Colovore RNO01, Storey County
- Location
- McCarran, Storey County, NV, United States. Site address: 100 Italy Drive, McCarran, Storey County, NV 89437. See it on the map, in 3D
- Stage
- Under construction, as of August 2026 (Colovore). Colovore's own site lists RNO01's status as Under Construction, corroborated by its tax abatement filing with the State of Nevada
- Status
- Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, how big, how much
| Field | Value | Source |
|---|---|---|
| Owner | Colovore | |
| Type | Colocation | Nevada Governor's Office of Economic Development |
| Amount | Not found in the sources consulted |
Capacity
Each figure as its source states it. Megawatts of IT capacity (the power available to the computing equipment), of power supplied to the site and of generation measure different things and are never added together; a campus figure is not a building's.
| Capacity | What it measures | Scope | As of | Source |
|---|---|---|---|---|
| 16 MW, planned | Capacity, its measure not stated by the source | One building | 2026 | Nevada Governor's Office of Economic Development |
Investment and financing
An announced investment, a construction loan, a public incentive and a regional programme are different objects: each is listed with what it covers, never added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| About US$30 M | Financing | One building | June 2026 | Nevada Governor's Office of Economic DevelopmentCapital equipment investment stated in the Nevada tax abatement application |
| US$80 M | Total construction cost | One building | 2026 | Nevada Governor's Office of Economic DevelopmentYear-1 construction cost figure from the application's real estate and construction projection |
Buildings and site
| Field | Value | Scope | Source |
|---|---|---|---|
| Cooling | liquid-cooled architecture eliminates the need for water-intensive cooling, achieving a Water Usage Effectiveness (WUE) of zero | One building | Nevada Governor's Office of Economic Development |
| Floor area of one building | 75,000 sq ft | One building | Nevada Governor's Office of Economic Development |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Colovore | Owner | Nevada Governor's Office of Economic Development | |
| King Street Capital | Financing | Nevada Governor's Office of Economic Development |
General contractor: Not found in the sources consulted.
Milestones
| Date | Milestone | Source |
|---|---|---|
| 2025 | Breaks ground on first Reno, NV (RNO01) facility | Nevada Governor's Office of Economic Development |
| 2025 | Colovore broke ground on RNO01 | Nevada Governor's Office of Economic Development |
| undefined 2026 (planned) | Colovore expects to begin new operations in Storey County by Q4 2026 | Nevada Governor's Office of Economic Development |
About the campus
RNO01, also known as Colovore Reno 1, is a Colovore data center in Storey County, Nevada at 100 Italy Drive, McCarran, listed by the operator as under construction. A Nevada tax abatement filing dated August 2026 shows the company investing approximately $30,000,000 in capital equipment, with a first-year construction cost of $80,000,000, planning to begin operations by the fourth quarter of 2026. Colovore's own materials describe RNO01 as a 16MW, liquid-cooled site that is fully committed ahead of delivery, with zero water usage effectiveness.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.
Sources
- Colovore | Data Centers, Colovore. Consulted 19 Nov 2026.
- Colovore Reno 1 LLC, Data Center Tax Abatement Incentive Application board packet (includes Colovore company materials), Nevada Governor's Office of Economic Development, 5 Aug 2026. Consulted 19 Nov 2026.
- StoreyCo_Pictometry FeatureServer layer 2 Parcels: APN 005-091-10, 100 Italy Dr, Storey County, Nevada (assessor parcel layer, county ArcGIS Online organisation). Consulted 20 Nov 2026.