Plastic traffic arrow unit price, Washington

Low bidders on WSDOT contracts carried a median of $340.50 per EACH for plastic traffic arrow, over the 24 months to 07 OCT 2026, across 2 low bids. Half of all 9 bids fell between $171.00 and $461.26.

Owner
Washington State DOT
Item
No code published
Unit
EACH
Latest letting
15 JUL 2026
$340.50Low bidder's median, per EACH
$400.00Median of all bids, per EACH
2Contracts in the window
$650.00Engineer's estimate, median per EACH

By year of letting

Plastic traffic arrow, WSDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20001111$80.0043$75.00
20012222$71.0096$70.00
20021616$69.2555$65.00
20032120$85.0083$85.00
20042828$87.50119$90.00
20053232$99.20123$100.00
20061717$96.0063$115.00
20073232$115.00130$125.00
20081818$147.5073$150.00
20092423$120.00131$145.00
20102828$125.00161$129.08
20112222$97.50114$100.00
201288$150.0054$165.00
20132525$150.00101$200.00
20141717$172.0568$219.50
20152121$164.0068$163.38
20162525$173.0073$170.50
20173636$172.50108$176.50
20183131$200.0089$206.00
20192121$265.0071$276.00
202088$222.5031$225.00
20211616$195.0056$195.00
20221515$330.0043$330.00
20231111$400.0039$450.00
202622$340.509$400.00
Plastic traffic arrow, WSDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By region

Plastic traffic arrow, WSDOT: unit prices by region, all lettings
RegionLow bidsLow-bid medianAll bidsMedian, all bids
NWR region197$150.00858$131.45
OR region94$131.00401$130.00
SCR region79$125.00277$130.00
NCR region73$150.00227$155.00
SWR region38$137.50165$132.00
ER region20$142.5061$142.83
Region 93$300.007$300.00
Plastic traffic arrow, WSDOT: unit prices by region, all lettings

Regions with at least three low bids, over all lettings.

By quantity

Plastic traffic arrow, WSDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 6126$185.00
6 to 13126$129.00
13 to 33126$142.50
34 to 243127$120.00
Plastic traffic arrow, WSDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest WSDOT contracts carrying Plastic traffic arrow
LetContractRegionQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
15 JUL 2026XE3755SCR region5$171.00$171.00$500.005INTERWEST CONSTRUCTION, INC.WSDOT
08 JUL 2026XE3751SCR region1$510.00$485.63$800.004TAPANI, INC.WSDOT
29 MAR 2023009941OR region6$319.60$504.50$250.006JOHANSEN CONSTRUCTION COMPANY,WSDOT
01 MAR 2023009936NCR region24$250.00$270.00$285.002CENTRAL WASHINGTON ASPHALT, INC.GRANITE CONSTRUCTION COMPANYWSDOT
01 MAR 2023009938ER region16$500.00$540.00$300.003CENTRAL WASHINGTON ASPHALT, INWSDOT
23 FEB 2023009939Region 98$410.00$410.00$250.003LAKESIDE INDUSTRIES, INC.WSDOT
23 FEB 2023009934NCR region115$325.00$329.00$225.003CENTRAL WASHINGTON ASPHALT, INC.INTERSTATE CONCRETE & ASPHALTWSDOT
01 FEB 2023009928OR region12$400.00$389.00$300.004TUCCI & SONS, INC.WSDOT
01 FEB 2023009916NWR region21$439.00$449.50$305.002GRANITE CONSTRUCTION COMPANYWSDOT
01 FEB 2023009921NCR region17$279.45$420.00$325.004JOHANSEN CONSTRUCTION COMPANY,WSDOT
19 JAN 2023009891OR region2$500.00$560.00$324.007CECCANTI, INC.WSDOT
11 JAN 2023009901NWR region4$900.00$900.00$500.001GARY MERLINO CONSTRUCTION CO.,WSDOT
11 JAN 2023009909SWR region8$350.00$367.50$300.004THOMPSON BROS. EXCAVATING, INCWSDOT
13 APR 2022009781NWR region30$330.00$342.00$180.004TUCCI & SONS, INC.WSDOT
13 APR 2022009796NWR region16$406.20$445.60$219.002GRANITE CONSTRUCTION COMPANYWSDOT
Latest WSDOT contracts carrying Plastic traffic arrow

Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.

How these prices were read

WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.