Trf sig cbl (ty a)(12 awg)(3 condr) unit price, Texas

Low bidders on TxDOT contracts carried a median of $2.00 per LF for item 6846008, trf sig cbl (ty a)(12 awg)(3 condr), from 07 MAY 2020 to 09 JUL 2024, across 45 low bids. Half of all 168 bids fell between $1.77 and $2.79.

Owner
Texas DOT
Item
6846008
Unit
LF
Latest letting
09 JUL 2024
$2.00Low bidder's median, per LF
$2.05Median of all bids, per LF
45Contracts in the window
$2.00Engineer's estimate, median per LF

By year of letting

Trf sig cbl (ty a)(12 awg)(3 condr), TxDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20201212$1.8553$2.10
20211111$2.0037$2.00
202277$2.0021$2.25
202388$2.0228$2.02
202477$2.0029$2.25
Trf sig cbl (ty a)(12 awg)(3 condr), TxDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Trf sig cbl (ty a)(12 awg)(3 condr), TxDOT: unit prices by district, all lettings
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Laredo District9$1.9527$2.14
Paris District7$2.6922$2.80
Houston District4$1.9820$2.00
Fort Worth District3$2.7118$1.92
Lufkin District3$2.2914$2.65
Austin District4$2.0013$2.00
San Antonio District3$2.0012$2.02
Waco District3$2.0012$2.84
Trf sig cbl (ty a)(12 awg)(3 condr), TxDOT: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Trf sig cbl (ty a)(12 awg)(3 condr), TxDOT: low bidder's median by quantity band
Quantity (LF)Low bidsLow-bid median
30 to 13011$2.10
130 to 28411$2.00
295 to 1,51011$2.25
1,791 to 14,75312$2.00
Trf sig cbl (ty a)(12 awg)(3 condr), TxDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest TxDOT contracts carrying Trf sig cbl (ty a)(12 awg)(3 condr)
LetContractDistrictQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
09 JUL 202407243004Laredo District680$3.50$4.25$0.502HUNTER INDUSTRIES, LTD.TxDOT
03 MAY 202405243202Fort Worth District4,820$4.03$4.00$2.205ZACHRY CONSTRUCTION CORPORATIONTxDOT
03 MAY 202405243234Laredo District380$2.25$2.50$2.257TEXAS MATERIALS GROUP, INC.TxDOT
02 MAY 202405243002Laredo District95$1.80$1.77$2.502WEBBER, LLCTxDOT
06 MAR 202403243205Pharr District2,525$2.00$2.45$2.605TEXAS CORDIA CONSTRUCTION, LLCTxDOT
01 FEB 202402243025Austin District250$2.00$2.00$1.843AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.TxDOT
05 JAN 202401243209Pharr District420$1.94$2.00$2.205ASAGO, LLCTxDOT
01 NOV 202311233018Paris District470$3.00$3.50$1.912HIGHWAY 19 CONSTRUCTION LLCTxDOT
03 AUG 202308233201Paris District7,575$2.04$2.50$2.254SEMA CONSTRUCTION, INC.TxDOT
03 AUG 202308233272Laredo District30$1.95$2.12$1.952TRIPLE H FIELD SERVICES, LLCTxDOT
27 JUN 202306233403Houston District5,861$2.00$2.00$2.005MAIN LANE INDUSTRIES LTD.TxDOT
27 JUN 202306233404Houston District5,160$2.09$2.00$1.705BALFOUR BEATTY INFRASTRUCTURE, INC.TxDOT
27 JUN 202306233414Laredo District127$2.50$4.63$2.483ANDERSON COLUMBIA CO., INC.TxDOT
05 MAY 202305233237Paris District4,018$2.00$2.04$2.502NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTIONTxDOT
07 MAR 202303233001Houston District7,225$1.96$2.00$3.025WILLIAMS BROTHERS CONSTRUCTION CO., INC.TxDOT
Latest TxDOT contracts carrying Trf sig cbl (ty a)(12 awg)(3 condr)

Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.

How these prices were read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy