Research record, fact-checked
Flexential Denver-Parker
- Location
- Parker, CO, United States. Site address: 15255 Compark Boulevard, Parker, Douglas County, Colorado. See it on the map, in 3D
- Stage
- Under construction, as of August 2026 (Flexential (PR Newswire)). Flexential listed the 22.5 MW Denver-Parker facility among its projects under construction on August 18, 2026; the Town of Parker dates the start of construction to July 2025.
- Status
- Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, how big, how much
| Field | Value | Source |
|---|---|---|
| Owner | Flexential | |
| Type | Leased hyperscale campuses | |
| Amount | Not found in the sources consulted |
Capacity
Each figure as its source states it. Megawatts of IT capacity (the power available to the computing equipment), of power supplied to the site and of generation measure different things and are never added together; a campus figure is not a building's.
| Capacity | What it measures | Scope | As of | Source |
|---|---|---|---|---|
| 22.5 MW | Capacity, its measure not stated by the source | Whole campus | Flexential (PR Newswire) |
Buildings and site
| Field | Value | Scope | Source |
|---|---|---|---|
| Floor area | 249,000 sq ft | Whole campus | Flexential (PR Newswire) |
| Site area | More than 17 acres | Whole campus | Flexential (PR Newswire) |
| Buildings under construction | Five steel-frame colocation data halls of about 277,000 square feet in total, built in phases | Whole campus | PCL Construction |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Flexential | Owner | State of Colorado (OIT), Colorado Public Parcels | |
| CORE Electric Cooperative | Energy partner | Flexential (PR Newswire) |
General contractor: Not found in the sources consulted.
Milestones
| Date | Milestone | Source |
|---|---|---|
| May 14, 2024 | Flexential announces the Parker data center; leasing from the second half of 2024, opening set for 2026 | Flexential (PR Newswire) |
| June 2025 | Town of Parker approves the site plan | Town of Parker, Colorado |
| July 2025 | Construction begins | Town of Parker, Colorado |
| March 17, 2026 | PCL reaches structural completion | PCL Construction |
| 2027 (summer) | Completion of construction scheduled | PCL Construction |
About the campus
Flexential is building a 22.5 MW data center of 249,000 square feet on over 17 acres at 15255 Compark Boulevard in Parker, Colorado, powered by CORE Electric Cooperative. The Town of Parker approved the site plan in June 2025 and construction began in July 2025; Flexential listed the facility among its projects under construction in August 2026. PCL Construction reached structural completion on a $192 million, 22.5 MW data center on a 17-acre site southeast of Denver in March 2026, with completion scheduled for summer 2027.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.
Sources
- PCL Tops Out $192 Million AI-Ready Data Center as Denver's Digital Infrastructure Demand Accelerates, PCL Construction, 17 Mar 2026. Consulted 20 Nov 2026.
- Colorado_Public_Parcel_Composite, query on owner FLEXENTIAL, State of Colorado (OIT), Colorado Public Parcels, 21 Apr 2026. Consulted 20 Nov 2026.
- Flexential Announces FlexAnywhere Platform Expansion with New State of the Art Data Center in Denver, Flexential (PR Newswire), 14 May 2024. Consulted 20 Nov 2026.
- Frequently Asked Questions: data center, Town of Parker, Colorado. Consulted 20 Nov 2026.
- Flexential Secures $800 Million to Fund Data Center Development Across Four High-Growth Markets, Flexential (PR Newswire), 18 Aug 2026. Consulted 20 Nov 2026.