Cement conc. pavement unit price, Washington
Low bidders on WSDOT contracts carried a median of $620.00 per CY for cement conc. pavement, over the 24 months to 07 OCT 2026, across 1 low bids. Half of all 4 bids fell between $510.90 and $691.88.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- CY
- Latest letting
- 08 JUL 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2000 | 1 | 1 | $170.00 | 6 | $135.00 |
| 2001 | 2 | 2 | $595.00 | 4 | $350.00 |
| 2003 | 1 | 1 | $150.00 | 8 | $174.50 |
| 2005 | 1 | 1 | $107.75 | 5 | $113.00 |
| 2007 | 4 | 4 | $253.75 | 17 | $306.60 |
| 2008 | 2 | 2 | $249.50 | 12 | $181.75 |
| 2009 | 4 | 4 | $401.00 | 17 | $398.00 |
| 2010 | 9 | 9 | $190.00 | 54 | $185.00 |
| 2011 | 4 | 4 | $250.00 | 32 | $210.50 |
| 2013 | 1 | 1 | $158.26 | 6 | $238.00 |
| 2014 | 3 | 3 | $260.00 | 16 | $285.00 |
| 2015 | 7 | 7 | $750.00 | 27 | $650.00 |
| 2016 | 1 | 1 | $167.10 | 2 | $183.55 |
| 2017 | 3 | 3 | $350.00 | 12 | $233.72 |
| 2018 | 4 | 4 | $462.50 | 13 | $420.00 |
| 2019 | 2 | 2 | $405.00 | 6 | $238.83 |
| 2020 | 1 | 1 | $720.00 | 5 | $630.00 |
| 2021 | 1 | 1 | $326.00 | 4 | $338.00 |
| 2023 | 3 | 3 | $1,017.00 | 12 | $1,133.50 |
| 2026 | 1 | 1 | $620.00 | 4 | $567.27 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| NWR region | 27 | $325.00 | 141 | $278.00 |
| SCR region | 13 | $198.00 | 69 | $195.00 |
| ER region | 8 | $211.25 | 28 | $204.00 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 4.20 to 75 | 13 | $850.00 |
| 83.80 to 1,303 | 14 | $322.00 |
| 1,310.40 to 3,941 | 14 | $205.05 |
| 4,025 to 43,298.70 | 14 | $173.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 08 JUL 2026 | XE3751 | SCR region | 155 | $620.00 | $567.27 | $450.00 | 4 | TAPANI, INC. | WSDOT |
| 29 MAR 2023 | 009941 | OR region | 5 | $1,305.00 | $1,125.00 | $500.00 | 6 | JOHANSEN CONSTRUCTION COMPANY, | WSDOT |
| 23 FEB 2023 | 009932 | NWR region | 38 | $1,017.00 | $1,800.00 | $500.00 | 4 | FABER CONSTRUCTION CORP. | WSDOT |
| 23 FEB 2023 | 009925 | ER region | 4,025 | $420.00 | $385.00 | $365.00 | 2 | MAX J. KUNEY COMPANY | WSDOT |
| 21 APR 2021 | 009662 | NWR region | 3,446 | $326.00 | $338.00 | $375.00 | 4 | SCARSELLA BROS., INC. | WSDOT |
| 05 FEB 2020 | 009501 | NWR region | 84 | $720.00 | $630.00 | $750.00 | 5 | TITAN EARTHWORK LLC | WSDOT |
| 13 MAR 2019 | 009385 | SCR region | 7,039 | $320.00 | $237.67 | $245.00 | 5 | MAX J. KUNEY COMPANY | WSDOT |
| 06 FEB 2019 | 009361 | NWR region | 664 | $490.00 | $490.00 | $400.00 | 1 | C.A. CAREY CORPORATION | WSDOT |
| 25 APR 2018 | 009258 | ER region | 258.40 | $280.00 | $290.00 | $300.00 | 2 | CPM DEVELOPMENT CORPORATION | WSDOT |
| 18 APR 2018 | 009233 | NWR region | 178.70 | $800.00 | $1,550.00 | $850.00 | 2 | A-1 LANDSCAPING AND CONSTRUCTI | WSDOT |
| 07 FEB 2018 | 009196 | SCR region | 662.40 | $385.00 | $387.30 | $450.00 | 6 | CENTRAL WASHINGTON ASPHALT, IN | WSDOT |
| 18 JAN 2018 | 009189 | ER region | 75 | $540.00 | $570.00 | $300.00 | 3 | SHAMROCK PAVING, INC. | WSDOT |
| 15 FEB 2017 | 009026 | SCR region | 1,571.50 | $350.00 | $350.00 | $315.00 | 3 | KIEWIT INFRASTRUCTURE WEST CO. | WSDOT |
| 25 JAN 2017 | 009011 | ER region | 1,303 | $205.00 | $212.50 | $215.00 | 7 | MAX J. KUNEY COMPANY | WSDOT |
| 25 JAN 2017 | 009006 | NCR region | 98 | $748.00 | $724.00 | $1,000.00 | 2 | GRANITE CONSTRUCTION COMPANY | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.