Hma cl. 1/2 in. pg 64-22 unit price, Washington
Low bidders on WSDOT contracts carried a median of $79.00 per TON for hma cl. 1/2 in. pg 64-22, from 10 MAR 2004 to 19 JAN 2023, across 213 low bids. Half of all 1,082 bids fell between $69.00 and $106.75.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- TON
- Latest letting
- 19 JAN 2023
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2004 | 6 | 6 | $61.50 | 33 | $56.50 |
| 2005 | 14 | 14 | $48.08 | 64 | $50.50 |
| 2006 | 8 | 8 | $80.00 | 28 | $71.50 |
| 2007 | 14 | 14 | $72.50 | 73 | $75.00 |
| 2008 | 6 | 6 | $70.83 | 38 | $73.02 |
| 2009 | 16 | 16 | $74.50 | 101 | $75.99 |
| 2010 | 17 | 17 | $61.80 | 115 | $65.00 |
| 2011 | 12 | 12 | $64.75 | 67 | $66.00 |
| 2012 | 8 | 8 | $88.50 | 47 | $82.50 |
| 2013 | 15 | 15 | $85.75 | 77 | $103.00 |
| 2014 | 11 | 11 | $81.00 | 69 | $85.00 |
| 2015 | 20 | 20 | $87.00 | 81 | $97.00 |
| 2016 | 26 | 26 | $104.75 | 137 | $103.00 |
| 2017 | 28 | 28 | $87.60 | 112 | $97.00 |
| 2018 | 8 | 8 | $129.62 | 26 | $122.50 |
| 2019 | 1 | 1 | $97.00 | 2 | $124.00 |
| 2020 | 1 | 1 | $520.00 | 3 | $520.00 |
| 2022 | 1 | 1 | $750.00 | 2 | $637.50 |
| 2023 | 1 | 1 | $165.00 | 7 | $170.25 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| NWR region | 130 | $78.38 | 642 | $80.90 |
| OR region | 39 | $83.00 | 208 | $82.00 |
| SWR region | 24 | $65.20 | 144 | $68.76 |
| NCR region | 8 | $167.50 | 44 | $162.50 |
| Region 9 | 10 | $192.50 | 33 | $180.00 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 2 to 660 | 53 | $150.00 |
| 680 to 4,300 | 53 | $83.00 |
| 4,339 to 11,400 | 53 | $71.75 |
| 11,660 to 130,040 | 54 | $65.20 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 19 JAN 2023 | 009891 | OR region | 7,280 | $165.00 | $170.25 | $131.00 | 7 | CECCANTI, INC. | WSDOT |
| 13 APR 2022 | 009785 | Region 9 | 25 | $750.00 | $637.50 | $575.00 | 2 | NORTHWEST CASCADE, INC. | WSDOT |
| 12 FEB 2020 | 009522 | Region 9 | 41 | $520.00 | $520.00 | $600.00 | 3 | GRANITE CONSTRUCTION COMPANY | WSDOT |
| 06 MAR 2019 | 009393 | Region 9 | 1,440 | $97.00 | $124.00 | $140.00 | 2 | LAKESIDE INDUSTRIES, INC. | WSDOT |
| 28 FEB 2018 | 009218 | NWR region | 1,150 | $100.61 | $106.00 | $100.00 | 5 | TIGER CONSTRUCTION, LTD. | WSDOT |
| 22 FEB 2018 | 009198 | NWR region | 15,151 | $100.00 | $100.00 | $85.00 | 2 | CADMAN MATERIALS, INC. | WSDOT |
| 14 FEB 2018 | 009208 | Region 9 | 500 | $205.00 | $252.50 | $250.00 | 2 | C.A. CAREY CORPORATION | WSDOT |
| 14 FEB 2018 | 009182 | NWR region | 3,730 | $79.00 | $110.00 | $97.00 | 5 | TUCCI & SONS, INC. | WSDOT |
| 29 JAN 2018 | 009195 | NWR region | 8,030 | $120.00 | $112.50 | $85.00 | 2 | GRANITE CONSTRUCTION COMPANY | WSDOT |
| 18 JAN 2018 | 009192 | NWR region | 220 | $145.00 | $178.00 | $180.00 | 4 | NORTHWEST CONSTRUCTION, INC. | WSDOT |
| 18 JAN 2018 | 009193 | NWR region | 380 | $250.00 | $260.00 | $300.00 | 2 | GRANITE CONSTRUCTION COMPANY | WSDOT |
| 10 JAN 2018 | 009194 | NWR region | 1,030 | $139.25 | $139.62 | $100.00 | 4 | ROAD CONSTRUCTION NORTHWEST, I | WSDOT |
| 13 DEC 2017 | 009180 | NWR region | 16,990 | $81.00 | $88.00 | $85.00 | 2 | LAKESIDE INDUSTRIES, INC. | WSDOT |
| 13 DEC 2017 | 009177 | NWR region | 15,440 | $92.00 | $95.00 | $80.00 | 3 | TAPANI, INC. | WSDOT |
| 13 DEC 2017 | 009172 | NWR region | 1,888 | $92.00 | $95.50 | $95.00 | 8 | COLACURCIO BROTHERS, INC. | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.