Research record, fact-checked

Tulsa County data center campus (Project Clydesdale)

Location
Owasso, Tulsa County, OK, United States. See it on the map, in 3D
Stage
Under construction, as of August 2026 (Beale Infrastructure). Beale Infrastructure's own announcement states the campus is under construction.
Status
Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, how big, how much

Sourced facts of the campus
FieldValueSource
DeveloperBeale Infrastructure
TypeLeased hyperscale campusesBeale Infrastructure
AmountNot found in the sources consulted
Sourced facts of the campus

Buildings and site

The campus's buildings, land and plant, as their sources describe them
FieldValueScopeSource
Site area506 acresWhole campusBeale Infrastructure
Substation capacitynew on-site substation funded by BealeWhole campusBeale Infrastructure
Floor area of one buildingAbout 200,000 sq ftOne buildingTulsa Metropolitan Area Planning Commission (INCOG Planning Services) and Tulsa County
Building height50 ftWhole campusTulsa Metropolitan Area Planning Commission
The campus's buildings, land and plant, as their sources describe them

Companies and their roles

Companies named by the operator, the developer, a filing or a government, each with its role
CompanyRoleNoteSource
Beale InfrastructureDeveloperBeale Infrastructure
GoogleTenantBeale Infrastructure
Kimley-HornDesignCredited for the campus rendering in Beale's release; its engineering role is not statedBeale Infrastructure
Public Service Company of OklahomaEnergy partnerBeale Infrastructure
Companies named by the operator, the developer, a filing or a government, each with its role

General contractor: Not found in the sources consulted.

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
June 4, 2025The Tulsa Metropolitan Area Planning Commission recommends approval of the rezoning (CZ-565), the PUD (PUD-871) and the preliminary plat of Project Clydesdale, 10 votes to 0Tulsa Metropolitan Area Planning Commission
October 31, 2025Beale Infrastructure
August 19, 2026Beale Infrastructure and Google announced the Tulsa County campus is under construction.Beale Infrastructure
Dated milestones, at the precision of their source; a planned date is marked as such

About the campus

Beale Infrastructure is building a 506 acre data center campus in unincorporated Tulsa County near Owasso and the Cherokee Industrial Park, for Google, confirmed under construction in an August 2026 announcement. Beale is funding 1.5 miles of new water line infrastructure for the project. This campus, known as Project Clydesdale, is separate from Meta's own Tulsa data center.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.

Sources

See it on the map. How the map is made.