Research record, fact-checked
Meta El Paso Data Center
- Location
- El Paso, TX, United States. Site address: 7001 Stan Roberts Sr, El Paso, TX 79934. See it on the map, in 3D
- Stage
- Under construction, as of March 2026 (Meta). Meta confirmed the site had already broken ground in 2025 and was expanding the project in March 2026.
- Status
- Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, how big, how much
| Field | Value | Source |
|---|---|---|
| Owner | Meta | |
| Type | Hyperscale, self-built | Meta |
| Headline amount | More than US$10 billion (US dollars), as of March 2026 | Meta |
| What it covers | Announced investment, lower bound: Updated investment figure, up from a smaller initial announcement in October 2025. Not to be read as a construction cost. |
Capacity
Each figure as its source states it. Megawatts of IT capacity (the power available to the computing equipment), of power supplied to the site and of generation measure different things and are never added together; a campus figure is not a building's.
| Capacity | What it measures | Scope | As of | Source |
|---|---|---|---|---|
| 1,000 MW, planned | Capacity, its measure not stated by the source | Whole campus | March 2026 | Meta |
Investment and financing
An announced investment, a construction loan, a public incentive and a regional programme are different objects: each is listed with what it covers, never added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| More than US$10 bn | Announced investment | Whole campus | March 2026 | MetaUpdated investment figure, up from a smaller initial announcement in October 2025. |
Buildings and site
| Field | Value | Scope | Source |
|---|---|---|---|
| Cooling | null | Whole campus | Meta |
| Buildings, in all | 12 | Whole campus | Texas Department of Licensing and Regulation |
| Substation capacity | 5 owner substations | Whole campus | Texas Department of Licensing and Regulation |
| Site area | About 1,038.948 acres | Whole campus | City of El Paso |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Meta | Owner | Meta | |
| JE Dunn | General contractor | Meta | |
| Hensel Phelps | General contractor | Meta | |
| El Paso Electric | Energy partner | Meta | |
| Stantec | Design | Engineer of record for the campus in the state accessibility registration | Texas Department of Licensing and Regulation |
| Olsson | Design | Stan Roberts Sr. Avenue road improvements; Prepared the roadway improvement exhibits attached to the City's development agreement for Stan Roberts Sr. Avenue along the site | City of El Paso |
| Wurldwide LLC | Owner | City of El Paso | |
| City of El Paso | public partner | City of El Paso |
Milestones
| Date | Milestone | Source |
|---|---|---|
| December 5, 2023 | City of El Paso | |
| 2025 | Meta broke ground on the El Paso data center. | Meta |
| March 26, 2026 | Meta announced an increase of the El Paso project to 1 GW and more than 10 billion dollars. | Meta |
| April 15, 2026 | Texas Department of Licensing and Regulation |
About the campus
Meta's El Paso, Texas data center broke ground in 2025 and was expanded in a March 2026 announcement to a planned 1 gigawatt, with investment raised to more than 10 billion dollars. General contractors JE Dunn and Hensel Phelps are named, and the site uses a closed loop liquid cooling system that recirculates the same water. The project is projected to support more than 4,000 construction jobs at peak and more than 300 operational jobs.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.
Sources
- Big things are happening, El Paso! - Meta Data Centers, Meta, 26 Mar 2026. Consulted 19 Nov 2026.
- Big things are happening, El Paso! - Meta Data Centers, Meta, 26 Mar 2026. Consulted 20 Nov 2026.
- TABS project TABS2026017750, Project Seafox, Texas Department of Licensing and Regulation, 15 Apr 2026. Consulted 20 Nov 2026.
- Memo Seafox Stan Roberts Development Packet (resolution of 2023-12-05 and Development Agreement for Road Improvements), City of El Paso, 14 Jan 2025. Consulted 20 Nov 2026.
- Data Centers (Northeast El Paso META Data Center), City of El Paso. Consulted 20 Nov 2026.
- EPParcels feature service (parcels owned by WURLDWIDE LLC), City of El Paso. Consulted 20 Nov 2026.