Research record, fact-checked

Menlo Digital MD-VA1, Herndon

Location
Herndon, Fairfax County, VA, United States. Site address: 13775 McLearen Road, Herndon, VA. See it on the map, in 3D
Stage
Under construction, as of undefined 2025 (Menlo Digital). Menlo Digital's own project page states construction commenced in the first quarter of 2025.
Status
Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, how big, how much

Sourced facts of the campus
FieldValueSource
OwnerMenlo Digital
TypeColocationMenlo Digital
AmountNot found in the sources consulted
Sourced facts of the campus

Capacity

Each figure as its source states it. Megawatts of IT capacity (the power available to the computing equipment), of power supplied to the site and of generation measure different things and are never added together; a campus figure is not a building's.

Capacity figures, each with what it measures
CapacityWhat it measuresScopeAs ofSource
48 MW, plannedIT capacity (power for the computing equipment)One building2025Menlo Digital
67.2 MW, plannedPower capacity of the site or its substationsOne building2025Menlo Digital
48 MWIT capacity (power for the computing equipment)One buildingMenlo Digital
Capacity figures, each with what it measures

Buildings and site

The campus's buildings, land and plant, as their sources describe them
FieldValueScopeSource
Floor area of one building307,498 sq ftOne buildingMenlo Digital
Stories2One buildingMenlo Digital
Site area9 acresWhole campusMenlo Digital
Substation capacityLincoln Park Substation, completed and energized in December 2024, delivering 67.2 MW total utility powerOne buildingMenlo Digital
The campus's buildings, land and plant, as their sources describe them

Companies and their roles

Companies named by the operator, the developer, a filing or a government, each with its role
CompanyRoleNoteSource
Menlo DigitalOwnerMenlo Digital
Dominion EnergyEnergy partnerMenlo Digital
Dominion Energy VirginiaEnergy partnerMenlo Digital
Clune ConstructionGeneral contractorMenlo Digital's topping-out release of April 23, 2025 states that Clune Construction leads the construction of MD-VA1.Menlo Digital
Southland ConcreteTrade contractorconcrete; Southland's own project page: footings, slab on grade and about 150,000 sq ft of slab on metal deck for the McLearen Road data center, contractor Clune Construction.Southland Concrete
Companies named by the operator, the developer, a filing or a government, each with its role

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
December 2024Menlo Digital
April 23, 2025Menlo Digital announces the structural topping out of MD-VA1Menlo Digital
undefined 2025Construction commenced on MD-VA1 Herndon.Menlo Digital
undefined 2026Menlo Digital
undefined 2027Menlo Digital expects final commissioning and operational readiness in the first half of 2027Menlo Digital
Dated milestones, at the precision of their source; a planned date is marked as such

About the campus

Menlo Digital is building a 307,498 square foot, two-story data center at 13775 McLearen Road in Herndon, Virginia, with 48 MW of critical IT load fed by 67.2 MW of total utility power from Dominion. Menlo Digital names the project MD-VA1 (Herndon) and states that construction commenced in the first quarter of 2025.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.

Sources

See it on the map. How the map is made.