Research record, fact-checked

Applied Digital Polaris Forge 1, Ellendale

Location
Ellendale, ND, United States. See it on the map, in 3D
Stage
Under construction, as of October 2026 (Applied Digital). Applied Digital's fiscal Q1 2027 results, covering the quarter ended August 31, 2026 and issued October 7, 2026, report the campus's first two buildings delivered and the third still building.
Status
Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, how big, how much

Sourced facts of the campus
FieldValueSource
OwnerApplied Digital
TypeLeased hyperscale campusesApplied Digital
AmountNot found in the sources consulted
Sourced facts of the campus

Capacity

Each figure as its source states it. Megawatts of IT capacity (the power available to the computing equipment), of power supplied to the site and of generation measure different things and are never added together; a campus figure is not a building's.

Capacity figures, each with what it measures
CapacityWhat it measuresScopeAs ofSource
150 MW, plannedIT capacity (power for the computing equipment)One building, Building 3August 2025Applied Digital
250 MW, deliveredIT capacity (power for the computing equipment)Whole campusOctober 2026Applied Digital
150 MWIT capacity (power for the computing equipment)One buildingApplied Digital
Capacity figures, each with what it measures

Buildings and site

The campus's buildings, land and plant, as their sources describe them
FieldValueScopeSource
Buildings delivered2Whole campusApplied Digital
Buildings under construction1Whole campusApplied Digital
Buildings, in all3Whole campusMcGough
Floor area2,250,000 sq ftWhole campusMcGough
Floor area of one building369,000 sq ftOne buildingMcGough
Stories3One buildingMcGough
GeneratorsFour standalone generator buildings of 80,000 sq ft in all, serving the first buildingOne buildingMcGough
Floor area of one building940,000 sq ftOne buildingMcGough
The campus's buildings, land and plant, as their sources describe them

Companies and their roles

Companies named by the operator, the developer, a filing or a government, each with its role
CompanyRoleNoteSource
Applied DigitalOwnerApplied Digital
CoreWeaveTenantApplied Digital
Goldman Sachs Bank USAFinancingadministrative and collateral agent of the ELN-04 bridge loan facility, repaid from the notesApplied Digital
McGoughGeneral contractorMcGough's portfolio page for Applied Digital Polaris Forge 1 lists the delivery method as CMAR (construction manager at risk).McGough
Companies named by the operator, the developer, a filing or a government, each with its role

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
August 2025Applied Digital finalized an additional 150 MW CoreWeave lease for Polaris Forge 1's third building.Applied Digital
October 2025The first 100 MW building at Polaris Forge 1 became operational.Applied Digital
October 2026Building 2 (150 MW) was fully delivered in two phases, bringing live campus capacity to 250 MW.Applied Digital
Dated milestones, at the precision of their source; a planned date is marked as such

About the campus

Polaris Forge 1 in Ellendale, North Dakota is Applied Digital's campus leased to CoreWeave, engineered to scale up to 1 gigawatt. Its first two buildings, 100 MW and 150 MW, are operational, bringing live capacity to 250 MW as of October 2026, while the third building, an additional 150 MW leased in August 2025, remains under construction toward a 2027 service date.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.