Low bidders on WSDOT contracts carried a median of $4,900.00 per EACH for temporary impact attenuator, over the 24 months to 07 OCT 2026, across 2 low bids. Half of all 12 bids fell between $4,500.00 and $5,325.00.

Owner
Washington State DOT
Item
No code published
Unit
EACH
Latest letting
26 AUG 2026
$4,900.00Low bidder's median, per EACH
$4,950.00Median of all bids, per EACH
2Contracts in the window
$6,250.00Engineer's estimate, median per EACH

By year of letting

Temporary impact attenuator, WSDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
200066$1,679.4131$3,500.00
20011111$3,650.0072$3,900.00
200277$3,400.0040$3,500.00
20031111$2,750.0066$4,200.00
20041111$5,000.0070$4,600.00
20051212$4,150.0047$4,500.00
200666$3,971.0017$4,000.00
20071212$4,425.0071$4,969.00
200888$4,285.0039$4,830.00
20091311$4,500.0080$4,720.00
20101414$4,850.00103$4,160.00
20111313$3,600.0099$3,200.00
201288$3,250.0061$3,900.00
20131312$3,175.0074$3,200.00
201488$3,250.0041$3,500.00
201555$3,500.0026$3,600.00
20161010$2,651.6459$3,200.00
201799$2,500.0039$3,500.00
20181010$3,150.0052$3,750.00
201944$4,350.0015$5,000.00
202044$4,000.0017$4,000.00
202166$3,900.0027$4,000.00
202277$5,000.0033$4,659.47
202355$5,815.0023$5,500.00
202622$4,900.0012$4,950.00
Temporary impact attenuator, WSDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By region

Temporary impact attenuator, WSDOT: unit prices by region, all lettings
RegionLow bidsLow-bid medianAll bidsMedian, all bids
NWR region108$3,900.00645$4,400.00
SCR region37$3,500.00196$3,662.50
OR region26$3,575.00167$3,500.00
NCR region19$3,500.0087$3,500.00
SWR region14$2,500.0084$3,535.00
ER region7$3,500.0030$5,050.00
Temporary impact attenuator, WSDOT: unit prices by region, all lettings

Regions with at least three low bids, over all lettings.

By quantity

Temporary impact attenuator, WSDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 253$4,500.00
2 to 353$3,500.00
3 to 553$3,500.00
5 to 2953$3,800.00
Temporary impact attenuator, WSDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest WSDOT contracts carrying Temporary impact attenuator
LetContractRegionQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
26 AUG 2026XE3764SCR region1$5,300.00$4,700.00$5,000.006INTERWEST CONSTRUCTION, INC.WSDOT
01 JUL 2026XE3756SCR region4$4,500.00$5,122.00$7,500.006N.A. DEGERSTROM, INC.WSDOT
19 APR 2023009952SCR region2$5,500.00$7,750.00$5,000.004INTERSTATE CONCRETE & ASPHALTWSDOT
05 APR 2023009948SCR region9$5,815.00$5,600.00$10,0003COMBINED CONSTRUCTION, INC.WSDOT
01 MAR 2023009935NWR region4$6,733.00$6,000.00$4,500.005FABER CONSTRUCTION CORP.WSDOT
01 FEB 2023009924NWR region6$4,200.00$4,200.00$4,500.007INTERWEST CONSTRUCTION, INC.WSDOT
11 JAN 2023009908NWR region2$7,500.00$6,725.00$5,000.004KONNERUP CONSTRUCTION, INC.WSDOT
06 APR 2022009795SWR region1$5,000.00$4,600.00$5,000.007SB STRUCTURES, LLCWSDOT
23 MAR 2022009783NWR region7$5,000.00$5,000.00$4,500.007INTERWEST CONSTRUCTION, INC.WSDOT
09 MAR 2022009774OR region4$3,600.00$4,050.00$4,000.002KRAEMER NORTH AMERICA, LLC.WSDOT
02 MAR 2022009762NWR region1$6,600.00$6,600.00$6,000.003MIDMOUNTAIN CONTRACTORS, INC.WSDOT
02 MAR 2022009772OR region1$5,000.00$4,500.00$4,500.003TUCCI & SONS, INC.WSDOT
24 FEB 2022009769NWR region8$2,400.00$4,250.00$4,000.004GRANITE CONSTRUCTION COMPANYWSDOT
09 FEB 2022009763OR region2$4,200.00$5,000.00$4,500.007KRAEMER NORTH AMERICA, LLC.WSDOT
15 DEC 2021009742NWR region1$6,000.00$5,500.00$4,000.004GRANITE CONSTRUCTION COMPANYWSDOT
Latest WSDOT contracts carrying Temporary impact attenuator

Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.

How these prices were read

WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy