Beam guardrail block unit price, Washington
Low bidders on WSDOT contracts carried a median of $11.50 per EACH for beam guardrail block, from 28 MAR 2007 to 01 MAR 2023, across 47 low bids. Half of all 144 bids fell between $9.50 and $35.50.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- EACH
- Latest letting
- 01 MAR 2023
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2007 | 1 | 1 | $8.50 | 4 | $9.00 |
| 2008 | 4 | 4 | $7.83 | 14 | $7.83 |
| 2009 | 3 | 3 | $9.00 | 6 | $9.00 |
| 2010 | 6 | 6 | $10.00 | 20 | $10.55 |
| 2011 | 2 | 2 | $7.17 | 7 | $7.80 |
| 2012 | 2 | 2 | $8.38 | 5 | $10.00 |
| 2013 | 2 | 2 | $20.00 | 6 | $13.50 |
| 2014 | 2 | 2 | $19.50 | 7 | $25.00 |
| 2015 | 2 | 2 | $10.00 | 5 | $10.00 |
| 2016 | 3 | 3 | $10.75 | 11 | $35.00 |
| 2017 | 3 | 3 | $15.00 | 6 | $15.00 |
| 2018 | 4 | 4 | $23.50 | 14 | $22.00 |
| 2019 | 5 | 5 | $30.00 | 14 | $35.00 |
| 2020 | 2 | 2 | $57.50 | 10 | $45.00 |
| 2021 | 1 | 1 | $30.00 | 2 | $30.00 |
| 2022 | 3 | 3 | $50.00 | 7 | $55.00 |
| 2023 | 2 | 2 | $45.00 | 6 | $60.50 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| ER region | 17 | $22.00 | 52 | $21.00 |
| NCR region | 12 | $20.75 | 38 | $27.50 |
| SCR region | 8 | $12.50 | 24 | $15.50 |
| OR region | 5 | $8.25 | 16 | $8.50 |
| NWR region | 3 | $10.00 | 7 | $13.00 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 3 to 19 | 11 | $30.00 |
| 19 to 35 | 12 | $23.50 |
| 40 to 100 | 12 | $10.00 |
| 100 to 1,646 | 12 | $10.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 01 MAR 2023 | 009938 | ER region | 41 | $60.00 | $65.00 | $35.00 | 3 | CENTRAL WASHINGTON ASPHALT, IN | WSDOT |
| 23 FEB 2023 | 009934 | NCR region | 14 | $30.00 | $30.00 | $35.00 | 3 | CENTRAL WASHINGTON ASPHALT, INC.INTERSTATE CONCRETE & ASPHALT | WSDOT |
| 09 FEB 2022 | 009765 | ER region | 15 | $37.00 | $64.00 | $30.00 | 2 | SHAMROCK PAVING, INC. | WSDOT |
| 12 JAN 2022 | 009756 | NCR region | 35 | $50.00 | $50.00 | $40.00 | 3 | CPM DEVELOPMENT CORPORATION | WSDOT |
| 05 JAN 2022 | 009752 | NCR region | 19 | $59.00 | $58.00 | $38.00 | 2 | CENTRAL WASHINGTON ASPHALT, IN | WSDOT |
| 27 JAN 2021 | 009638 | NCR region | 19 | $30.00 | $30.00 | $40.00 | 2 | CENTRAL WASHINGTON ASPHALT, INC.INTERSTATE CONCRETE & ASPHALT | WSDOT |
| 01 APR 2020 | 009533 | SCR region | 8 | $40.00 | $45.00 | $40.00 | 5 | KRCI LLC | WSDOT |
| 11 MAR 2020 | 009528 | NCR region | 25 | $75.00 | $45.00 | $30.00 | 5 | CORAL CONSTRUCTION COMPANY | WSDOT |
| 17 APR 2019 | 009400 | ER region | 20 | $27.00 | $28.50 | $10.00 | 2 | CPM DEVELOPMENT CORPORATION | WSDOT |
| 20 MAR 2019 | 009407 | ER region | 508 | $105.00 | $105.00 | $20.00 | 3 | CENTRAL WASHINGTON ASPHALT, IN | WSDOT |
| 20 MAR 2019 | 009404 | ER region | 504 | $30.00 | $40.00 | $10.00 | 2 | DIRT AND AGGREGATE INTERCHANGE | WSDOT |
| 06 FEB 2019 | 009377 | ER region | 374 | $10.00 | $19.00 | $10.00 | 3 | SHAMROCK PAVING, INC. | WSDOT |
| 24 JAN 2019 | 009369 | ER region | 10 | $75.00 | $44.40 | $35.00 | 4 | SHAMROCK PAVING, INC. | WSDOT |
| 21 MAR 2018 | 009224 | ER region | 71 | $50.00 | $50.00 | $15.00 | 3 | CENTRAL WASHINGTON ASPHALT, IN | WSDOT |
| 14 MAR 2018 | 009223 | ER region | 400 | $10.00 | $10.00 | $25.00 | 3 | SHAMROCK PAVING, INC. | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way