Trf sig cbl (ty a)(12 awg)(4 condr) unit price, Texas
Low bidders on TxDOT contracts carried a median of $3.00 per LF for item 684-7009, trf sig cbl (ty a)(12 awg)(4 condr), over the 24 months to 19 NOV 2026, across 53 low bids. Half of all 258 bids fell between $2.65 and $3.50.
- Owner
- Texas DOT
- Item
- 684-7009
- Unit
- LF
- Latest letting
- 03 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 1 | 1 | $2.40 | 7 | $2.25 |
| 2025 | 28 | 28 | $2.85 | 122 | $2.85 |
| 2026 | 25 | 25 | $3.00 | 136 | $3.09 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Houston District | 15 | $3.00 | 86 | $2.91 |
| San Antonio District | 15 | $3.00 | 84 | $3.00 |
| Pharr District | 3 | $1.50 | 17 | $2.80 |
| Laredo District | 5 | $2.50 | 14 | $2.92 |
| Beaumont District | 3 | $3.00 | 10 | $3.29 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 26 to 500 | 13 | $3.00 |
| 515 to 1,744 | 13 | $3.05 |
| 1,800 to 2,480 | 13 | $2.85 |
| 2,550 to 60,150 | 14 | $3.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 03 NOV 2026 | A00222928 | Houston District | 30,000 | $3.09 | $3.09 | $2.50 | 7 | TRAF-TEX, INC. | TxDOT |
| 07 OCT 2026 | A00064192 | San Antonio District | 2,480 | $2.20 | $2.32 | $2.89 | 8 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 03 SEP 2026 | A00206794 | San Antonio District | 670 | $4.16 | $3.75 | $2.72 | 6 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 03 SEP 2026 | A00206469 | Pharr District | 1,744 | $1.50 | $2.54 | $2.84 | 4 | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., LLC | TxDOT |
| 06 AUG 2026 | A00119935 | Laredo District | 6,245 | $1.95 | $3.20 | $2.00 | 4 | PULICE CONSTRUCTION, INC. | TxDOT |
| 05 AUG 2026 | A00068611 | Houston District | 635 | $3.10 | $2.78 | $2.00 | 7 | SER CONSTRUCTION PARTNERS, LLC | TxDOT |
| 01 JUL 2026 | A00217902 | Fort Worth District | 185 | $3.25 | $3.38 | $3.00 | 4 | JAY MILLS CONTRACTING, INCORPORATED | TxDOT |
| 01 JUL 2026 | A00184345 | Lubbock District | 40 | $3.50 | $3.50 | $5.30 | 3 | VACA UNDERGROUND UTILITIES INC | TxDOT |
| 01 JUL 2026 | A00058522 | Tyler District | 1,595 | $3.60 | $3.50 | n/a | 7 | DRAKE COMPANIES LLC | TxDOT |
| 03 JUN 2026 | A00186691 | San Antonio District | 171 | $3.20 | $4.35 | $3.00 | 6 | STX CIVIL | TxDOT |
| 03 JUN 2026 | A00206853 | Pharr District | 1,450 | $3.00 | $3.00 | $1.00 | 7 | CASTILLO ARANDA LLC | TxDOT |
| 03 JUN 2026 | A00132662 | Abilene District | 6,175 | $3.00 | $3.00 | $3.00 | 1 | FNF CONSTRUCTION, INC. | TxDOT |
| 03 JUN 2026 | A00193431 | San Antonio District | 2,130 | $4.00 | $3.92 | $3.50 | 10 | E-Z BEL CONSTRUCTION, LLC | TxDOT |
| 03 JUN 2026 | A00062698 | San Antonio District | 6,540 | $3.30 | $2.83 | $2.75 | 6 | JORDAN FOSTER CONSTRUCTION, LLC | TxDOT |
| 03 JUN 2026 | A00193911 | Houston District | 11,940 | $3.00 | $2.79 | $2.80 | 10 | DECO CONTRACTORS, INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.