Polaris Forge 3

Location
Center, Oliver County, ND, United States. See it on the map, in 3D
Stage
Under construction, as of July 2026 (Applied Digital Corporation (SEC filing)). Applied Digital's annual report filed July 29, 2026 describes Polaris Forge 3 as under construction across two buildings.
Status
Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, how big, how much

Sourced facts of the campus
FieldValueSource
OwnerApplied Digital
TypeLeased hyperscale campuses
AmountNot found in the sources consulted
Sourced facts of the campus

Capacity

Each figure as its source states it. Megawatts of IT capacity (the power available to the computing equipment), of power supplied to the site and of generation measure different things and are never added together; a campus figure is not a building's.

Capacity figures, each with what it measures
CapacityWhat it measuresScopeAs ofSource
300 MWCapacity, its measure not stated by the sourceWhole campusApplied Digital Corporation (SEC filing)
Up to 430 MWCapacity, its measure not stated by the sourceWhole campusMontana-Dakota Utilities Co. (filing with the North Dakota Public Service Commission)
Capacity figures, each with what it measures

Buildings and site

The campus's buildings, land and plant, as their sources describe them
FieldValueScopeSource
Buildings under construction2Whole campusApplied Digital Corporation (SEC filing)
Buildings, in all2Whole campusMontana-Dakota Utilities Co. (filing with the North Dakota Public Service Commission)
Site area640 acresWhole campusMontana-Dakota Utilities Co. (filing with the North Dakota Public Service Commission)
Substation capacityNew 345 kV switching substation on or near the property, fed by a tap of about 1,000 feet from the Coyote to Center 345 kV line; about 15 miles of new 345 kV line to Nelson Lake Substation by 2029Whole campusMontana-Dakota Utilities Co. (filing with the North Dakota Public Service Commission)
The campus's buildings, land and plant, as their sources describe them

Companies and their roles

Companies named by the operator, the developer, a filing or a government, each with its role
CompanyRoleNoteSource
Applied DigitalOwnerApplied Digital
Undisclosed investment-grade hyperscalerTenantApplied Digital Corporation (SEC filing)
APLD BIS-01 LLCOwnerApplied Digital's project entity, Montana-Dakota's customer in PSC case PU-26-236.Montana-Dakota Utilities Co. (filing with the North Dakota Public Service Commission)
Montana-Dakota Utilities Co.Energy partnerMontana-Dakota Utilities Co.
Companies named by the operator, the developer, a filing or a government, each with its role

General contractor: Not found in the sources consulted.

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
July 29, 2026Applied Digital Corporation (SEC filing)
August 2027Initial operations anticipatedMontana-Dakota Utilities Co.
Dated milestones, at the precision of their source; a planned date is marked as such

About the campus

Polaris Forge 3 is Applied Digital's campus in Center, Oliver County, North Dakota. Applied Digital's July 2026 annual report describes it as a 300 MW critical IT load campus under construction across two buildings, leased to an investment-grade hyperscaler under two leases of about 15 years, with delivery expected from the second half of 2027 through the second half of 2028.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.