Research record, fact-checked
Meta Tulsa Data Center
- Location
- Tulsa, OK, United States. Site address: 21304 E 11th St, Catoosa, OK 74015 (Project Anthem, Lot 1, Block 1; the plat says its addresses are for reference only). See it on the map, in 3D
- Stage
- Under construction, as of 2026 (Meta). Meta's own current site list gives 2026 as the break ground year, more recent than the April 2026 announcement, which used only future tense.
- Status
- Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, how big, how much
| Field | Value | Source |
|---|---|---|
| Owner or developer | Not found in the sources consulted | |
| Type | Hyperscale, self-built | Meta |
| Headline amount | More than US$1 billion (US dollars), as of April 2026 | Meta |
| What it covers | Announced investment, lower bound. Not to be read as a construction cost. |
Investment and financing
An announced investment, a construction loan, a public incentive and a regional programme are different objects: each is listed with what it covers, never added to another.
Buildings and site
| Field | Value | Scope | Source |
|---|---|---|---|
| Floor area | About 2,000,000 sq ft | Whole campus | Fortis Construction (project site for Meta) |
| Site area | 339.116 acres | Whole campus | Tulsa Metropolitan Area Planning Commission |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Fortis Construction | General contractor | Meta | |
| Public Service Company of Oklahoma | Energy partner | Meta | |
| Olsson, Inc. | Design | surveyor and engineer named on the final plat of Project Anthem, and applicant for its preliminary plat extension | Tulsa Metropolitan Area Planning Commission |
| Atmoss, LLC | landowner | a Delaware limited liability company, owner of record of the Project Anthem land (10300 Greenbriar Place, Oklahoma City) | Tulsa Metropolitan Area Planning Commission |
Milestones
| Date | Milestone | Source |
|---|---|---|
| August 7, 2024 | Preliminary plat of Project Anthem approved | Tulsa Metropolitan Area Planning Commission |
| 2026 | Meta's site list gives 2026 as the break ground year. | Meta |
| April 21, 2026 | Meta announced the Tulsa, Oklahoma data center. | Meta |
| May 20, 2026 | The Tulsa Metropolitan Area Planning Commission approves the accelerated release of a building permit for Project Anthem before the final plat is filed, and extends the preliminary plat to August 7, 2027 | Tulsa Metropolitan Area Planning Commission |
About the campus
Meta's Tulsa data center, in East Tulsa, Oklahoma, was announced in April 2026 as an investment of more than $1 billion. The project's construction site describes a roughly 2 million-square-foot campus being built for Meta by Fortis Construction with local and national trade partners, with more than 1,000 construction workers expected on site at peak.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.
Sources
- United States - Meta Data Centers, Meta. Consulted 19 Nov 2026.
- Hello, Tulsa! - Meta Data Centers, Meta, 21 Apr 2026. Consulted 19 Nov 2026.
- Tulsa Data Center, Fortis Construction (project site for Meta). Consulted 20 Nov 2026.
- Hello, Tulsa! - Meta Data Centers, Meta, 21 Apr 2026. Consulted 20 Nov 2026.
- Hello, Tulsa! - Meta Data Centers, Meta, 21 Apr 2026. Consulted 20 Nov 2026.
- Meta Breaks Ground on New $1 Billion Data Center in Tulsa, PartnerTulsa (Tulsa Authority for Economic Opportunity), 21 Apr 2026. Consulted 20 Nov 2026.
- Project Anthem: Accelerated Release of a Building Permit (staff report with final plat, hearing of May 20, 2026), Tulsa Metropolitan Area Planning Commission, 20 May 2026. Consulted 20 Nov 2026.
- Minutes, Meeting No. 2961, Wednesday, May 20, 2026, Tulsa Metropolitan Area Planning Commission, 20 May 2026. Consulted 20 Nov 2026.