Fermi America Project Matador

Location
TX, United States. See it on the map, in 3D
Stage
Under construction, as of September 30, 2026 (Fermi Inc. (U.S. Securities and Exchange Commission filing)). Site works have started (Primoris completed the excavation for six gas turbine power islands by June 2026), but Fermi's quarterly report says vertical construction of the data center awaits a definitive tenant lease.
Status
Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, how big, how much

Sourced facts of the campus
FieldValueSource
DeveloperFermi America
TypeLeased hyperscale campuses
AmountNot found in the sources consulted
Sourced facts of the campus

Capacity

Each figure as its source states it. Megawatts of IT capacity (the power available to the computing equipment), of power supplied to the site and of generation measure different things and are never added together; a campus figure is not a building's.

Capacity figures, each with what it measures
CapacityWhat it measuresScopeAs ofSource
17,000 MW, plannedOn-site power generationWhole campusSeptember 2026Fermi America
About 11,000 MWCapacity, its measure not stated by the sourceWhole campusFermi Inc. (U.S. Securities and Exchange Commission filing)
About 17,000 MWCapacity, its measure not stated by the sourceWhole campusFermi Inc. (U.S. Securities and Exchange Commission filing)
Capacity figures, each with what it measures

Buildings and site

The campus's buildings, land and plant, as their sources describe them
FieldValueScopeSource
Site area7,570 acresWhole campusFermi America
Site areaAbout 5,236 acrescampus (land held or to be held under the Texas Tech lease)Fermi Inc. (U.S. Securities and Exchange Commission filing)
Site areaAbout 8,400 acrescampus (expected aggregate)Fermi Inc. (U.S. Securities and Exchange Commission filing)
Floor areaAbout 15,000,000 sq ftcampus (planned)Fermi Inc. (U.S. Securities and Exchange Commission filing)
Site area5,769.531 acresWhole campusTexas Tech University System, Texas Tech University and Fermi SPE, LLC (copy hosted by the Amarillo Tribune; also exhibit 10.9 of Fermi Inc.'s Form S-11)
On-site generation90 SGT800 gas turbines (stacks HRSGA-1 to HRSGA-6 and HRSGB to HRSGH, 1 to 12 each) and 3 GE6B gas turbinesWhole campusTexas Commission on Environmental Quality
Cooling16 cooling towers (power plant)Whole campusTexas Commission on Environmental Quality
Generators6Whole campusTexas Commission on Environmental Quality
The campus's buildings, land and plant, as their sources describe them

Companies and their roles

Companies named by the operator, the developer, a filing or a government, each with its role
CompanyRoleNoteSource
Fermi AmericaDeveloperFermi America
Primoris Energy ServicesGeneral contractorphase one power: balance of plant for the first six Siemens SGT-800 gas turbines; Engineering and construction of the on-site gas generation, not of the data center buildings.Fermi Inc. (PR Newswire)
TSK Electronica y Electricidad USA, Corp.Designphase two power: three Siemens SGT6-5000F gas turbines; Early works and fast start engineering under a service agreement.Fermi Inc. (PR Newswire)
Hyundai Engineering & ConstructionDesignfour AP1000 nuclear units (front-end engineering design); FEED only; Fermi describes an EPC contract as a potential later step.Fermi America
Fermi America LLCDeveloperU.S. Nuclear Regulatory Commission (Federal Register)
Texas Tech University Systemlandowner (lessor)Fermi Inc. (U.S. Securities and Exchange Commission filing)
Fermi SPE, LLCtenant (ground lessee)Texas Tech University System, Texas Tech University and Fermi SPE, LLC (copy hosted by the Amarillo Tribune; also exhibit 10.9 of Fermi Inc.'s Form S-11)
National Nuclear Security Administrationcounterparty of the land exchange (NNSA Exchange Property)Fermi Inc. (U.S. Securities and Exchange Commission filing)
Fermi Equipment Holdco, LLCair permit applicant (natural gas-fired power plant)Texas Commission on Environmental Quality
Companies named by the operator, the developer, a filing or a government, each with its role

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
June 17, 2025U.S. Nuclear Regulatory Commission (Federal Register)
August 1, 2025TCEQ receives the air permit application for the campus's natural gas-fired power plantTexas Commission on Environmental Quality
December 4, 2025TCEQ public meeting on the power plant's air permit in PanhandleTexas Commission on Environmental Quality
January 30, 2026TCEQ's Executive Director serves the response to hearing requests on the power plant's air permitTexas Commission on Environmental Quality
June 30, 2026Fermi Inc. (PR Newswire)
September 2026Fermi America reported site development progress at Project Matador as of September 30, 2026.Fermi America
October 9, 2026U.S. Nuclear Regulatory Commission (Federal Register)
Dated milestones, at the precision of their source; a planned date is marked as such

About the campus

Project Matador, also called HyperGrid, is Fermi America's planned energy and data center campus in Carson County, Texas, about 17 miles northeast of Amarillo and next to the Pantex Plant, on land leased from the Texas Tech University System for 99 years. Fermi plans about 15 million square feet of AI infrastructure space powered by on-site gas, nuclear and solar generation of about 11 GW, expandable to about 17 GW. Site works have started: Primoris has excavated the foundations of the first six gas turbines, whose balance of plant it is building, while Fermi says vertical construction of the data center awaits a tenant lease. Four AP1000 reactors are under NRC review.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.