Ty i high perf pm (w)6"(sld)(100MIL) unit price, Texas
Low bidders on TxDOT contracts carried a median of $0.80 per LF for item 666-7293, ty i high perf pm (w)6"(sld)(100mil), over the 24 months to 19 NOV 2026, across 115 low bids. Half of all 591 bids fell between $0.64 and $1.20.
- Owner
- Texas DOT
- Item
- 666-7293
- Unit
- LF
- Latest letting
- 04 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 10 | 10 | $0.96 | 47 | $1.00 |
| 2025 | 54 | 54 | $0.80 | 302 | $0.75 |
| 2026 | 55 | 55 | $0.78 | 263 | $0.90 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Waco District | 31 | $0.80 | 144 | $0.70 |
| Fort Worth District | 21 | $0.60 | 120 | $0.65 |
| Yoakum District | 16 | $1.09 | 89 | $1.00 |
| Lubbock District | 10 | $0.73 | 51 | $0.75 |
| Wichita Falls District | 6 | $0.75 | 33 | $0.70 |
| San Angelo District | 7 | $0.82 | 30 | $0.75 |
| Houston District | 5 | $1.20 | 24 | $1.20 |
| San Antonio District | 3 | $1.00 | 19 | $0.80 |
| Amarillo District | 3 | $0.85 | 15 | $0.98 |
| Corpus Christi District | 4 | $1.23 | 12 | $2.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 36 to 4,000 | 28 | $1.70 |
| 4,020 to 15,677 | 29 | $1.00 |
| 16,403 to 55,007 | 29 | $0.70 |
| 57,545 to 2,187,158 | 29 | $0.68 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 04 NOV 2026 | A00209149 | Laredo District | 760 | $3.32 | $2.90 | $0.78 | 7 | STX CIVIL | TxDOT |
| 04 NOV 2026 | A00224201 | Waco District | 4,000 | $1.20 | $1.20 | $1.05 | 3 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 04 NOV 2026 | A00224204 | Waco District | 12,000 | $0.70 | $0.70 | $1.03 | 3 | TEXAS MATERIALS GROUP, INC. | TxDOT |
| 03 NOV 2026 | A00224202 | Waco District | 45,000 | $0.70 | $0.82 | $0.95 | 4 | TEXAS MATERIALS GROUP, INC. | TxDOT |
| 03 NOV 2026 | A00224203 | Waco District | 2,000 | $1.85 | $1.48 | $1.75 | 4 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 07 OCT 2026 | A00209263 | Waco District | 180,847 | $0.52 | $0.52 | $0.55 | 5 | NORTHEASTERN PAVERS, LLC | TxDOT |
| 07 OCT 2026 | A00211436 | Amarillo District | 2,715 | $2.48 | $2.48 | n/a | 5 | GIBSON & ASSOCIATES, INC. | TxDOT |
| 07 OCT 2026 | A00131942 | San Angelo District | 260 | $0.54 | $0.60 | $0.84 | 7 | FLAT LINE, INC. | TxDOT |
| 06 OCT 2026 | A00186301 | Waco District | 18,621 | $0.75 | $0.73 | $1.00 | 6 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 28 SEP 2026 | A00223925 | Fort Worth District | 650 | $3.00 | $4.00 | $1.00 | 2 | TEXWAY WASTEWATER SERVICES, LLC | TxDOT |
| 03 SEP 2026 | A00184830 | Amarillo District | 17,705 | $0.85 | $0.95 | $0.70 | 7 | GILVIN-TERRILL, LTD. | TxDOT |
| 06 AUG 2026 | A00195300 | Wichita Falls District | 108,525 | $0.62 | $0.58 | $0.74 | 5 | A. L. HELMCAMP, INC. | TxDOT |
| 06 AUG 2026 | A00193006 | Amarillo District | 131,234 | $0.70 | $0.68 | $0.70 | 3 | J. LEE MILLIGAN, INC. | TxDOT |
| 06 AUG 2026 | A00136986 | San Antonio District | 3,768 | $0.75 | $0.78 | $1.00 | 8 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 06 AUG 2026 | A00220224 | Fort Worth District | 21,700 | $0.56 | $0.60 | $0.55 | 5 | FOUTSCO PAVING COMPANY, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.