 | 8 | A. K. GILLIS & SONS, LLC | TxDOT |
| 06 OCT 2026 | A00207643 | Paris District | 72 | $10.00 | $16.50 | $62.27 | 7 | HIGHWAY 19 CONSTRUCTION LLC | TxDOT |
| 03 SEP 2026 | A00184830 | Amarillo District | 75 | $50.00 | $50.00 | $30.00 | 7 | GILVIN-TERRILL, LTD. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.