CyrusOne DFW7, Fort Worth
- Location
- Fort Worth, Tarrant County, TX, United States. Site address: Asphalt Dr, Fort Worth, TX 76179 (no street number in the registration). See it on the map, in 3D
- Stage
- Under construction, as of January 13, 2026 (CyrusOne). CyrusOne's own January 13, 2026 press release states DFW7 is currently under construction, having broken ground in April 2025.
- Status
- Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, how big, how much
| Field | Value | Source |
|---|---|---|
| Owner | CyrusOne | |
| Type | Colocation | CyrusOne |
| Amount | Not found in the sources consulted |
Capacity
Each figure as its source states it. Megawatts of IT capacity (the power available to the computing equipment), of power supplied to the site and of generation measure different things and are never added together; a campus figure is not a building's.
| Capacity | What it measures | Scope | As of | Source |
|---|---|---|---|---|
| 200 MW, planned | Capacity, its measure not stated by the source | Whole campus | January 2026 | CyrusOne |
| About 70 MW | IT capacity (power for the computing equipment) | One phase, initial | CyrusOne |
Buildings and site
| Field | Value | Scope | Source |
|---|---|---|---|
| Floor area of one building | About 190,400 sq ft | One building | Texas Department of Licensing and Regulation |
| Stories | 1 | One building | Texas Department of Licensing and Regulation |
| Site area | 63.475 acres | Whole campus | City of Fort Worth (public parcel view of Tarrant Appraisal District data) |
| Floor area of one building | 109,000 sq ft | One building | Texas Department of Licensing and Regulation |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| CyrusOne | Owner | CyrusOne | |
| Eolian | Energy partner | CyrusOne | |
| Clune Construction Company | General contractor | States on its own site that it broke ground on the campus with CyrusOne | Clune Construction |
| JHET Architects | Design | Design firm on the state registration of DFW7, and of the DFW8 fit-out on Asphalt Road | Texas Department of Licensing and Regulation |
| C1 Fort Worth, LLC | Owner | Texas Department of Licensing and Regulation | |
| Oncor | Energy partner | CyrusOne |
Milestones
| Date | Milestone | Source |
|---|---|---|
| September 25, 2024 | Texas Department of Licensing and Regulation | |
| April 2025 | CyrusOne breaks ground on DFW7 | CyrusOne |
| April 4, 2025 | CyrusOne | |
| January 13, 2026 | CyrusOne and Eolian announce the partnership, confirming DFW7 is under construction | CyrusOne |
| February 22, 2026 | Texas Department of Licensing and Regulation | |
| July 1, 2026 | Texas Department of Licensing and Regulation |
About the campus
DFW7 is CyrusOne's first campus in Fort Worth, Texas, on Asphalt Drive, a multi-building campus with an initial IT capacity of around 70 MW. Its first building is registered with the state as a single-story data center of about 190,400 square feet with a two-story office, an estimated cost of $200 million and JHET Architects as design firm; Clune broke ground on it with CyrusOne in April 2025.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.
Sources
- CyrusOne and Eolian Partner to Enable Rapid Deployment of 200 Megawatt Data Center Campus in Fort Worth, Texas, CyrusOne, 13 Jan 2026. Consulted 19 Nov 2026.
- Data Center Dynamics: CyrusOne Breaks Ground on Fort Worth Data Center Campus in Texas, Clune Construction, 11 Apr 2025. Consulted 20 Nov 2026.
- TABS Project TABS2025001810, CyrusOne DFW7 | Shell and Upfit, Texas Department of Licensing and Regulation, 25 Sep 2024. Consulted 20 Nov 2026.
- CyrusOne Breaks Ground on New Fort Worth Data Center Campus, CyrusOne, 4 Apr 2025. Consulted 20 Nov 2026.
- TABS Project TABS2026019605, CyrusOne DFW8 TFO, Texas Department of Licensing and Regulation, 6 May 2026. Consulted 20 Nov 2026.
- Parcels_Public_Vview FeatureServer, query for TAXPIN 40453P-2-4, City of Fort Worth (public parcel view of Tarrant Appraisal District data). Consulted 20 Nov 2026.
- TABS Project TABS2026019605, CyrusOne DFW8 TFO, Texas Department of Licensing and Regulation. Consulted 20 Nov 2026.
- TABS Project TABS2025001810, CyrusOne DFW7 | Shell and Upfit, Texas Department of Licensing and Regulation. Consulted 20 Nov 2026.