Research record, fact-checked
Centra RNO2, Reno
- Location
- Reno, NV, United States. Site address: 265 Keystone Ave, Reno, NV 89503, USA. See it on the map, in 3D
- Stage
- Under construction, as of July 2026 (City of Reno). The City of Reno's FAQ, updated in July 2026, describes concrete pours in May and June 2026 and the final soils and compaction letter approved in June 2026.
- Status
- Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, how big, how much
| Field | Value | Source |
|---|---|---|
| Developer | Centra | |
| Type | Leased hyperscale campuses | |
| Amount | Not found in the sources consulted |
Capacity
Each figure as its source states it. Megawatts of IT capacity (the power available to the computing equipment), of power supplied to the site and of generation measure different things and are never added together; a campus figure is not a building's.
| Capacity | What it measures | Scope | As of | Source |
|---|---|---|---|---|
| 4.4 MW, planned | Capacity, its measure not stated by the source | One building | 2026 | Centra |
Buildings and site
| Field | Value | Scope | Source |
|---|---|---|---|
| Floor area of one building | 230,000 sq ft | One building | Centra |
| Site area | 3.26 acres | Whole campus | City of Reno Planning Commission |
| Stories | 2 | One building | Centra |
| Water | about 2 acre-feet of water | One building | City of Reno |
| Cooling | Rooftop chillers behind a 15-foot acoustically absorptive barrier | One building | City of Reno |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Centra | Developer | Centra | |
| Clark Construction | General contractor | Named by the City of Reno as the contractor granted extended hours for the concrete pours. | City of Reno |
| ENGEO | Design | Prepared the geotechnical report. | City of Reno |
Milestones
| Date | Milestone | Source |
|---|---|---|
| January 15, 2025 | Conditional use permit approved by the Reno Planning Commission | City of Reno |
| September 11, 2025 | Geotechnical report approved by the City, before the original building permit | City of Reno |
| October 15, 2025 | Site preparation for foundation pouring was underway. | Centra |
| November 18, 2025 | Centra announced groundbreaking on RNO2. | Centra |
About the campus
Centra's RNO2 data center is under construction at 265 Keystone Ave in Reno, Nevada, on a site of about 3.26 acres approved for a conditional use permit by the Reno Planning Commission on January 15, 2025. Centra describes a two-story precast building targeting 4.4 MW in the fourth quarter of 2026. The City of Reno names Clark Construction as the contractor that poured concrete in May and June 2026.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.
Sources
- CENTRA Breaks Ground on RNO2, Centra, 18 Nov 2025. Consulted 19 Nov 2026.
- Reno 2 (RNO2), Centra. Consulted 19 Nov 2026.
- Keystone Data Center Frequently Asked Questions (FAQ), updated 7/28/2026, City of Reno, 28 Jul 2026. Consulted 20 Nov 2026.
- Agenda, Regular Meeting of January 15, 2025, item LDC25-00026 Keystone Data Center, City of Reno Planning Commission, 15 Jan 2025. Consulted 20 Nov 2026.
- Reno 2 (RNO2), Centra. Consulted 20 Nov 2026.
- Inside CENTRA: October Progress from Reno, Centra, 15 Oct 2025. Consulted 19 Nov 2026.