End, gate, corner, and pull post for chain link fence unit price, Washington
Low bidders on WSDOT contracts carried a median of $222.50 per EACH for end, gate, corner, and pull post for chain link fence, from 23 JAN 2003 to 23 FEB 2023, across 70 low bids. Half of all 440 bids fell between $150.00 and $300.00.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- EACH
- Latest letting
- 23 FEB 2023
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2003 | 5 | 5 | $110.00 | 32 | $110.00 |
| 2004 | 7 | 7 | $150.00 | 41 | $175.00 |
| 2005 | 4 | 4 | $192.50 | 19 | $228.00 |
| 2006 | 3 | 3 | $300.00 | 14 | $177.50 |
| 2007 | 5 | 5 | $200.00 | 32 | $207.00 |
| 2008 | 8 | 8 | $240.00 | 51 | $250.00 |
| 2009 | 7 | 7 | $168.50 | 66 | $175.00 |
| 2010 | 4 | 4 | $250.00 | 25 | $300.00 |
| 2011 | 4 | 4 | $215.00 | 25 | $200.00 |
| 2012 | 2 | 2 | $460.00 | 13 | $281.95 |
| 2013 | 4 | 4 | $215.00 | 31 | $210.00 |
| 2014 | 3 | 3 | $250.00 | 24 | $250.00 |
| 2015 | 1 | 1 | $2,500.00 | 3 | $300.00 |
| 2016 | 2 | 2 | $718.70 | 12 | $300.00 |
| 2017 | 1 | 1 | $245.00 | 6 | $247.50 |
| 2018 | 2 | 2 | $187.50 | 8 | $410.00 |
| 2019 | 2 | 2 | $223.25 | 8 | $286.25 |
| 2020 | 1 | 1 | $500.00 | 8 | $287.50 |
| 2021 | 2 | 2 | $404.63 | 6 | $265.00 |
| 2022 | 1 | 1 | $320.00 | 7 | $330.00 |
| 2023 | 2 | 2 | $400.00 | 9 | $492.50 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| NWR region | 36 | $210.00 | 245 | $200.00 |
| OR region | 7 | $250.00 | 57 | $260.00 |
| SWR region | 6 | $178.25 | 43 | $135.00 |
| ER region | 9 | $300.00 | 33 | $281.95 |
| SCR region | 7 | $300.00 | 30 | $317.50 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 3 | 17 | $300.00 |
| 3 to 8 | 18 | $247.50 |
| 8 to 19 | 17 | $200.00 |
| 21 to 101 | 18 | $161.75 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 23 FEB 2023 | 009925 | ER region | 24 | $400.00 | $400.00 | $280.00 | 2 | MAX J. KUNEY COMPANY | WSDOT |
| 19 JAN 2023 | 009891 | OR region | 4 | $400.00 | $550.00 | $658.00 | 7 | CECCANTI, INC. | WSDOT |
| 09 FEB 2022 | 009763 | OR region | 4 | $320.00 | $330.00 | $315.00 | 7 | KRAEMER NORTH AMERICA, LLC. | WSDOT |
| 21 APR 2021 | 009662 | NWR region | 12 | $250.00 | $250.00 | $275.00 | 4 | SCARSELLA BROS., INC. | WSDOT |
| 03 FEB 2021 | 009632 | SCR region | 4 | $559.27 | $542.13 | $300.00 | 2 | MORENO & NELSON CONSTRUCTION | WSDOT |
| 20 FEB 2020 | 009516 | OR region | 38 | $500.00 | $287.50 | $227.00 | 8 | INTERWEST CONSTRUCTION, INC. | WSDOT |
| 13 MAR 2019 | 009374 | NWR region | 7 | $272.50 | $300.00 | $350.00 | 7 | MARSHBANK CONSTRUCTION, INC. | WSDOT |
| 06 FEB 2019 | 009361 | NWR region | 10 | $174.00 | $174.00 | $200.00 | 1 | C.A. CAREY CORPORATION | WSDOT |
| 25 APR 2018 | 009258 | ER region | 2 | $325.00 | $362.50 | $225.00 | 2 | CPM DEVELOPMENT CORPORATION | WSDOT |
| 07 FEB 2018 | 009196 | SCR region | 4 | $50.00 | $460.00 | $500.00 | 6 | CENTRAL WASHINGTON ASPHALT, IN | WSDOT |
| 01 FEB 2017 | 009010 | NCR region | 3 | $245.00 | $247.50 | $205.00 | 6 | STRIDER CONSTRUCTION CO., INC. | WSDOT |
| 02 MAR 2016 | 008843 | SCR region | 3 | $1,122.87 | $648.93 | $500.00 | 2 | ACME CONCRETE PAVING, INC. | WSDOT |
| 13 JAN 2016 | 008831 | NWR region | 8 | $314.53 | $300.00 | $280.00 | 10 | FABER CONSTRUCTION CORP. | WSDOT |
| 25 FEB 2015 | 008702 | Region 9 | 5 | $2,500.00 | $300.00 | $250.00 | 3 | LAKESIDE INDUSTRIES, INC. | WSDOT |
| 03 DEC 2014 | 008685 | OR region | 14 | $250.00 | $250.00 | $300.00 | 15 | SELBY BRIDGE COMPANY, INC. | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.