Polaris Forge 2
- Location
- Harwood, ND, United States. See it on the map, in 3D
- Stage
- Under construction, as of July 2026 (Applied Digital Corporation (SEC filing)). Applied Digital's annual report filed July 29, 2026 dates the groundbreaking to August 18, 2025 and expects initial capacity in the second half of 2026.
- Status
- Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, how big, how much
| Field | Value | Source |
|---|---|---|
| Owner | Applied Digital | |
| Type | Leased hyperscale campuses | |
| Headline amount | US$3 billion (US dollars), as of August 2025 | Applied Digital |
| What it covers | Announced investment. Not to be read as a construction cost. |
Capacity
Each figure as its source states it. Megawatts of IT capacity (the power available to the computing equipment), of power supplied to the site and of generation measure different things and are never added together; a campus figure is not a building's.
| Capacity | What it measures | Scope | As of | Source |
|---|---|---|---|---|
| 280 MW, planned | Capacity, its measure not stated by the source | Whole campus | August 2025 | Applied Digital |
| 200 MW | Capacity, its measure not stated by the source | One phase | Applied Digital Corporation (SEC filing) |
Investment and financing
An announced investment, a construction loan, a public incentive and a regional programme are different objects: each is listed with what it covers, never added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$3 bn | Announced investment | Whole campus | August 2025 | Applied Digital |
Buildings and site
| Field | Value | Scope | Source |
|---|---|---|---|
| Site area | More than 900 acres | Whole campus | Applied Digital |
| Buildings, in all | 2 | Whole campus | Applied Digital |
| Buildings, in all | 2 | One phase | Applied Digital |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Applied Digital | Owner | Applied Digital | |
| Cass County Electric Cooperative | Energy partner | Applied Digital | |
| Century Builders | General contractor | Century Builders General Contractors (Fargo) prepared the preliminary site logistics plan for the APLD Harwood Campus (September 9, 2025) filed with Cass County. | Cass County, North Dakota (Highway Department, Commission agenda packet) |
| APLD FAR-01 LLC | Owner | Applied Digital's project entity, party to the September 2025 Cass County road agreement. | Cass County, North Dakota (Highway Department, Commission agenda packet) |
Milestones
| Date | Milestone | Source |
|---|---|---|
| August 2025 | Applied Digital announced it would break ground on Polaris Forge 2 near Harwood, North Dakota. | Applied Digital |
| August 18, 2025 | Applied Digital Corporation (SEC filing) | |
| September 2025 | Construction period stated in the county agreement: fall 2025 through the 2027 construction year | Cass County, North Dakota (Highway Department, Commission agenda packet) |
| September 2, 2025 | City of Harwood, North Dakota | |
| July 29, 2026 | Applied Digital Corporation (SEC filing) |
About the campus
Polaris Forge 2 is Applied Digital's campus on over 900 acres near Harwood, North Dakota, announced in August 2025 as a $3 billion, 280 MW AI factory with two initial facilities. Applied Digital's October 2026 results list the campus among its sites in various stages of construction, with initial operations expected to raise delivered IT load across its North Dakota campuses to 300 MW by the end of calendar 2026.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.
Sources
- Applied Digital Reports Fiscal First Quarter 2027 Results, Applied Digital, 7 Oct 2026. Consulted 19 Nov 2026.
- Applied Digital to Break Ground on $3 Billion Polaris Forge 2 Campus in North Dakota, Expanding North Dakota's Role as a National AI Infrastructure Leader, Applied Digital, 18 Aug 2025. Consulted 19 Nov 2026.
- Applied Digital to Break Ground on $3 Billion Polaris Forge 2 Campus in North Dakota, Applied Digital, 18 Aug 2025. Consulted 20 Nov 2026.
- Form 10-K for the fiscal year ended May 31, 2026, Applied Digital Corporation (SEC filing), 29 Jul 2026. Consulted 20 Nov 2026.
- Harwood City Council Minutes, Regular Meeting, September 2nd, 2025 (draft), City of Harwood, North Dakota, 2 Sep 2025. Consulted 20 Nov 2026.
- Agenda item for the September 22, 2025 Commission meeting: Applied Digital MOA (Bypass, Right Turn Lane, & Access Approach), with the Memorandum of Agreement with APLD FAR-01 LLC and Century Builders' preliminary site logistics plan, Cass County, North Dakota (Highway Department, Commission agenda packet), 16 Sep 2025. Consulted 20 Nov 2026.
- Cass County parcels owned by APLD FAR-01 LLC, Cass County, North Dakota GIS (CassNDParcels). Consulted 20 Nov 2026.