Research record, fact-checked
Polaris Forge 3
- Location
- Center, Oliver County, ND, United States. See it on the map, in 3D
- Stage
- Under construction, as of July 2026 (Applied Digital Corporation (SEC filing)). Applied Digital's annual report filed July 29, 2026 describes Polaris Forge 3 as under construction across two buildings.
- Status
- Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, how big, how much
| Field | Value | Source |
|---|---|---|
| Owner | Applied Digital | |
| Type | Leased hyperscale campuses | |
| Amount | Not found in the sources consulted |
Capacity
Each figure as its source states it. Megawatts of IT capacity (the power available to the computing equipment), of power supplied to the site and of generation measure different things and are never added together; a campus figure is not a building's.
| Capacity | What it measures | Scope | As of | Source |
|---|---|---|---|---|
| 300 MW | Capacity, its measure not stated by the source | Whole campus | Applied Digital Corporation (SEC filing) | |
| Up to 430 MW | Capacity, its measure not stated by the source | Whole campus | Montana-Dakota Utilities Co. (filing with the North Dakota Public Service Commission) |
Buildings and site
| Field | Value | Scope | Source |
|---|---|---|---|
| Buildings under construction | 2 | Whole campus | Applied Digital Corporation (SEC filing) |
| Buildings, in all | 2 | Whole campus | Montana-Dakota Utilities Co. (filing with the North Dakota Public Service Commission) |
| Site area | 640 acres | Whole campus | Montana-Dakota Utilities Co. (filing with the North Dakota Public Service Commission) |
| Substation capacity | New 345 kV switching substation on or near the property, fed by a tap of about 1,000 feet from the Coyote to Center 345 kV line; about 15 miles of new 345 kV line to Nelson Lake Substation by 2029 | Whole campus | Montana-Dakota Utilities Co. (filing with the North Dakota Public Service Commission) |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Applied Digital | Owner | Applied Digital | |
| Undisclosed investment-grade hyperscaler | Tenant | Applied Digital Corporation (SEC filing) | |
| APLD BIS-01 LLC | Owner | Applied Digital's project entity, Montana-Dakota's customer in PSC case PU-26-236. | Montana-Dakota Utilities Co. (filing with the North Dakota Public Service Commission) |
| Montana-Dakota Utilities Co. | Energy partner | Montana-Dakota Utilities Co. |
General contractor: Not found in the sources consulted.
Milestones
| Date | Milestone | Source |
|---|---|---|
| July 29, 2026 | Applied Digital Corporation (SEC filing) | |
| August 2027 | Initial operations anticipated | Montana-Dakota Utilities Co. |
About the campus
Polaris Forge 3 is Applied Digital's campus in Center, Oliver County, North Dakota. Applied Digital's July 2026 annual report describes it as a 300 MW critical IT load campus under construction across two buildings, leased to an investment-grade hyperscaler under two leases of about 15 years, with delivery expected from the second half of 2027 through the second half of 2028.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.
Sources
- Applied Digital Reports Fiscal First Quarter 2027 Results, Applied Digital, 7 Oct 2026. Consulted 19 Nov 2026.
- Applied Digital Reports Fiscal First Quarter 2027 Results, Applied Digital, 7 Oct 2026. Consulted 20 Nov 2026.
- Form 10-K for the fiscal year ended May 31, 2026, Applied Digital Corporation (SEC filing), 29 Jul 2026. Consulted 20 Nov 2026.
- Case No. PU-26-236, Application for Permanent Authority, Switch Yard Service, APLD BIS-01, Center, ND, with Exhibits A to D (testimony of Darcy J. Neigum), Montana-Dakota Utilities Co. (filing with the North Dakota Public Service Commission), 17 Jul 2026. Consulted 20 Nov 2026.
- Montana-Dakota Utilities Announces Electric Service Agreement with Applied Digital for Proposed AI Factory, Montana-Dakota Utilities Co., 22 Jun 2026. Consulted 20 Nov 2026.