Painted crosswalk line unit price, Washington
Low bidders on WSDOT contracts carried a median of $2.75 per SF for painted crosswalk line, from 11 JAN 2001 to 13 APR 2022, across 42 low bids. Half of all 161 bids fell between $2.20 and $3.25.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- SF
- Latest letting
- 13 APR 2022
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2001 | 2 | 2 | $3.98 | 5 | $3.00 |
| 2002 | 2 | 2 | $2.23 | 7 | $1.71 |
| 2003 | 1 | 1 | $5.00 | 3 | $5.00 |
| 2004 | 2 | 2 | $4.10 | 8 | $4.35 |
| 2006 | 1 | 1 | $3.25 | 3 | $3.25 |
| 2007 | 4 | 4 | $2.88 | 12 | $2.83 |
| 2008 | 1 | 1 | $2.40 | 5 | $2.40 |
| 2010 | 5 | 5 | $2.45 | 23 | $2.35 |
| 2011 | 4 | 4 | $2.17 | 16 | $2.52 |
| 2012 | 3 | 3 | $2.50 | 25 | $2.25 |
| 2013 | 2 | 2 | $2.70 | 8 | $2.25 |
| 2014 | 2 | 2 | $3.00 | 6 | $3.50 |
| 2015 | 2 | 2 | $2.00 | 6 | $2.50 |
| 2016 | 1 | 1 | $5.00 | 3 | $5.00 |
| 2017 | 2 | 2 | $3.08 | 5 | $2.40 |
| 2018 | 2 | 2 | $3.48 | 6 | $2.65 |
| 2019 | 1 | 1 | $2.45 | 3 | $2.45 |
| 2020 | 2 | 2 | $2.90 | 8 | $2.50 |
| 2021 | 2 | 2 | $2.50 | 7 | $3.50 |
| 2022 | 1 | 1 | $19.50 | 2 | $19.25 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| ER region | 27 | $2.75 | 99 | $2.55 |
| SWR region | 4 | $1.25 | 27 | $1.50 |
| NWR region | 3 | $3.50 | 13 | $3.50 |
| Region 9 | 3 | $4.20 | 10 | $4.10 |
| NCR region | 3 | $2.70 | 7 | $2.70 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (SF) | Low bids | Low-bid median |
|---|---|---|
| 80 to 190 | 10 | $3.67 |
| 200 to 590 | 11 | $3.10 |
| 608 to 1,120 | 10 | $2.45 |
| 1,376 to 4,408 | 11 | $2.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 13 APR 2022 | 009785 | Region 9 | 96 | $19.50 | $19.25 | $40.00 | 2 | NORTHWEST CASCADE, INC. | WSDOT |
| 21 APR 2021 | 009662 | NWR region | 730 | $3.50 | $3.50 | $4.00 | 4 | SCARSELLA BROS., INC. | WSDOT |
| 24 MAR 2021 | 009664 | SWR region | 2,904 | $1.50 | $1.50 | $3.00 | 3 | MCDONALD EXCAVATING, INC. | WSDOT |
| 11 MAR 2020 | 009526 | ER region | 128 | $3.00 | $2.33 | $2.50 | 4 | CENTRAL WASHINGTON ASPHALT, IN | WSDOT |
| 23 JAN 2020 | 009509 | ER region | 780 | $2.80 | $2.62 | $4.00 | 4 | GARCO CONSTRUCTION, INC. | WSDOT |
| 20 MAR 2019 | 009407 | ER region | 1,776 | $2.45 | $2.45 | $2.50 | 3 | CENTRAL WASHINGTON ASPHALT, IN | WSDOT |
| 21 MAR 2018 | 009224 | ER region | 320 | $4.50 | $3.00 | $5.00 | 3 | CENTRAL WASHINGTON ASPHALT, IN | WSDOT |
| 18 JAN 2018 | 009189 | ER region | 2,624 | $2.45 | $2.54 | $2.25 | 3 | SHAMROCK PAVING, INC. | WSDOT |
| 05 APR 2017 | 009062 | ER region | 4,408 | $2.15 | $2.35 | $2.75 | 3 | POE ASPHALT PAVING, INC. | WSDOT |
| 01 MAR 2017 | 009031 | ER region | 96 | $4.00 | $3.50 | $10.00 | 2 | CENTRAL WASHINGTON ASPHALT, IN | WSDOT |
| 14 DEC 2016 | 008989 | NWR region | 330 | $5.00 | $5.00 | $3.00 | 3 | GRANITE CONSTRUCTION COMPANY | WSDOT |
| 01 APR 2015 | 008728 | ER region | 1,376 | $2.75 | $2.75 | $5.00 | 3 | CENTRAL WASHINGTON ASPHALT, IN | WSDOT |
| 25 FEB 2015 | 008702 | Region 9 | 770 | $1.25 | $1.50 | $4.00 | 3 | LAKESIDE INDUSTRIES, INC. | WSDOT |
| 26 MAR 2014 | 008587 | ER region | 224 | $4.00 | $3.75 | $5.00 | 4 | CENTRAL WASHINGTON ASPHALT, IN | WSDOT |
| 30 JAN 2014 | 008567 | NCR region | 572 | $2.00 | $2.05 | $2.50 | 2 | GRANITE CONSTRUCTION COMPANY | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.