Menlo Digital MD-VA1, Herndon
- Location
- Herndon, Fairfax County, VA, United States. Site address: 13775 McLearen Road, Herndon, VA. See it on the map, in 3D
- Stage
- Under construction, as of undefined 2025 (Menlo Digital). Menlo Digital's own project page states construction commenced in the first quarter of 2025.
- Status
- Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, how big, how much
| Field | Value | Source |
|---|---|---|
| Owner | Menlo Digital | |
| Type | Colocation | Menlo Digital |
| Amount | Not found in the sources consulted |
Capacity
Each figure as its source states it. Megawatts of IT capacity (the power available to the computing equipment), of power supplied to the site and of generation measure different things and are never added together; a campus figure is not a building's.
| Capacity | What it measures | Scope | As of | Source |
|---|---|---|---|---|
| 48 MW, planned | IT capacity (power for the computing equipment) | One building | 2025 | Menlo Digital |
| 67.2 MW, planned | Power capacity of the site or its substations | One building | 2025 | Menlo Digital |
| 48 MW | IT capacity (power for the computing equipment) | One building | Menlo Digital |
Buildings and site
| Field | Value | Scope | Source |
|---|---|---|---|
| Floor area of one building | 307,498 sq ft | One building | Menlo Digital |
| Stories | 2 | One building | Menlo Digital |
| Site area | 9 acres | Whole campus | Menlo Digital |
| Substation capacity | Lincoln Park Substation, completed and energized in December 2024, delivering 67.2 MW total utility power | One building | Menlo Digital |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Menlo Digital | Owner | Menlo Digital | |
| Dominion Energy | Energy partner | Menlo Digital | |
| Dominion Energy Virginia | Energy partner | Menlo Digital | |
| Clune Construction | General contractor | Menlo Digital's topping-out release of April 23, 2025 states that Clune Construction leads the construction of MD-VA1. | Menlo Digital |
| Southland Concrete | Trade contractor | concrete; Southland's own project page: footings, slab on grade and about 150,000 sq ft of slab on metal deck for the McLearen Road data center, contractor Clune Construction. | Southland Concrete |
Milestones
| Date | Milestone | Source |
|---|---|---|
| December 2024 | Menlo Digital | |
| April 23, 2025 | Menlo Digital announces the structural topping out of MD-VA1 | Menlo Digital |
| undefined 2025 | Construction commenced on MD-VA1 Herndon. | Menlo Digital |
| undefined 2026 | Menlo Digital | |
| undefined 2027 | Menlo Digital expects final commissioning and operational readiness in the first half of 2027 | Menlo Digital |
About the campus
Menlo Digital is building a 307,498 square foot, two-story data center at 13775 McLearen Road in Herndon, Virginia, with 48 MW of critical IT load fed by 67.2 MW of total utility power from Dominion. Menlo Digital names the project MD-VA1 (Herndon) and states that construction commenced in the first quarter of 2025.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.
Sources
- MD-VA1 (Herndon) - Menlo Digital, Menlo Digital. Consulted 19 Nov 2026.
- Menlo Digital Celebrates Topping Out of MD-VA1 Data Center in Herndon, Virginia, Menlo Digital, 23 Apr 2025. Consulted 20 Nov 2026.
- Menlo Equities (project page), Southland Concrete. Consulted 20 Nov 2026.