Research record, fact-checked

Meta Jeffersonville Data Center

Location
Jeffersonville, IN, United States. See it on the map, in 3D
Stage
Under construction, as of January 2024 (Indiana Economic Development Corporation). The Indiana Economic Development Corporation's release of January 25, 2024 says Meta is starting construction that month.
Status
Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, how big, how much

Sourced facts of the campus
FieldValueSource
OwnerMeta
TypeHyperscale, self-builtMeta
Headline amountMore than US$800 million (US dollars), as of 2026Meta
What it coversAnnounced investment, lower bound. Not to be read as a construction cost.
Sourced facts of the campus

Investment and financing

An announced investment, a construction loan, a public incentive and a regional programme are different objects: each is listed with what it covers, never added to another.

Amounts, each with its kind and scope
AmountWhat it isScopeAs ofSource
More than US$800 MAnnounced investmentWhole campus2026Meta
Amounts, each with its kind and scope

Buildings and site

The campus's buildings, land and plant, as their sources describe them
FieldValueScopeSource
Floor areaNearly 700,000 sq ftWhole campusMeta
Site area619 acresWhole campusIndiana Economic Development Corporation
CoolingClosed-loop, liquid cooled system that will use zero operational waterWhole campusMeta
The campus's buildings, land and plant, as their sources describe them

Companies and their roles

Companies named by the operator, the developer, a filing or a government, each with its role
CompanyRoleNoteSource
MetaOwnerMeta
Turner Construction CompanyGeneral contractorMeta's announcement refers construction information to Turner Construction Company.Meta
Duke Energy IndianaEnergy partnerIndiana Utility Regulatory Commission
Blocke, LLCOwnerIndiana Utility Regulatory Commission
Companies named by the operator, the developer, a filing or a government, each with its role

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
2024Meta broke ground on the Jeffersonville data center.Meta
Dated milestones, at the precision of their source; a planned date is marked as such

About the campus

Meta's Jeffersonville, Indiana data center broke ground in 2024, representing an investment of more than 800 million dollars, about 1,250 construction workers at peak and around 100 operational jobs once complete. Meta publishes no capacity for the site.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.