Research record, fact-checked

Colovore RNO01, Storey County

Location
McCarran, Storey County, NV, United States. Site address: 100 Italy Drive, McCarran, Storey County, NV 89437. See it on the map, in 3D
Stage
Under construction, as of August 2026 (Colovore). Colovore's own site lists RNO01's status as Under Construction, corroborated by its tax abatement filing with the State of Nevada
Status
Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, how big, how much

Sourced facts of the campus
FieldValueSource
OwnerColovore
TypeColocationNevada Governor's Office of Economic Development
AmountNot found in the sources consulted
Sourced facts of the campus

Capacity

Each figure as its source states it. Megawatts of IT capacity (the power available to the computing equipment), of power supplied to the site and of generation measure different things and are never added together; a campus figure is not a building's.

Capacity figures, each with what it measures
CapacityWhat it measuresScopeAs ofSource
16 MW, plannedCapacity, its measure not stated by the sourceOne building2026Nevada Governor's Office of Economic Development
Capacity figures, each with what it measures

Investment and financing

An announced investment, a construction loan, a public incentive and a regional programme are different objects: each is listed with what it covers, never added to another.

Amounts, each with its kind and scope
AmountWhat it isScopeAs ofSource
About US$30 MFinancingOne buildingJune 2026Nevada Governor's Office of Economic DevelopmentCapital equipment investment stated in the Nevada tax abatement application
US$80 MTotal construction costOne building2026Nevada Governor's Office of Economic DevelopmentYear-1 construction cost figure from the application's real estate and construction projection
Amounts, each with its kind and scope

Buildings and site

The campus's buildings, land and plant, as their sources describe them
FieldValueScopeSource
Coolingliquid-cooled architecture eliminates the need for water-intensive cooling, achieving a Water Usage Effectiveness (WUE) of zeroOne buildingNevada Governor's Office of Economic Development
Floor area of one building75,000 sq ftOne buildingNevada Governor's Office of Economic Development
The campus's buildings, land and plant, as their sources describe them

Companies and their roles

Companies named by the operator, the developer, a filing or a government, each with its role
CompanyRoleNoteSource
ColovoreOwnerNevada Governor's Office of Economic Development
King Street CapitalFinancingNevada Governor's Office of Economic Development
Companies named by the operator, the developer, a filing or a government, each with its role

General contractor: Not found in the sources consulted.

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
2025Breaks ground on first Reno, NV (RNO01) facilityNevada Governor's Office of Economic Development
2025Colovore broke ground on RNO01Nevada Governor's Office of Economic Development
undefined 2026 (planned)Colovore expects to begin new operations in Storey County by Q4 2026Nevada Governor's Office of Economic Development
Dated milestones, at the precision of their source; a planned date is marked as such

About the campus

RNO01, also known as Colovore Reno 1, is a Colovore data center in Storey County, Nevada at 100 Italy Drive, McCarran, listed by the operator as under construction. A Nevada tax abatement filing dated August 2026 shows the company investing approximately $30,000,000 in capital equipment, with a first-year construction cost of $80,000,000, planning to begin operations by the fourth quarter of 2026. Colovore's own materials describe RNO01 as a 16MW, liquid-cooled site that is fully committed ahead of delivery, with zero water usage effectiveness.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.

Sources

See it on the map. How the map is made.