Research record, fact-checked
Aligned PDX-01, Hillsboro
- Location
- Hillsboro, OR, United States. Site address: NE 30th Ave. & NE Evergreen Rd., Hillsboro, OR 97124. See it on the map, in 3D
- Stage
- Stage not confirmed: Not found in the sources consulted (Aligned Data Centers). Aligned's own Hillsboro page describes the building's design standard and the market, but gives no construction progress and no delivery date.
- Status
- Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, how big, how much
| Field | Value | Source |
|---|---|---|
| Developer | Aligned Data Centers | |
| Type | Leased hyperscale campuses | |
| Amount | Not found in the sources consulted |
Capacity
Each figure as its source states it. Megawatts of IT capacity (the power available to the computing equipment), of power supplied to the site and of generation measure different things and are never added together; a campus figure is not a building's.
| Capacity | What it measures | Scope | As of | Source |
|---|---|---|---|---|
| 108 MW | Capacity, its measure not stated by the source | Whole campus | Aligned Data Centers | |
| 72 MW | IT capacity (power for the computing equipment) | One building | Aligned Data Centers | |
| 36 MW | Capacity, its measure not stated by the source | One building | Aligned Data Centers |
Buildings and site
| Field | Value | Scope | Source |
|---|---|---|---|
| Site area | 27 acres | Whole campus | Aligned Data Centers |
| Buildings, in all | 2 | Whole campus | Aligned Data Centers |
| Floor area of one building | 628,276 sq ft | One building | Largo Concrete |
| Stories | Four levels above grade (elevated slabs on metal deck) | One building | Largo Concrete |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Aligned Data Centers | Developer | Aligned Data Centers | |
| Holder Construction | General contractor | General contractor on PDX-01, as named by two of its subcontractors on their own project pages. | Largo Concrete |
| Gensler | Design | Largo Concrete | |
| Thornton Tomasetti | Design | Largo Concrete | |
| Largo Concrete | Trade contractor | concrete; Elevated slabs on metal deck. | Largo Concrete |
| Pacific Foundation | Trade contractor | foundations (ground improvement); Rigid-inclusion ground improvement. | Pacific Foundation |
Milestones
| Date | Milestone | Source |
|---|---|---|
| January 10, 2023 | Campus announced | Aligned Data Centers |
| January 2025 | Concrete subcontractor's work on PDX-01 completed | Largo Concrete |
About the campus
PDX-01 is Aligned Data Centers' 27-acre campus at NE 30th Ave. and NE Evergreen Rd. in Hillsboro, Oregon, designed to Tier III standards. Aligned's own page gives no capacity figure, construction status or delivery date for the building.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.
Sources
- Scalable and Adaptive Data Centers in Hillsboro, Oregon, Aligned Data Centers. Consulted 19 Nov 2026.
- Aligned PDX01, Largo Concrete. Consulted 20 Nov 2026.
- Aligned PDX01, Pacific Foundation. Consulted 20 Nov 2026.
- Aligned Data Centers Expands into Pacific Northwest with New Hillsboro Campus to Support Hyperscale & Large Enterprise Demand, Aligned Data Centers, 10 Jan 2023. Consulted 20 Nov 2026.