Microsoft Alviso datacenter
- Location
- San Jose, CA, United States. Site address: 1657 Alviso-Milpitas Road, San Jose, California. See it on the map, in 3D
- Stage
- Site preparation under way, as of 2026 (Microsoft). Microsoft's own update describes a multi-phase effort to prepare the land, with construction beginning in fall 2025 focused on earthmoving and soil remediation, and site preparation expected to finish by summer 2026; no vertical building construction or MW figure is stated.
- Status
- Research record, fact-checked: compiled from the primary sources below (the operator, the developer, filings, governments and utilities), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, how big, how much
| Field | Value | Source |
|---|---|---|
| Owner | Microsoft Corporation | |
| Type | Hyperscale, self-built | Microsoft |
| Amount | Not found in the sources consulted |
Buildings and site
| Field | Value | Scope | Source |
|---|---|---|---|
| Buildings, in all | 2 | Whole campus | California Energy Commission |
| Floor area | About 396,914 sq ft | Whole campus | California Energy Commission |
| Stories | 1 | One building | California Energy Commission |
| Site area | 64.5 acres | Whole campus | California Office of Land Use and Climate Innovation (CEQAnet) |
| Generators | 224 | Whole campus | California Energy Commission |
| Substation capacity | Onsite 115 kV substation with two 115 kV supply lines | Whole campus | California Energy Commission |
| On-site generation | Backup generators with a generating capacity not exceeding 100 MW | Whole campus | California Office of Land Use and Climate Innovation (CEQAnet) |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| HITT Contracting Inc. | General contractor | Microsoft | |
| Microsoft Corporation | Owner | California Energy Commission |
Milestones
| Date | Milestone | Source |
|---|---|---|
| July 14, 2022 | California Energy Commission adopts the Small Power Plant Exemption order (docket 19-SPPE-04) | California Energy Commission |
| 2025 | Construction began, focused on earthmoving and soil remediation. | Microsoft |
| 2026 (planned) | Site preparation expected to be completed by summer 2026. | Microsoft |
About the campus
Microsoft is preparing its Alviso site at 1657 Alviso-Milpitas Road in San Jose, California (parcel 015-31-054, 64.5 acres) for a datacenter campus. The California Energy Commission's 2022 exemption describes two single-story data center buildings of about 396,914 gross square feet, an onsite 115 kV substation and 224 renewable natural gas backup generators. Microsoft's own update says land preparation began in fall 2025, with HITT Contracting Inc. as general contractor.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the campus's land, its buildings with their mapped heights, its substations and the power lines around it, with the published figures on its card. What no map or source gives (a hall's height where none is tagged, the rooftop plant, the generator yards) is drawn as typical equipment and listed as illustrative under the model. Open the campus in 3D.
Sources
- Alviso datacenter construction update, Microsoft. Consulted 19 Nov 2026.
- San Jose Data Center (19-SPPE-04), California Energy Commission. Consulted 20 Nov 2026.
- San Jose Data Center, Draft EIR (SCH 2021020002), California Office of Land Use and Climate Innovation (CEQAnet), 23 Dec 2021. Consulted 20 Nov 2026.