Wk zn pav mrk sht term rmv (w)(4") unit price, Texas
Low bidders on TxDOT contracts carried a median of $1.41 per LF for item 6626112, wk zn pav mrk sht term rmv (w)(4"), from 09 JAN 2020 to 09 JUL 2024, across 48 low bids. Half of all 187 bids fell between $1.06 and $2.00.
- Owner
- Texas DOT
- Item
- 6626112
- Unit
- LF
- Latest letting
- 09 JUL 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 11 | 11 | $1.25 | 47 | $1.35 |
| 2021 | 15 | 14 | $1.40 | 68 | $1.40 |
| 2022 | 17 | 14 | $1.50 | 45 | $1.50 |
| 2023 | 5 | 5 | $1.75 | 14 | $2.00 |
| 2024 | 4 | 4 | $2.50 | 13 | $2.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Tyler District | 18 | $1.53 | 71 | $1.50 |
| Austin District | 10 | $1.25 | 50 | $1.25 |
| Lufkin District | 12 | $1.25 | 34 | $1.25 |
| Atlanta District | 5 | $1.55 | 17 | $1.55 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 170 to 1,000 | 12 | $2.00 |
| 1,035 to 3,141 | 12 | $1.27 |
| 3,300 to 4,970 | 12 | $1.40 |
| 5,139 to 43,757 | 12 | $1.30 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 09 JUL 2024 | 07243024 | Austin District | 200 | $2.00 | $2.00 | $1.17 | 5 | TEXAS MATERIALS GROUP, INC. | TxDOT |
| 05 JUN 2024 | 06243034 | Lufkin District | 226 | $3.00 | $3.00 | $3.00 | 1 | TEXAS MATERIALS GROUP, INC. | TxDOT |
| 05 JAN 2024 | 01243210 | Atlanta District | 4,234 | $5.80 | $2.20 | $0.50 | 3 | RK HALL, LLC | TxDOT |
| 04 JAN 2024 | 01243034 | Austin District | 4,752 | $1.17 | $1.11 | $1.30 | 4 | CLARK CONSTRUCTION OF TEXAS, INC. | TxDOT |
| 06 SEP 2023 | 09233007 | Tyler District | 3,754 | $3.00 | $2.50 | $1.59 | 2 | FNH CONSTRUCTION, LLC | TxDOT |
| 06 SEP 2023 | 09233011 | Lufkin District | 43,757 | $1.25 | $1.25 | $1.50 | 1 | TEXAS MATERIALS GROUP, INC. | TxDOT |
| 27 JUN 2023 | 06233409 | Odessa District | 1,290 | $2.64 | $2.82 | $1.30 | 4 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 08 MAR 2023 | 03233221 | Tyler District | 3,474 | $1.75 | $1.88 | $1.50 | 4 | MADDEN CONTRACTING COMPANY, LLC. | TxDOT |
| 07 MAR 2023 | 03233011 | Tyler District | 540 | $1.20 | $2.00 | $1.00 | 3 | H. V. CAVER, INC. | TxDOT |
| 02 DEC 2022 | 12223207 | Lufkin District | 9,230 | $1.00 | $1.00 | $0.50 | 1 | MOORE BROTHERS CONSTRUCTION COMPANY | TxDOT |
| 02 NOV 2022 | 11223013 | Austin District | 2,525 | $1.50 | $1.47 | $1.50 | 4 | LONE STAR PAVING COMPANY | TxDOT |
| 02 NOV 2022 | 11223024 | Austin District | 1,000 | $1.50 | $1.75 | $1.10 | 3 | LONE STAR PAVING COMPANY | TxDOT |
| 08 SEP 2022 | 09223218 | Tyler District | 10,540 | n/a | $1.65 | $1.50 | 3 | MADDEN CONTRACTING COMPANY, LLC. | TxDOT |
| 07 SEP 2022 | 09223010 | Tyler District | 23,926 | n/a | $1.60 | $1.20 | 4 | MADDEN CONTRACTING COMPANY, LLC. | TxDOT |
| 07 SEP 2022 | 09223025 | Atlanta District | 71,280 | n/a | $1.98 | $1.50 | 2 | MADDEN CONTRACTING COMPANY, LLC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.