Meta Hyperion, Richland Parish
- Location
- Holly Ridge, Richland Parish, LA, United States. See it on the map, in 3D
- Stage
- Under construction, as of July 2026 (Meta). Meta described active expansion of an already building campus, with groundbreaking reported in December 2024.
- Status
- Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, how big, how much
| Field | Value | Source |
|---|---|---|
| Joint venture partners | Meta, Blue Owl Capital (managed funds) | |
| Type | Hyperscale, self-built | Meta |
| Amount | Not found in the sources consulted |
Capacity
Each figure as its source states it. Megawatts of IT capacity (the power available to the computing equipment), of power supplied to the site and of generation measure different things and are never added together; a campus figure is not a building's.
| Capacity | What it measures | Scope | As of | Source |
|---|---|---|---|---|
| 5,000 MW, planned | Capacity, its measure not stated by the source | Whole campus | July 2026 | Meta |
Investment and financing
An announced investment, a construction loan, a public incentive and a regional programme are different objects: each is listed with what it covers, never added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| More than US$50 bn | Announced investment in the region | Whole campus | July 2026 | MetaRegional investment figure covering infrastructure, workforce training and the energy agreement, not a verified building cost. |
| About US$27 bn | Financing | Whole campus | October 2025 | MetaTotal development cost committed by the Meta and Blue Owl joint venture. |
Buildings and site
| Field | Value | Scope | Source |
|---|---|---|---|
| Cooling | closed-loop system circulating a glycol mixture through the data halls, using zero water for a majority of the year | Whole campus | Meta |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Meta | Joint venture partner | Owns 20 percent of the joint venture developing the campus. | Meta |
| Meta | Tenant | Meta leases the campus from the joint venture once construction is complete. | Meta |
| Blue Owl Capital (managed funds) | Joint venture partner | Owns 80 percent of the joint venture developing the campus. | Meta |
| DPR Construction | General contractor | Meta | |
| Turner Construction Company | General contractor | Meta | |
| Mortenson Construction | General contractor | Meta | |
| Entergy Louisiana | Energy partner | Meta | |
| City of Delhi | Energy partner | water and wastewater utility upgrades and a new industrial wastewater treatment plant | Meta |
Milestones
| Date | Milestone | Source |
|---|---|---|
| December 2024 | Groundbreaking on the Richland Parish data center. | Meta |
| October 21, 2025 | Meta and funds managed by Blue Owl Capital announced a joint venture to develop the Hyperion campus. | Meta |
| July 2026 | Meta announced an expansion of the campus to 5 GW. | Meta |
About the campus
Meta's Hyperion data center campus near Holly Ridge in Richland Parish, Louisiana broke ground in December 2024 and is being expanded to 5 GW of compute capacity as of July 2026. Meta and funds managed by Blue Owl Capital formed a joint venture in October 2025, with Blue Owl funds owning 80 percent and Meta 20 percent, committing about 27 billion dollars in development costs; Meta leases the completed campus. A further regional investment of more than 50 billion dollars was announced in July 2026, covering infrastructure and an energy agreement with Entergy Louisiana.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.
Sources
- Deepening our investment in Richland Parish, Louisiana - Meta Data Centers, Meta, Jul 2026. Consulted 19 Nov 2026.
- Meta Announces Joint Venture With Funds Managed by Blue Owl Capital to Develop Hyperion Data Center, Meta, 21 Oct 2025. Consulted 19 Nov 2026.
- Deepening our investment in Richland Parish, Louisiana, Meta. Consulted 20 Nov 2026.
- Meta Richland Parish Data Center info sheet, Meta. Consulted 20 Nov 2026.