Research record, fact-checked
Corscale Gainesville Crossing
- Location
- Gainesville, VA, United States. See it on the map, in 3D
- Stage
- Under construction, as of July 2024 (Corscale). Corscale's own press release announces the groundbreaking of the second building
- Status
- Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, how big, how much
| Field | Value | Source |
|---|---|---|
| Developer | Corscale | |
| Type | Leased hyperscale campuses | Corscale |
| Amount | Not found in the sources consulted |
Capacity
Each figure as its source states it. Megawatts of IT capacity (the power available to the computing equipment), of power supplied to the site and of generation measure different things and are never added together; a campus figure is not a building's.
| Capacity | What it measures | Scope | As of | Source |
|---|---|---|---|---|
| 72 MW | Capacity, its measure not stated by the source | One building, Building 2 of the Gainesville Crossing campus | July 2024 | Corscale |
| 54 MW | Capacity, its measure not stated by the source | One building, Building 3 of the Gainesville Crossing campus | January 2025 | Corscale |
| 54 MW | Capacity, its measure not stated by the source | One building, Building 3 | Corscale | |
| 326 MW | Capacity, its measure not stated by the source | Whole campus | Corscale |
Buildings and site
| Field | Value | Scope | Source |
|---|---|---|---|
| Site area | 130 acres | Whole campus | Corscale |
| Floor area | More than 2,300,000 sq ft | Whole campus | Corscale |
| Buildings, in all | 5 | Whole campus | Corscale |
| Stories | 2 | One building | Corscale |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Corscale | Developer | Corscale | |
| HITT Contracting | General contractor | Building 2 | Corscale |
| Corgan | Design | Building 2 | Corscale |
Milestones
| Date | Milestone | Source |
|---|---|---|
| May 2024 | First building at the campus completed | Corscale |
| July 2024 | Construction begins on the second building at Gainesville Crossing | Corscale |
| January 2025 | Construction begins on the third building at Gainesville Crossing | Corscale |
| January 29, 2025 | Corscale | |
| June 2025 (planned) | Second facility expected completion mid-2025 | Corscale |
About the campus
Gainesville Crossing Building 2 is the second data center on Corscale's Gainesville Crossing campus in Virginia, a 72 MW facility fully leased to an undisclosed hyperscale tenant. Corscale, an affiliate of Patrinely and Affinius Capital, began construction on July 29, 2024, with completion expected mid-2025. The full campus is planned for five two-story buildings totaling 2.3 million square feet and 326 MW of available power on a 130-acre site.
- Gainesville Crossing Building 2: Building 2 of the Gainesville Crossing campus
- Gainesville Crossing Building 3: Building 3 of the Gainesville Crossing campus
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.
Sources
- Gainesville Crossing: Construction Begins on Second Facility, Corscale, 29 Jul 2024. Consulted 19 Nov 2026.
- Gainesville Crossing: Construction Begins on Third Facility, Corscale, 29 Jan 2025. Consulted 19 Nov 2026.
- Gainesville Crossing: Construction Begins on Second Facility, Corscale, 29 Jul 2024. Consulted 20 Nov 2026.
- Gainesville Crossing: Construction Begins on Third Facility, Corscale, 29 Jan 2025. Consulted 20 Nov 2026.