End, gate, corner, and pull post for chain link fence unit price, Washington

Low bidders on WSDOT contracts carried a median of $222.50 per EACH for end, gate, corner, and pull post for chain link fence, from 23 JAN 2003 to 23 FEB 2023, across 70 low bids. Half of all 440 bids fell between $150.00 and $300.00.

Owner
Washington State DOT
Item
No code published
Unit
EACH
Latest letting
23 FEB 2023
$222.50Low bidder's median, per EACH
$215.00Median of all bids, per EACH
70Contracts in the window
$211.00Engineer's estimate, median per EACH

By year of letting

End, gate, corner, and pull post for chain link fence, WSDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
200355$110.0032$110.00
200477$150.0041$175.00
200544$192.5019$228.00
200633$300.0014$177.50
200755$200.0032$207.00
200888$240.0051$250.00
200977$168.5066$175.00
201044$250.0025$300.00
201144$215.0025$200.00
201222$460.0013$281.95
201344$215.0031$210.00
201433$250.0024$250.00
201511$2,500.003$300.00
201622$718.7012$300.00
201711$245.006$247.50
201822$187.508$410.00
201922$223.258$286.25
202011$500.008$287.50
202122$404.636$265.00
202211$320.007$330.00
202322$400.009$492.50
End, gate, corner, and pull post for chain link fence, WSDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By region

End, gate, corner, and pull post for chain link fence, WSDOT: unit prices by region, all lettings
RegionLow bidsLow-bid medianAll bidsMedian, all bids
NWR region36$210.00245$200.00
OR region7$250.0057$260.00
SWR region6$178.2543$135.00
ER region9$300.0033$281.95
SCR region7$300.0030$317.50
End, gate, corner, and pull post for chain link fence, WSDOT: unit prices by region, all lettings

Regions with at least three low bids, over all lettings.

By quantity

End, gate, corner, and pull post for chain link fence, WSDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 317$300.00
3 to 818$247.50
8 to 1917$200.00
21 to 10118$161.75
End, gate, corner, and pull post for chain link fence, WSDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest WSDOT contracts carrying End, gate, corner, and pull post for chain link fence
LetContractRegionQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
23 FEB 2023009925ER region24$400.00$400.00$280.002MAX J. KUNEY COMPANYWSDOT
19 JAN 2023009891OR region4$400.00$550.00$658.007CECCANTI, INC.WSDOT
09 FEB 2022009763OR region4$320.00$330.00$315.007KRAEMER NORTH AMERICA, LLC.WSDOT
21 APR 2021009662NWR region12$250.00$250.00$275.004SCARSELLA BROS., INC.WSDOT
03 FEB 2021009632SCR region4$559.27$542.13$300.002MORENO & NELSON CONSTRUCTIONWSDOT
20 FEB 2020009516OR region38$500.00$287.50$227.008INTERWEST CONSTRUCTION, INC.WSDOT
13 MAR 2019009374NWR region7$272.50$300.00$350.007MARSHBANK CONSTRUCTION, INC.WSDOT
06 FEB 2019009361NWR region10$174.00$174.00$200.001C.A. CAREY CORPORATIONWSDOT
25 APR 2018009258ER region2$325.00$362.50$225.002CPM DEVELOPMENT CORPORATIONWSDOT
07 FEB 2018009196SCR region4$50.00$460.00$500.006CENTRAL WASHINGTON ASPHALT, INWSDOT
01 FEB 2017009010NCR region3$245.00$247.50$205.006STRIDER CONSTRUCTION CO., INC.WSDOT
02 MAR 2016008843SCR region3$1,122.87$648.93$500.002ACME CONCRETE PAVING, INC.WSDOT
13 JAN 2016008831NWR region8$314.53$300.00$280.0010FABER CONSTRUCTION CORP.WSDOT
25 FEB 2015008702Region 95$2,500.00$300.00$250.003LAKESIDE INDUSTRIES, INC.WSDOT
03 DEC 2014008685OR region14$250.00$250.00$300.0015SELBY BRIDGE COMPANY, INC.WSDOT
Latest WSDOT contracts carrying End, gate, corner, and pull post for chain link fence

Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.

How these prices were read

WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy