Ns select material alternate shoulder material unit price, Virginia
Low bidders on VDOT contracts carried a median of $59.01 per TON for item 305SX20-0006, ns select material alternate shoulder material, over the 24 months to 28 OCT 2026, across 44 low bids. Half of all 121 bids fell between $49.00 and $79.00.
- Owner
- Virginia DOT
- Item
- 305SX20-0006
- Unit
- TON
- Latest letting
- 22 JUL 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2025 | 20 | 17 | $55.80 | 51 | $55.00 |
| 2026 | 32 | 27 | $60.00 | 70 | $61.80 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Richmond | 11 | $53.00 | 34 | $66.51 |
| Fredericksburg | 10 | $61.25 | 31 | $60.00 |
| Staunton | 7 | $68.00 | 19 | $53.55 |
| Lynchburg | 7 | $60.00 | 16 | $60.80 |
| Salem | 4 | $62.90 | 11 | $70.00 |
| Bristol | 5 | $50.00 | 10 | $49.30 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 11 | $55.80 |
| 1 to 1 | 11 | $53.00 |
| 1 to 1 | 11 | $53.00 |
| 1 to 1 | 11 | $70.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 22 JUL 2026 | CM127PMF129009 | Bristol | 1 | $56.00 | $61.50 | 2 | BIZZACK CONSTRUCTION, LLC | VDOT |
| 22 JUL 2026 | CM227PMM128888 | Salem | 1 | n/a | $74.50 | 1 | ADAMS CONSTRUCTION COMPANY | VDOT |
| 22 JUL 2026 | CM327PMG128967 | Lynchburg | 1 | $60.00 | $60.00 | 3 | ADAMS CONSTRUCTION COMPANY | VDOT |
| 22 JUL 2026 | CM427PMJ129176 | Richmond | 1 | $75.00 | $75.00 | 3 | ALLAN MYERS VA, INC. | VDOT |
| 22 JUL 2026 | CM427PMK129177 | Richmond | 1 | $84.00 | $84.00 | 3 | ALLAN MYERS VA, INC. | VDOT |
| 25 FEB 2026 | CM226PMF127369B | Salem | 1 | $70.00 | $70.00 | 1 | ADAMS CONSTRUCTION COMPANY | VDOT |
| 04 FEB 2026 | CM126PMD127275 | Bristol | 1 | $41.00 | $42.50 | 2 | W-L CONSTRUCTION & PAVING, INC. | VDOT |
| 04 FEB 2026 | CM126PMF127279 | Bristol | 1 | $50.00 | $49.25 | 2 | W-L CONSTRUCTION & PAVING, INC. | VDOT |
| 04 FEB 2026 | CM226PMH127370 | Salem | 1 | n/a | $65.00 | 1 | ADAMS CONSTRUCTION COMPANY | VDOT |
| 04 FEB 2026 | CM226PMK127371 | Salem | 1 | n/a | $115.00 | 1 | ADAMS CONSTRUCTION COMPANY | VDOT |
| 04 FEB 2026 | CM226PML127372 | Salem | 1 | $28.20 | $50.23 | 2 | ADAMS CONSTRUCTION COMPANY | VDOT |
| 04 FEB 2026 | CM326PMF127088 | Lynchburg | 1 | $65.00 | $66.37 | 2 | SUPERIOR PAVING CORPORATION | VDOT |
| 04 FEB 2026 | CM326PME127086 | Lynchburg | 1 | $57.00 | $57.00 | 1 | ADAMS CONSTRUCTION COMPANY | VDOT |
| 04 FEB 2026 | CM426PM5127962 | Richmond | 1 | $43.00 | $82.54 | 2 | ALLAN MYERS VA, INC. | VDOT |
| 04 FEB 2026 | CM426PMC127947 | Richmond | 1 | $115.00 | $115.55 | 2 | ALLAN MYERS VA, INC. | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.