Mailbox support type 1 unit price, Washington
Low bidders on WSDOT contracts carried a median of $300.00 per EACH for mailbox support type 1, from 11 JAN 2001 to 01 FEB 2023, across 89 low bids. Half of all 511 bids fell between $227.00 and $400.00.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- EACH
- Latest letting
- 01 FEB 2023
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2001 | 2 | 2 | $152.50 | 9 | $150.00 |
| 2002 | 8 | 8 | $197.50 | 30 | $220.00 |
| 2003 | 3 | 3 | $200.00 | 18 | $205.00 |
| 2004 | 5 | 5 | $200.00 | 24 | $220.00 |
| 2005 | 6 | 6 | $187.50 | 28 | $250.00 |
| 2006 | 9 | 9 | $275.00 | 39 | $260.00 |
| 2007 | 9 | 9 | $295.00 | 43 | $300.00 |
| 2008 | 8 | 8 | $262.50 | 54 | $305.00 |
| 2009 | 5 | 5 | $300.00 | 32 | $300.00 |
| 2010 | 9 | 9 | $300.00 | 62 | $300.00 |
| 2011 | 3 | 3 | $420.00 | 27 | $500.00 |
| 2012 | 2 | 2 | $375.00 | 16 | $400.00 |
| 2013 | 4 | 4 | $350.00 | 31 | $350.00 |
| 2014 | 3 | 3 | $350.00 | 34 | $375.00 |
| 2016 | 2 | 2 | $500.00 | 13 | $500.00 |
| 2017 | 2 | 2 | $350.00 | 9 | $350.00 |
| 2018 | 2 | 2 | $655.12 | 7 | $600.00 |
| 2019 | 1 | 1 | $839.00 | 3 | $839.00 |
| 2020 | 1 | 1 | $1,450.00 | 5 | $425.00 |
| 2021 | 3 | 3 | $373.70 | 16 | $550.00 |
| 2023 | 2 | 2 | $1,325.00 | 11 | $1,250.00 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| NWR region | 36 | $300.00 | 220 | $319.50 |
| OR region | 21 | $300.00 | 126 | $300.00 |
| SWR region | 11 | $250.00 | 79 | $325.00 |
| NCR region | 11 | $295.00 | 43 | $300.00 |
| ER region | 7 | $350.00 | 26 | $350.00 |
| SCR region | 3 | $210.00 | 17 | $267.00 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 22 | $262.50 |
| 1 to 3 | 22 | $350.00 |
| 3 to 9 | 22 | $300.00 |
| 10 to 76 | 23 | $215.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 01 FEB 2023 | 009928 | OR region | 1 | $2,500.00 | $1,000.00 | $1,089.00 | 4 | TUCCI & SONS, INC. | WSDOT |
| 19 JAN 2023 | 009891 | OR region | 1 | $150.00 | $1,300.00 | $1,066.00 | 7 | CECCANTI, INC. | WSDOT |
| 10 FEB 2021 | 009643 | NWR region | 2 | $325.00 | $756.50 | $800.00 | 8 | STRIDER CONSTRUCTION CO., INC. | WSDOT |
| 13 JAN 2021 | 009623 | ER region | 3 | $400.00 | $400.00 | $1,000.00 | 5 | MAX J. KUNEY COMPANY | WSDOT |
| 06 JAN 2021 | 009628 | NCR region | 1 | $373.70 | $400.00 | $350.00 | 3 | MORENO & NELSON CONSTRUCTION | WSDOT |
| 08 APR 2020 | 009535 | OR region | 1 | $1,450.00 | $425.00 | $650.00 | 5 | ROGNLIN'S, INC. | WSDOT |
| 06 MAR 2019 | 009380 | NWR region | 1 | $839.00 | $839.00 | $1,200.00 | 3 | FABER CONSTRUCTION CORP. | WSDOT |
| 25 APR 2018 | 009258 | ER region | 13 | $360.00 | $480.00 | $375.00 | 2 | CPM DEVELOPMENT CORPORATION | WSDOT |
| 28 FEB 2018 | 009218 | NWR region | 1 | $950.23 | $950.23 | $500.00 | 5 | TIGER CONSTRUCTION, LTD. | WSDOT |
| 13 DEC 2017 | 009177 | NWR region | 3 | $500.00 | $500.00 | $505.00 | 3 | TAPANI, INC. | WSDOT |
| 01 FEB 2017 | 009010 | NCR region | 1 | $200.00 | $350.00 | $320.00 | 6 | STRIDER CONSTRUCTION CO., INC. | WSDOT |
| 06 APR 2016 | 008867 | OR region | 1 | $500.00 | $500.00 | $600.00 | 6 | M.J. HUGHES CONSTRUCTION, INC. | WSDOT |
| 23 MAR 2016 | 008861 | OR region | 1 | $500.00 | $885.00 | $200.00 | 7 | SCARSELLA BROS., INC. | WSDOT |
| 03 DEC 2014 | 008685 | OR region | 2 | $400.00 | $400.00 | $350.00 | 15 | SELBY BRIDGE COMPANY, INC. | WSDOT |
| 30 APR 2014 | 008608 | NWR region | 2 | $300.00 | $600.00 | $510.00 | 7 | GRANITE CONSTRUCTION COMPANY | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way